Project overview

Arkk Avenue is a MahaRERA Registered Project bearing MahaRERA Registration Number P51800003639. Arkk Avenue is located at Wrong Registration Done In Mumbai, Its Correct Address Is Belatgaon Nasik. This is a Ongoing being developed by Arkk Builders And Developers.

Arkk Avenue has 1 BHK Apartments with carpet areas ranging from 250 to 411 Sq.ft. Carpet. The Project has total 85 of which 37 are currently available for sale.

Arkk Avenue is being developed on a total land area of 45747 Sq.ft. out of which 4575 Sq.ft. i.e 10% is reserved for recreational purposes. Arkk Avenue has 2 Wings / Towers Building A,Building B

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Arkk Avenue
  • Location:
  • Wrong Registration Done In Mumbai, Its Correct Address Is Belatgaon Nasik
  • Const. Stage:
    Ongoing
  • Possession:
    31 Dec 2019
Developer Details

  • Developer:
    Arkk Builders And Developers
  • Phone:
  • Address:
  • Karmabhoomi Chsl
Project RERA Details
MAHA REARA No: P51800003639
Project Type Residential / Group Housing
RERA Project Status Ongoing
Architect Rekha Lohar
Funding Bank YES BANK
Proposed Possession 31 Dec 2019
Revised Possession 31 Dec 2019
Extended Possession
Litigations No Litigations
Last Modified 04 Oct 2018
Last Retrived 26 Jul 2025
Arkk Avenue QR Code
Arkk Avenue
MahaRERA - P51800003639
Apartment Details & Configuration
TypeArea
1 BHK25.23 Sq.mts. ( 272 Sq.ft. )
1 BHK31.55 Sq.mts. ( 340 Sq.ft. )
1 BHK32.51 Sq.mts. ( 350 Sq.ft. )
1 BHK32.64 Sq.mts. ( 351 Sq.ft. )
1 BHK35.99 Sq.mts. ( 387 Sq.ft. )
1 BHK36.12 Sq.mts. ( 389 Sq.ft. )
1 BHK36.17 Sq.mts. ( 389 Sq.ft. )
1 BHK36.22 Sq.mts. ( 390 Sq.ft. )
1 BHK38.15 Sq.mts. ( 411 Sq.ft. )
1 BHK23.23 Sq.mts. ( 250 Sq.ft. )
1 BHK34.29 Sq.mts. ( 369 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Arkk Avenuelast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space80% completed
80% Complete
Will Be Done At Finishing Stage
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station
Na
Energy management
Na
Fire Protection And Fire Safety Requirements
Na
Landscaping & Tree Planting60% completed
60% Complete
Plantation Will Be Done At Finishing Stage
Open Parking100% completed
95% Complete
Yes
Sewerage (Chamber, Lines, Septic Tank , STP)95% completed
95% Complete
Connection And Pipping To Main Line Done
Solid Waste Management And Disposal
Na
Storm Water Drains
Na
Street Lighting90% completed
90% Complete
Will Be Done At Finishing Stage
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting
Na
Water Supply80% completed
80% Complete
Borewell Has Been Dugged
Buildings / Wings in Arkk Avenue
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Arkk Avenue by Arkk Builders And Developerslast updated on 26 Jul 2025 as per information obtained from MARA RERA.

45747 Sq. ft.

Project Area

4575 Sq. ft.

Recreational Open Space

Total 2

Wings / Towers in Project

Apartments Statistics

85 apartments in total
Total
85
Booked
48
Available
37

Saleable Area Statistics (Sq. ft.)

30658 Total
Total
30658
Booked
17286
Available
13372
Total 85 apartments in project. 48 apartments booked. 56% apartments booked.
Total 30658 Sq.ft. saleable area. 17286 saleable area booked.
56% area booked.

Building A

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building ADec 20195100000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK25.23 Sq.mts. ( 272 Sq.ft. )2
2 Booked100% Booked
100% Booked
1 BHK31.55 Sq.mts. ( 340 Sq.ft. )4
4 Booked100% Booked
100% Booked
1 BHK32.51 Sq.mts. ( 350 Sq.ft. )4
4 Booked100% Booked
100% Booked
1 BHK32.64 Sq.mts. ( 351 Sq.ft. )16
13 Booked81% Booked
81% Booked
1 BHK35.99 Sq.mts. ( 387 Sq.ft. )5
4 Booked80% Booked
80% Booked
1 BHK36.12 Sq.mts. ( 389 Sq.ft. )4
3 Booked75% Booked
75% Booked
1 BHK36.17 Sq.mts. ( 389 Sq.ft. )3
2 Booked66% Booked
66% Booked
1 BHK36.22 Sq.mts. ( 390 Sq.ft. )4
3 Booked75% Booked
75% Booked
1 BHK38.15 Sq.mts. ( 411 Sq.ft. )1
1 Booked100% Booked
100% Booked
43 total apartments / 36 apartments booked. 83% apartments booked.
Work Description in Building Building ACompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress80% done
80% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Building B

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building BDec 20195100000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK23.23 Sq.mts. ( 250 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK25.23 Sq.mts. ( 272 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK31.55 Sq.mts. ( 340 Sq.ft. )4
2 Booked50% Booked
50% Booked
1 BHK32.51 Sq.mts. ( 350 Sq.ft. )3
1 Booked33% Booked
33% Booked
1 BHK32.64 Sq.mts. ( 351 Sq.ft. )16
4 Booked25% Booked
25% Booked
1 BHK34.29 Sq.mts. ( 369 Sq.ft. )4
2 Booked50% Booked
50% Booked
1 BHK35.99 Sq.mts. ( 387 Sq.ft. )4
None Booked0% Booked
0% Booked
1 BHK36.17 Sq.mts. ( 389 Sq.ft. )4
None Booked0% Booked
0% Booked
1 BHK36.22 Sq.mts. ( 390 Sq.ft. )4
3 Booked75% Booked
75% Booked
1 BHK38.15 Sq.mts. ( 411 Sq.ft. )1
None Booked0% Booked
0% Booked
42 total apartments / 12 apartments booked. 28% apartments booked.
Work Description in Building Building BCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Arkk Builders And Developers
for Project
Arkk Avenue
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation