Project overview

Arkade Rare is a MahaRERA Registered Project bearing MahaRERA Registration Number P51800077307. Arkade Rare is located at 403B ,403B/1 . This is a New being developed by Arkade Developers Limited.

Arkade Rare has 2 BHK Apartments with carpet areas ranging from 524 to 626 Sq.ft. Carpet. The Project has total 226 of which 222 are currently available for sale.

Arkade Rare is being developed on a total land area of 128817 Sq.ft. out of which 28898 Sq.ft. i.e 22% is reserved for recreational purposes. Arkade Rare has 7 Wings / Towers Wing A,Wing B,Wing C,Wing D,Wing E,Wing F,Wing G

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Arkade Rare
  • Location:
  • 403B ,403B/1
  • Const. Stage:
    New
  • Possession:
    31 Dec 2028
Developer Details

  • Developer:
    Arkade Developers Limited
  • Phone:
  • Address:
  • Arkade House
Project RERA Details
MAHA REARA No: P51800077307
Project Type Residential / Group Housing
RERA Project Status New
Architect Kalakruti Architects & Plannerss
Funding Bank HDFC BANK
Proposed Possession 31 Dec 2028
Revised Possession
Extended Possession
Litigations No Litigations
Last Modified 18 Nov 2024
Last Retrived 26 Jul 2025
Arkade Rare QR Code
Arkade Rare
MahaRERA - P51800077307
Apartment Details & Configuration
TypeArea
2 BHK48.59 Sq.mts. ( 523 Sq.ft. )
2 BHK54.56 Sq.mts. ( 587 Sq.ft. )
2 BHK58.15 Sq.mts. ( 626 Sq.ft. )
2 BHK58.27 Sq.mts. ( 627 Sq.ft. )
2 BHK48.7 Sq.mts. ( 524 Sq.ft. )
2 BHK48.81 Sq.mts. ( 525 Sq.ft. )
2 BHK54.36 Sq.mts. ( 585 Sq.ft. )
2 BHK54.43 Sq.mts. ( 586 Sq.ft. )
2 BHK63.1 Sq.mts. ( 679 Sq.ft. )
2 BHK63.34 Sq.mts. ( 682 Sq.ft. )
2 BHK67.53 Sq.mts. ( 727 Sq.ft. )
2 BHK74.57 Sq.mts. ( 803 Sq.ft. )
3 BHK80.34 Sq.mts. ( 865 Sq.ft. )
3 BHK94.22 Sq.mts. ( 1014 Sq.ft. )
3 BHK94.36 Sq.mts. ( 1016 Sq.ft. )
2 BHK62.88 Sq.mts. ( 677 Sq.ft. )
2 BHK63.14 Sq.mts. ( 680 Sq.ft. )
2 BHK63.44 Sq.mts. ( 683 Sq.ft. )
3 BHK80.22 Sq.mts. ( 863 Sq.ft. )
2 BHK54.49 Sq.mts. ( 587 Sq.ft. )
2 BHK54.54 Sq.mts. ( 587 Sq.ft. )
2 BHK48.67 Sq.mts. ( 524 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Arkade Rarelast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
Car Parking System
Na
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station
Na
Energy management
Na
Fire Protection And Fire Safety Requirements
Na
Fitness Center or Society office
Na
Landscaping & Tree Planting
Na
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)
Na
Solid Waste Management And Disposal40% completed
40% Complete
Na
Storm Water Drains
Na
Street Lighting
Na
Swimming Pool
Na
Treatment And Disposal Of Sewage And Sullage Water
Only Disposal
Water Conservation, Rain water Harvesting
Na
Water Supply
Na
Buildings / Wings in Arkade Rare
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Arkade Rare by Arkade Developers Limitedlast updated on 26 Jul 2025 as per information obtained from MARA RERA.

128817 Sq. ft.

Project Area

28898 Sq. ft.

Recreational Open Space

Total 7

Wings / Towers in Project

Apartments Statistics

226 apartments in total
Total
226
Booked
4
Available
222

Saleable Area Statistics (Sq. ft.)

144654 Total
Total
144654
Booked
3216
Available
141438
Total 226 apartments in project. 4 apartments booked. 1% apartments booked.
Total 144654 Sq.ft. saleable area. 3216 saleable area booked.
2% area booked.

Wing A

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing ADec 20287100500
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK48.59 Sq.mts. ( 523 Sq.ft. )2
None Booked0% Booked
0% Booked
2 BHK54.56 Sq.mts. ( 587 Sq.ft. )2
None Booked0% Booked
0% Booked
2 BHK58.15 Sq.mts. ( 626 Sq.ft. )2
None Booked0% Booked
0% Booked
2 BHK58.27 Sq.mts. ( 627 Sq.ft. )1
None Booked0% Booked
0% Booked
7 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Wing ACompletion
Excavation
work-in-progress90% done
90% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
X number of Podiums
X number of Slabs of Super Structure

Wing B

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing BDec 202871005098
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK48.7 Sq.mts. ( 524 Sq.ft. )2
None Booked0% Booked
0% Booked
2 BHK48.81 Sq.mts. ( 525 Sq.ft. )2
None Booked0% Booked
0% Booked
2 BHK54.36 Sq.mts. ( 585 Sq.ft. )1
None Booked0% Booked
0% Booked
2 BHK54.43 Sq.mts. ( 586 Sq.ft. )2
None Booked0% Booked
0% Booked
7 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Wing BCompletion
Excavation
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
X number of Podiums
X number of Slabs of Super Structure

Wing C

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing CDec 202871005097
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK63.1 Sq.mts. ( 679 Sq.ft. )2
None Booked0% Booked
0% Booked
2 BHK63.34 Sq.mts. ( 682 Sq.ft. )2
None Booked0% Booked
0% Booked
2 BHK67.53 Sq.mts. ( 727 Sq.ft. )2
None Booked0% Booked
0% Booked
2 BHK74.57 Sq.mts. ( 803 Sq.ft. )2
None Booked0% Booked
0% Booked
3 BHK80.34 Sq.mts. ( 865 Sq.ft. )1
None Booked0% Booked
0% Booked
9 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Wing CCompletion
Excavation
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
X number of Podiums
X number of Slabs of Super Structure

Wing D

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing DDec 202871005097
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
3 BHK94.22 Sq.mts. ( 1014 Sq.ft. )1
None Booked0% Booked
0% Booked
3 BHK94.36 Sq.mts. ( 1016 Sq.ft. )1
None Booked0% Booked
0% Booked
2 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Wing DCompletion
Excavation
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
work-in-progress90% done
90% Booked
X number of Podiums
X number of Slabs of Super Structure

Wing E

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing EDec 2028211005097
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK62.88 Sq.mts. ( 677 Sq.ft. )15
None Booked0% Booked
0% Booked
2 BHK63.14 Sq.mts. ( 680 Sq.ft. )15
None Booked0% Booked
0% Booked
2 BHK63.44 Sq.mts. ( 683 Sq.ft. )16
None Booked0% Booked
0% Booked
2.5 BHK74.57 Sq.mts. ( 803 Sq.ft. )16
None Booked0% Booked
0% Booked
3 BHK80.22 Sq.mts. ( 863 Sq.ft. )15
3 Booked20% Booked
20% Booked
77 total apartments / 3 apartments booked. 3% apartments booked.
Work Description in Building Wing ECompletion
Excavation
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
work-in-progress90% done
90% Booked
X number of Podiums
X number of Slabs of Super Structure

Wing F

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing FDec 2028211005097
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK48.7 Sq.mts. ( 524 Sq.ft. )16
None Booked0% Booked
0% Booked
2 BHK48.81 Sq.mts. ( 525 Sq.ft. )16
None Booked0% Booked
0% Booked
2 BHK54.49 Sq.mts. ( 587 Sq.ft. )14
None Booked0% Booked
0% Booked
2 BHK54.54 Sq.mts. ( 587 Sq.ft. )16
None Booked0% Booked
0% Booked
62 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Wing FCompletion
Excavation
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
work-in-progress90% done
90% Booked
X number of Podiums
X number of Slabs of Super Structure

Wing G

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing GDec 2028211005097
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK48.67 Sq.mts. ( 524 Sq.ft. )16
None Booked0% Booked
0% Booked
2 BHK54.56 Sq.mts. ( 587 Sq.ft. )16
None Booked0% Booked
0% Booked
2 BHK58.15 Sq.mts. ( 626 Sq.ft. )30
62 total apartments / 1 apartments booked. 1% apartments booked.
Work Description in Building Wing GCompletion
Excavation
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
work-in-progress20% done
20% Booked
X number of Slabs of Super Structure
Channel Partners
Channel Partners Registered by Developer
Arkade Developers Limited
for Project
Arkade Rare
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation