Project overview

Auralis The Twins is a MahaRERA Registered Project bearing MahaRERA Registration Number P51700009177. Auralis The Twins is located at F.P. No- 136 B. This is a Ongoing being developed by Deep Homes & Constructions Llp.

Auralis The Twins has 2.5 BHK & 3.5 BHK Apartments with carpet areas ranging from 1244 to 1008 Sq.ft. Carpet. The Project has total 682 of which 85 are currently available for sale.

Auralis The Twins is being developed on a total land area of 90636 Sq.ft. out of which 14140 Sq.ft. i.e 16% is reserved for recreational purposes. Auralis The Twins has 3 Wings / Towers Rental,Tower-1,Tower-2

ProjectDeveloperLocationPossession
New Kirtikar ProposedChaturthi Developers40060201-07-2025 00:00:00
Shanti KunjShreyas Enterprises616,617,61831-12-2017 00:00:00
AtlantisAshwamedh Builders & DevelopersT P Scheme No 1, F P No 32030-06-2021 00:00:00
PadmalaxmiKedar Bhikaji Bapat945 946 947 And 94831-03-2018 00:00:00
Ashar 16 Wing C Phase IiiMs Ashar RealtorsPlot No D-2 Midc Wagle Estate Panchpakhadi Thane 31-12-2018 00:00:00
Ashar 16 Wing E Phase IMs Ashar RealtorsPlot No D2 Midc Wagle Estate Thane 31-12-2018 00:00:00
Project Details
  • Project:
    Auralis The Twins
  • Location:
  • F.P. No- 136 B
  • Const. Stage:
    Ongoing
  • Possession:
    01 Mar 2019
Developer Details

  • Developer:
    Deep Homes & Constructions Llp
  • Phone:
  • Address:
  • Na
Project RERA Details
MAHA REARA No: P51700009177
Project Type Residential / Group Housing
RERA Project Status Ongoing
Architect Mr.Anil Jagwani
Funding Bank HDFC BANK
Proposed Possession 01 Mar 2019
Revised Possession 01 Mar 2019
Extended Possession 31 Jan 2021
Litigations No Litigations
Last Modified 19 Nov 2020
Last Retrived 26 Jul 2025
Auralis The Twins QR Code
Auralis The Twins
MahaRERA - P51700009177
Apartment Details & Configuration
TypeArea
SINGLE ROOM15.21 Sq.mts. ( 164 Sq.ft. )
2 BHK70.18 Sq.mts. ( 755 Sq.ft. )
3 BHK103.85 Sq.mts. ( 1118 Sq.ft. )
2.5 BHK93.64 Sq.mts. ( 1008 Sq.ft. )
3.5 BHK115.54 Sq.mts. ( 1244 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Auralis The Twinslast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Will Be Done Prior To Oc
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station90% completed
90% Complete
Will Be Done Prior To Oc
Energy management45% completed
45% Complete
Will Be Done Prior To Oc
Fire Protection And Fire Safety Requirements60% completed
60% Complete
Will Be Done Prior To Oc
Landscaping & Tree Planting45% completed
45% Complete
Will Be Done Prior To Oc
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)95% completed
95% Complete
Will Be Done Prior To Oc
Solid Waste Management And Disposal65% completed
65% Complete
Will Be Done Prior To Oc
Storm Water Drains95% completed
95% Complete
Will Be Done Prior To Oc
Street Lighting
Will Be Done Prior To Oc
Treatment And Disposal Of Sewage And Sullage Water85% completed
85% Complete
Will Be Done Prior To Oc
Water Conservation, Rain water Harvesting85% completed
85% Complete
Will Be Done Prior To Oc
Water Supply
Will Be Done Prior To Oc
Buildings / Wings in Auralis The Twins
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Auralis The Twins by Deep Homes & Constructions Llplast updated on 26 Jul 2025 as per information obtained from MARA RERA.

90636 Sq. ft.

Project Area

14140 Sq. ft.

Recreational Open Space

Total 3

Wings / Towers in Project

Apartments Statistics

682 apartments in total
Total
682
Booked
597
Available
85

Saleable Area Statistics (Sq. ft.)

297619 Total
Total
297619
Booked
205310
Available
92308
Total 682 apartments in project. 597 apartments booked. 87% apartments booked.
Total 297619 Sq.ft. saleable area. 205310 saleable area booked.
69% area booked.

Rental

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
RentalJan 190020101000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
SINGLE ROOM15.21 Sq.mts. ( 164 Sq.ft. )468
468 Booked100% Booked
100% Booked
468 total apartments / 468 apartments booked. 100% apartments booked.
Work Description in Building RentalCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
Completed 100% done
100% Booked
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Tower-1

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Tower-1Jan 20193211110221
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK70.18 Sq.mts. ( 755 Sq.ft. )51
39 Booked76% Booked
76% Booked
3 BHK103.85 Sq.mts. ( 1118 Sq.ft. )56
41 Booked73% Booked
73% Booked
107 total apartments / 80 apartments booked. 74% apartments booked.
Work Description in Building Tower-1Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
Completed 100% done
100% Booked
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Tower-2

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Tower-2Jan 20192811110220
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2.5 BHK93.64 Sq.mts. ( 1008 Sq.ft. )56
32 Booked57% Booked
57% Booked
3.5 BHK115.54 Sq.mts. ( 1244 Sq.ft. )51
17 Booked33% Booked
33% Booked
107 total apartments / 49 apartments booked. 45% apartments booked.
Work Description in Building Tower-2Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
Completed 100% done
100% Booked
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Deep Homes & Constructions Llp
for Project
Auralis The Twins
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation