Arkade Rare is a MahaRERA Registered Project bearing MahaRERA Registration Number P51800077307. Arkade Rare is located at 403B ,403B/1 . This is a New being developed by Arkade Developers Limited.
Arkade Rare has 2 BHK Apartments with carpet areas ranging from 524 to 626 Sq.ft. Carpet. The Project has total 226 of which 222 are currently available for sale.
Arkade Rare is being developed on a total land area of 128817 Sq.ft. out of which 28898 Sq.ft. i.e 22% is reserved for recreational purposes. Arkade Rare has 7 Wings / Towers Wing A,Wing B,Wing C,Wing D,Wing E,Wing F,Wing G
| Project | Developer | Location | Possession |
-
Project:
Arkade Rare
-
Location:
-
403B ,403B/1
-
Const. Stage:
New
-
Possession:
31 Dec 2028
| MAHA REARA No: |
P51800077307 |
| Project Type |
Residential / Group Housing |
| RERA Project Status |
New |
| Architect |
Kalakruti Architects & Plannerss |
| Funding Bank |
HDFC BANK |
| Proposed Possession |
31 Dec 2028 |
| Revised Possession |
|
| Extended Possession |
|
| Litigations |
No Litigations |
| Last Modified |
18 Nov 2024 |
| Last Retrived |
26 Jul 2025 |
Arkade Rare QR Code
Arkade Rare
MahaRERA - P51800077307
| Type | Area |
| 2 BHK | 48.59 Sq.mts. ( 523 Sq.ft. ) |
| 2 BHK | 54.56 Sq.mts. ( 587 Sq.ft. ) |
| 2 BHK | 58.15 Sq.mts. ( 626 Sq.ft. ) |
| 2 BHK | 58.27 Sq.mts. ( 627 Sq.ft. ) |
| 2 BHK | 48.7 Sq.mts. ( 524 Sq.ft. ) |
| 2 BHK | 48.81 Sq.mts. ( 525 Sq.ft. ) |
| 2 BHK | 54.36 Sq.mts. ( 585 Sq.ft. ) |
| 2 BHK | 54.43 Sq.mts. ( 586 Sq.ft. ) |
| 2 BHK | 63.1 Sq.mts. ( 679 Sq.ft. ) |
| 2 BHK | 63.34 Sq.mts. ( 682 Sq.ft. ) |
| 2 BHK | 67.53 Sq.mts. ( 727 Sq.ft. ) |
| 2 BHK | 74.57 Sq.mts. ( 803 Sq.ft. ) |
| 3 BHK | 80.34 Sq.mts. ( 865 Sq.ft. ) |
| 3 BHK | 94.22 Sq.mts. ( 1014 Sq.ft. ) |
| 3 BHK | 94.36 Sq.mts. ( 1016 Sq.ft. ) |
| 2 BHK | 62.88 Sq.mts. ( 677 Sq.ft. ) |
| 2 BHK | 63.14 Sq.mts. ( 680 Sq.ft. ) |
| 2 BHK | 63.44 Sq.mts. ( 683 Sq.ft. ) |
| 3 BHK | 80.22 Sq.mts. ( 863 Sq.ft. ) |
| 2 BHK | 54.49 Sq.mts. ( 587 Sq.ft. ) |
| 2 BHK | 54.54 Sq.mts. ( 587 Sq.ft. ) |
| 2 BHK | 48.67 Sq.mts. ( 524 Sq.ft. ) |
Facilities & Amenities
Facilities, Amenities & Common areas details of Arkade Rarelast updated on 26 Jul 2025 as per information obtained from MARA RERA.
| Project Facilities & Amenities |
Available |
Details |
Aggregate area of recreational Open Space
|
|
Na |
|
|
|
Na |
|
|
|
Na |
Electrical Meter Room, Sub-Station, Receiving Station
|
|
Na |
|
|
|
Na |
Fire Protection And Fire Safety
Requirements
|
|
Na |
Fitness Center or Society office
|
|
Na |
Landscaping & Tree Planting
|
|
Na |
|
|
|
Na |
Sewerage (Chamber, Lines, Septic Tank , STP)
|
|
Na |
Solid Waste Management And Disposal40% completed
|
|
Na |
|
|
|
Na |
|
|
|
Na |
|
|
|
Na |
Treatment And Disposal Of Sewage And Sullage Water
|
|
Only Disposal |
Water Conservation, Rain water Harvesting
|
|
Na |
|
|
|
Na |
Buildings / Wings in Arkade Rare
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Arkade Rare by Arkade Developers Limitedlast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Apartments Statistics
226
apartments in total
Saleable Area Statistics (Sq. ft.)
144654
Total
Total 226 apartments in project. 4 apartments booked. 1% apartments booked.
Total 144654 Sq.ft. saleable area. 3216 saleable area booked.
2% area booked.
| Wing | Proposed Date of Completion | Number of Slabs | Plinth | Basement's | Stilts | Podium's | Open Parkings | Closed Parkings |
| Wing A | Dec 2028 | 7 | 1 | 0 | 0 | 5 | 0 | 0 |
| Apartment Type | Carpet Area | Number of Apartments | Booked Apartments |
| 2 BHK | 48.59 Sq.mts. ( 523 Sq.ft. ) | 2 | |
| 2 BHK | 54.56 Sq.mts. ( 587 Sq.ft. ) | 2 | |
| 2 BHK | 58.15 Sq.mts. ( 626 Sq.ft. ) | 2 | |
| 2 BHK | 58.27 Sq.mts. ( 627 Sq.ft. ) | 1 | |
7 total apartments / 0 apartments booked. 0% apartments booked. |
| Work Description in Building Wing A | Completion |
| Excavation | |
| Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate | |
| Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises | |
| Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises | |
| Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. | |
| Stilt Floor | |
| The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing | |
| X number of Basement(s) and Plinth | |
| X number of Podiums | |
| X number of Slabs of Super Structure | |
| Wing | Proposed Date of Completion | Number of Slabs | Plinth | Basement's | Stilts | Podium's | Open Parkings | Closed Parkings |
| Wing B | Dec 2028 | 7 | 1 | 0 | 0 | 5 | 0 | 98 |
| Apartment Type | Carpet Area | Number of Apartments | Booked Apartments |
| 2 BHK | 48.7 Sq.mts. ( 524 Sq.ft. ) | 2 | |
| 2 BHK | 48.81 Sq.mts. ( 525 Sq.ft. ) | 2 | |
| 2 BHK | 54.36 Sq.mts. ( 585 Sq.ft. ) | 1 | |
| 2 BHK | 54.43 Sq.mts. ( 586 Sq.ft. ) | 2 | |
7 total apartments / 0 apartments booked. 0% apartments booked. |
| Work Description in Building Wing B | Completion |
| Excavation | |
| Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate | |
| Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises | |
| Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises | |
| Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. | |
| Stilt Floor | |
| The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing | |
| X number of Basement(s) and Plinth | |
| X number of Podiums | |
| X number of Slabs of Super Structure | |
| Wing | Proposed Date of Completion | Number of Slabs | Plinth | Basement's | Stilts | Podium's | Open Parkings | Closed Parkings |
| Wing C | Dec 2028 | 7 | 1 | 0 | 0 | 5 | 0 | 97 |
| Apartment Type | Carpet Area | Number of Apartments | Booked Apartments |
| 2 BHK | 63.1 Sq.mts. ( 679 Sq.ft. ) | 2 | |
| 2 BHK | 63.34 Sq.mts. ( 682 Sq.ft. ) | 2 | |
| 2 BHK | 67.53 Sq.mts. ( 727 Sq.ft. ) | 2 | |
| 2 BHK | 74.57 Sq.mts. ( 803 Sq.ft. ) | 2 | |
| 3 BHK | 80.34 Sq.mts. ( 865 Sq.ft. ) | 1 | |
9 total apartments / 0 apartments booked. 0% apartments booked. |
| Work Description in Building Wing C | Completion |
| Excavation | |
| Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate | |
| Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises | |
| Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises | |
| Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. | |
| Stilt Floor | |
| The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing | |
| X number of Basement(s) and Plinth | |
| X number of Podiums | |
| X number of Slabs of Super Structure | |
| Wing | Proposed Date of Completion | Number of Slabs | Plinth | Basement's | Stilts | Podium's | Open Parkings | Closed Parkings |
| Wing D | Dec 2028 | 7 | 1 | 0 | 0 | 5 | 0 | 97 |
| Apartment Type | Carpet Area | Number of Apartments | Booked Apartments |
| 3 BHK | 94.22 Sq.mts. ( 1014 Sq.ft. ) | 1 | |
| 3 BHK | 94.36 Sq.mts. ( 1016 Sq.ft. ) | 1 | |
2 total apartments / 0 apartments booked. 0% apartments booked. |
| Work Description in Building Wing D | Completion |
| Excavation | |
| Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate | |
| Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises | |
| Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises | |
| Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. | |
| Stilt Floor | |
| The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing | |
| X number of Basement(s) and Plinth | |
| X number of Podiums | |
| X number of Slabs of Super Structure | |
| Wing | Proposed Date of Completion | Number of Slabs | Plinth | Basement's | Stilts | Podium's | Open Parkings | Closed Parkings |
| Wing E | Dec 2028 | 21 | 1 | 0 | 0 | 5 | 0 | 97 |
| Apartment Type | Carpet Area | Number of Apartments | Booked Apartments |
| 2 BHK | 62.88 Sq.mts. ( 677 Sq.ft. ) | 15 | |
| 2 BHK | 63.14 Sq.mts. ( 680 Sq.ft. ) | 15 | |
| 2 BHK | 63.44 Sq.mts. ( 683 Sq.ft. ) | 16 | |
| 2.5 BHK | 74.57 Sq.mts. ( 803 Sq.ft. ) | 16 | |
| 3 BHK | 80.22 Sq.mts. ( 863 Sq.ft. ) | 15 | |
77 total apartments / 3 apartments booked. 3% apartments booked. |
| Work Description in Building Wing E | Completion |
| Excavation | |
| Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate | |
| Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises | |
| Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises | |
| Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. | |
| Stilt Floor | |
| The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing | |
| X number of Basement(s) and Plinth | |
| X number of Podiums | |
| X number of Slabs of Super Structure | |
| Wing | Proposed Date of Completion | Number of Slabs | Plinth | Basement's | Stilts | Podium's | Open Parkings | Closed Parkings |
| Wing F | Dec 2028 | 21 | 1 | 0 | 0 | 5 | 0 | 97 |
| Apartment Type | Carpet Area | Number of Apartments | Booked Apartments |
| 2 BHK | 48.7 Sq.mts. ( 524 Sq.ft. ) | 16 | |
| 2 BHK | 48.81 Sq.mts. ( 525 Sq.ft. ) | 16 | |
| 2 BHK | 54.49 Sq.mts. ( 587 Sq.ft. ) | 14 | |
| 2 BHK | 54.54 Sq.mts. ( 587 Sq.ft. ) | 16 | |
62 total apartments / 0 apartments booked. 0% apartments booked. |
| Work Description in Building Wing F | Completion |
| Excavation | |
| Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate | |
| Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises | |
| Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises | |
| Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. | |
| Stilt Floor | |
| The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing | |
| X number of Basement(s) and Plinth | |
| X number of Podiums | |
| X number of Slabs of Super Structure | |
| Wing | Proposed Date of Completion | Number of Slabs | Plinth | Basement's | Stilts | Podium's | Open Parkings | Closed Parkings |
| Wing G | Dec 2028 | 21 | 1 | 0 | 0 | 5 | 0 | 97 |
| Apartment Type | Carpet Area | Number of Apartments | Booked Apartments |
| 2 BHK | 48.67 Sq.mts. ( 524 Sq.ft. ) | 16 | |
| 2 BHK | 54.56 Sq.mts. ( 587 Sq.ft. ) | 16 | |
| 2 BHK | 58.15 Sq.mts. ( 626 Sq.ft. ) | 30 | |
62 total apartments / 1 apartments booked. 1% apartments booked. |
| Work Description in Building Wing G | Completion |
| Excavation | |
| Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate | |
| Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises | |
| Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises | |
| Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. | |
| Stilt Floor | |
| The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing | |
| X number of Basement(s) and Plinth | |
| X number of Podiums | |
| X number of Slabs of Super Structure | |
Channel Partners Registered by Developer
Arkade Developers Limited
for Project
Arkade Rare
last updated on
26 Jul 2025 as per information obtained from MARA RERA.
| Name |
Company |
Location |
Mobile |
Designation |