Project overview
Aryaman Marina is a MahaRERA Registered Project bearing MahaRERA Registration Number P51800012786. Aryaman Marina is located at Mumbai Suburban, 400061. This is a New Project being developed by Aryaman Infratech India Pvt Ltd.
Aryaman Marina has 1 BHK, 1RK, 2 BHK & 3 BHK Apartments with carpet areas ranging from 170 to 948 Sq.ft. Carpet. The Project has total 66 of which 38 are currently available for sale.
Aryaman Marina is being developed on a total land area of 10386 Sq.ft. Aryaman Marina has 1 Wings / Towers V-Parijat Chsl
| Project | Developer | Location | Possession |
-
Project:
Aryaman Marina
-
Location:
-
Mumbai Suburban, 400061
-
Const. Stage:
New Project
-
Possession:
30 Jun 2022
-
Developer:
Aryaman Infratech India Pvt Ltd
-
Phone:
-
Address:
-
223, Laxmi Plaza, Laxmi Ind Estate, Sab Tv Lane, Andheri West, 400053
| MAHA REARA No: |
P51800012786 |
| Project Type |
Mixed (Plots & Buildings) |
| RERA Project Status |
New Project |
| Funding Bank |
KOTAK MAHINDRA BANK |
| Proposed Possession |
30 Jun 2022 |
| Revised Possession |
|
| Extended Possession |
|
| Litigations |
No Litigations |
| Last Modified |
20 Nov 2018 |
| Last Retrived |
28 Jul 2025 |
Aryaman Marina QR Code
Aryaman Marina
MahaRERA - P51800012786
| Type | Area |
| 1 BHK | 31.04 Sq.mts. ( 334 Sq.ft. ) |
| 1 BHK | 34.2 Sq.mts. ( 368 Sq.ft. ) |
| 1 BHK | 36.15 Sq.mts. ( 389 Sq.ft. ) |
| 1 BHK | 37.36 Sq.mts. ( 402 Sq.ft. ) |
| 1RK | 15.79 Sq.mts. ( 170 Sq.ft. ) |
| 2 BHK | 46.93 Sq.mts. ( 505 Sq.ft. ) |
| 2 BHK | 54.36 Sq.mts. ( 585 Sq.ft. ) |
| 3 BHK | 64.21 Sq.mts. ( 691 Sq.ft. ) |
| 3 BHK | 88.1 Sq.mts. ( 948 Sq.ft. ) |
Facilities & Amenities
Facilities, Amenities & Common areas details of Aryaman Marinalast updated on 28 Jul 2025 as per information obtained from MARA RERA.
| Project Facilities & Amenities |
Available |
Details |
Aggregate area of recreational Open Space
|
|
Na |
|
|
|
Na |
Electrical Meter Room, Sub-Station, Receiving Station
|
|
Yet To Start |
|
|
|
Na |
Fire Protection And Fire Safety
Requirements
|
|
Yet To Start |
Landscaping & Tree Planting
|
|
Na |
|
|
|
Na |
Sewerage (Chamber, Lines, Septic Tank , STP)
|
|
Yet To Start |
Solid Waste Management And Disposal
|
|
Na |
|
|
|
Yet To Start |
|
|
|
Na |
Treatment And Disposal Of Sewage And Sullage Water
|
|
Na |
Water Conservation, Rain water Harvesting
|
|
Yet To Start |
|
|
|
Yet To Start |
Buildings / Wings in Aryaman Marina
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Aryaman Marina by Aryaman Infratech India Pvt Ltdlast updated on 28 Jul 2025 as per information obtained from MARA RERA.
Apartments Statistics
66
apartments in total
Saleable Area Statistics (Sq. ft.)
26710
Total
Total 66 apartments in project. 28 apartments booked. 42% apartments booked.
Total 26710 Sq.ft. saleable area. 13953 saleable area booked.
52% area booked.
| Wing | Proposed Date of Completion | Number of Slabs | Plinth | Basement's | Stilts | Podium's | Open Parkings | Closed Parkings |
| V-Parijat Chsl | Jan 1900 | 18 | 1 | 0 | 1 | 0 | 0 | 68 |
| Apartment Type | Carpet Area | Number of Apartments | Booked Apartments |
| 1 BHK | 31.04 Sq.mts. ( 334 Sq.ft. ) | 32 | |
| 1 BHK | 34.2 Sq.mts. ( 368 Sq.ft. ) | 15 | |
| 1 BHK | 36.15 Sq.mts. ( 389 Sq.ft. ) | 1 | |
| 1 BHK | 37.36 Sq.mts. ( 402 Sq.ft. ) | 1 | |
| 1RK | 15.79 Sq.mts. ( 170 Sq.ft. ) | 1 | |
| 2 BHK | 46.93 Sq.mts. ( 505 Sq.ft. ) | 9 | |
| 2 BHK | 54.36 Sq.mts. ( 585 Sq.ft. ) | 1 | |
| 3 BHK | 64.21 Sq.mts. ( 691 Sq.ft. ) | 5 | |
| 3 BHK | 88.1 Sq.mts. ( 948 Sq.ft. ) | 1 | |
66 total apartments / 28 apartments booked. 42% apartments booked. |
| Work Description in Building V-Parijat Chsl | Completion |
| Excavation | |
| Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate | |
| Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises | |
| Overall Percentage of Completion of the work done For the entire Building /Wing | |
| Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises | |
| Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. | |
| Stilt Floor | |
| The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing | |
| X number of Basement(s) and Plinth | |
| X number of Podiums | |
| X number of Slabs of Super Structure | |
Channel Partners Registered by Developer
Aryaman Infratech India Pvt Ltd
for Project
Aryaman Marina
last updated on
28 Jul 2025 as per information obtained from MARA RERA.
| Name |
Company |
Location |
Mobile |
Designation |