Project overview

Arihant Residency is a MahaRERA Registered Project bearing MahaRERA Registration Number P99000032477. Arihant Residency is located at 63/6, 63/8, 63/29. This is a New being developed by Aditya Deepak Karnawat.

Arihant Residency has 1RK Apartments with carpet areas ranging from 0 to 0 Sq.ft. Carpet. The Project has total 28 of which 12 are currently available for sale.

Arihant Residency is being developed on a total land area of 15048 Sq.ft. Arihant Residency has 4 Wings / Towers A - Wing,B - Wing,C - Wing,Not Applicable

ProjectDeveloperLocationPossession
RudranshPadmavati Developers401404, Palghar31-12-2017 00:00:00
Astavinayak ApartmentM/s RAJ RIDDHI ASSOCIATESS N 27 H N 2 Plot No 531-05-2018 00:00:00
OM SAIMAYFAIR ENTERPRISES62/228-07-2019 00:00:00
Ambrosia building 3Pawan Abhimanyu Singh403/1 And 403/1B31-12-2018 00:00:00
Arron Complex Phase 1Arron Builders and DevelopersS.No 35330-01-2018 00:00:00
VIVA VISHNUPURAM- AMRUTVIVA HOMES PRIVATE LIMITED133/230-06-2021 00:00:00
Nilemore Ganesh Co-Op Hsg Soc LtdShree Builders And Land DevelopersS No 125 &Amp; 128 Plot No 21 Behind Shani Mandir Laxmi Ben Chedha Marg, Palghar31-12-2027 00:00:00
GULMOHAR AVENUEHIMANSHU SHAM TENDULKARCts No 77430-04-2025 00:00:00
SHRI SAI DARSHANOM SAI BUILDERS AND DEVELOEPRS27/1/A30-12-2021 00:00:00
SACHIN APARTMENTSACHIN CIVIL CONTRACTOR79/2, 79/106-11-2019 00:00:00
GODAI APARTMENTBALWANT ATMARAM PATILPlot No. 12, S. No. 50/330-03-2023 00:00:00
SAI KIRANSUGANDHI BUILDERS & DEVELOPERS PRIVATE LIMITEDSurvey No 6, H.No 1031-12-2024 00:00:00
AARAMBHTHE PARK REALTYPlot No. 3/ Survey No. 56/1/5/A/315-12-2023 00:00:00
MADHAV VATIKA - VIR M N H DEVELOPERS LLPSurvey No-25/2/A Plot No - 2, 3, 7 & 831-07-2026 00:00:00
SAMRUDDHI APARTMENTNITANT SATISH PATILS. No. 2312 Pt. Plot No. 6430-03-2023 00:00:00
RUBY ENCLAVES R CONSTRUCTIONSPlot No 33 Survey No 23/3 Village Navali30-10-2020 00:00:00
SAUBHAGYA APARTMENTMANDA PRAKASH PATILPlot No. 45, S. No. 50/530-03-2023 00:00:00
NETRA GAJANAND BUILDING NO. THREE TYPE ARandhir Bhavnath SinghSurvey Number- 52/1/C/1, 52/1/B/2, 52/1/C/231-12-2026 00:00:00
ARIHANT ARSHIYA PHASE IIIARIHANT SUPERSTRUCTURES LIMITEDSurvey No. 20/1, 20/2 Plus 3, 21/1, 21/2A, 21/2B, 22/1, 22/2, 22/3, 22/430-09-2020 00:00:00
MITHILA PALACEKAMAL RAMVINOD JHA40120330-06-2026 00:00:00
SAI ENCLAVE BUILDING NO.2M/S. RADHEYA CONSTRUCTION COMPANYS.No.317 H.No.3, 6C,8, 931-12-2029 00:00:00
Acciano BiancaM/s. Ideal Enterprises41/1, 2, 3P, 4, 5, 631-12-2025 00:00:00
BASERA GARDENSKYLAND STRUCTURESSurvey No 34 Hissa No 531-12-2027 00:00:00
AMBROSIA 13THDC NAGRI LLP831/19/B31-03-2026 00:00:00
DECENT LIFE SPACE 2ADINATH ASSOCIATES70/A/1 51/A/531-12-2026 00:00:00
Kotak KunjPradeep KotakPalghar30-04-2019 00:00:00
CLASSIQUESHRUSHTI DEVELOPERSPlot No 3 And 430-12-2022 00:00:00
Riddhivinayak ApartmentJai Bajarang ConstructionGut No-27/2/A, Plot No-2430-11-2019 00:00:00
PARAMOUNT ENCLAVE BUILDING NO 6KAVITA REALTY1023/7 (Old 1023/1+2/2418-12-2025 00:00:00
MYZO SUITESMYZO INFRA PRIVATE LIMITED49/131-12-2027 00:00:00
Shree Maruti Co-op. Housing Society Ltd.RAMESHWARAM ENTERPRISESAchole Road30-03-2025 00:00:00
Empire Estate 2Javid Yasin KojarSurvey No.8 Hissa No.1, Survey No.183 Hissa No.431-12-2025 00:00:00
CRYSTAL PARK WING CSAI CRYSTAL BUILDRES AND DEVELOPERS40/B/61/331-12-2024 00:00:00
PARADISE PHASE 2DIVEKAR CONSTRUCTION2366,2367,236831-08-2024 00:00:00
INDRAPRASTH GOVINDSAI INFRAGut No-104/1/C, 104/3 And 95/3/231-12-2028 00:00:00
NAKODA VILUROVivek Patrick Pimenta233/A/1/2/231-12-2024 00:00:00
MATRU DEEPKUVER JAGMAL KHODBHAYAS.No.380,Plot No.3106-03-2026 00:00:00
MALHAR LIFESPACESMALHAR LIFESPACES224/828-11-2021 00:00:00
VASANT VILLAVASANT CONSTRUCTION99/1 Pt.30-09-2020 00:00:00
Nirman HeightNirman Builder & DeveloperSurvey No-91/2/A, Plot No-2830-09-2022 00:00:00
DHARTI-4DHARTIDHAN DEVELOPERS411/D/1 (Old 411/C/1)31-12-2026 00:00:00
KINJAL COMPLEX IIKINJAL ENTERPRISESPalghar31-12-2025 00:00:00
FIA ORIONNIMISH LAXMICHAND PASADSurvey No 79/2 156/2 Plot No 430-12-2021 00:00:00
BHOOMI NIWASBHOOMI CORPARATIONSurvey No 36,37/130-06-2019 00:00:00
SHRI BALAJI NIWASBHOOMI ENTERPRISESSurvey No.37,Hissa No.6,Plot No.231-12-2019 00:00:00
Flower AlleySalauddin ShaikhPalghar, 40150131-12-2018 00:00:00
Golden HeightsGolden Group And DevelopersPalghar, 40140431-12-2019 00:00:00
CELLO DECENT HOMES PHASE 2DECENT HOMES14,15/1/1 A Paiki 31-07-2019 00:00:00
JK HERITAGEVAILANKANNI REALTORS83 H.No.1 Pt31-12-2027 00:00:00
Jivdani ComplexMeena Dalvi421303, Vada, Palghar01-12-2024 00:00:00
AARUNYASWAGAT DEVELOPERSSurvey No-7/1/A31-03-2025 00:00:00
HORIZON HEIGHTSGROWTH HOUSINGSurvey No-65,Survey.No-276, Hissa No.-4,Survey No-276, Hissa No.-5, Survey No-280 Hissa No.-2, Survey No-27631-12-2028 00:00:00
JAY AMBE APARTMENTSAI INFRASurvey No 205/24, Plot No. 2431-12-2027 00:00:00
MADHAV VATIKA-IXHARESH THAKKAR HUFSurvey No. 25/1 ,Plot No. 79 , 8030-06-2027 00:00:00
FIA PARADISENIMISH LAXMICHAND PASADSurvey No 125 Plot No 5, Old Plot No 1330-12-2022 00:00:00
SIDDHARTH AVENUE C WINGHUM DEVELOPERS PRIVATE LIMITED20030-03-2022 00:00:00
OMKARAANH NIRMANPlot No 12 13 And 14 Survey No 828 3P30-12-2020 00:00:00
Nisarg Shrushti Phase-2Arvel RealtorsSurvey No - 97/215-11-2026 00:00:00
KANCHAN IMPERIALNOVEL BUILDCON84/1/3/A30-06-2023 00:00:00
DANDEKARS GANDHAKOSHJAYANT VISHNU DANDEKAR101 4 A 101 D30-09-2025 00:00:00
Shree Gajanand Apartment Building No 5 Type B1Shree Gajanand RealtyPalghar28-02-2025 00:00:00
Shree Balaji HeavenShree Balaji HomesChiller Road31-03-2026 00:00:00
NAVKAR HEIGHTSNAVKAR HEIGHTSS.No.19/4A (Cts No.489 Part)31-12-2024 00:00:00
Seven HeightsAditi Builders And Developers40150131-12-2025 00:00:00
Sukh Shanti ApartmentSaiMirra RealtyS. No. 20931-12-2024 00:00:00
HAYAAT RELIABLEM M LIFESTYLE15531-12-2028 00:00:00
SHREE SIDDHIVINAYAK RESIDENCYR S ENTERPRISES60/130-06-2025 00:00:00
Lake ViewRishabh EnterprisesSurvey No. 17/2, 17/531-12-2025 00:00:00
OAKWOOD PHASE-2JEEVDANI BUILDERS & DEVELOPERS LLPPlot No 146, 147 Of Sector 7 Of Sri Prastha Layour31-05-2025 00:00:00
SAI SANKALP BUILDING NO 01 WING A AND BSAI SANKALP ENTERPRISESPalghar31-12-2025 00:00:00
ASHTAVINAYAK BUILDERS AND DEVELOPERSASHTAVINAYAK BUILDERS AND DEVELOPERS14431-12-2025 00:00:00
NEW MUKTI CO-OPERATIVE HOUSING SOCIETY LIMITEDSAI SIDDHI BUILDERS AND DEVELOPERSS. No. 81 & 82 Plot No 5131-12-2025 00:00:00
OAKWOOD PHASE-1JEEVDANI BUILDERS & DEVELOPERS LLPPlot No 146, 147 Of Sector-Vii Of Sri Prastha Layout31-05-2022 00:00:00
FIA CONSTRUCTION COMPANY A/C FIA ENIGMANIMISH LAXMICHAND PASADPlot No 62,S.No.82631-12-2024 00:00:00
Shree Balaji AvenuePrabha Realty40150130-06-2024 00:00:00
C VINAYAK INDUSTRIAL ESTATEVINAYAK CONSTRUCTIONCn No/Cts No-130Pt Survey No/Plot No 1 And 231-12-2018 00:00:00
KUSUM PARKSUNSHINE BUILDERSPlot No 141 Survey No 82630-12-2021 00:00:00
PRITHVI SRISHTIPRITHVI ANAND REALTYSurvey No 74/1Pt30-06-2018 00:00:00
KRISH MANSIONKBAFNA INFRAA PRIVATE LIMITED1032324-12-2024 00:00:00
ROMAN RESIDENCYShantee HousingS No 68 H No 131-12-2027 00:00:00
PARVATI HOMESKRISHNA BUILDER & DEVELOPERSPalghar, 40140431-12-2025 00:00:00
HEAVENSKeyators1599A, 1599B, 1601A, 1601B, 160231-12-2028 00:00:00
ROYAL DREAMS PRIDEALBERT AUGSTIN RODRIGUESS No 150 Hissa No 1/1 And 1/201-06-2024 00:00:00
KAUSHIK RESIDENCYMUSKAAN DEVELOPERSGaonthan Pardi No.1831-12-2027 00:00:00
Empire Estate 1Javed Yasin Kojar24 1 1 And 24 1 231-12-2023 00:00:00
GURUJI RESIDENCYNAVKAR DEVELOPERSPlot No 17 Survey No 71/5/70/331-12-2023 00:00:00
BEGINNING HEIGHTSANAND MOHAN DUBEY155231-12-2029 00:00:00
KANCHAN AVENUE AND KANCHAN RATNANOVEL ESTATES.No. 100/2 Cts No -151931-12-2029 00:00:00
KANCHAN TRADE CENTRENOVEL REALTORSS.No.83/B/1 And 96/B/2/331-12-2029 00:00:00
KANCHAN BUSINESS HUB AND KANCHAN HEIGHTSNOVEL BUILD-CONS.No.19030-04-2030 00:00:00
ZENITH HEIGHTSARVEL ZENITH REALTORSS. No. -86/1/231-03-2030 00:00:00
PHILIA SQUAREKBAFNA INFRAA PRIVATE LIMITEDS. No. 99/2/A/1/203-01-2028 00:00:00
OSIAN ROYALEEskcays Estatess Private Limited15/1/B19-07-2026 00:00:00
HIMGIRI CO.OP HOUSING SOCIETY LTDKALPATARU VENTURES187 H No 431-12-2028 00:00:00
GIRIRAJ DARSHANKISHORE S. DUBECts No 370,37125-03-2019 00:00:00
S S Dream CitySanjay Yadav401404, Palghar31-07-2022 00:00:00
Raj IconNeelshrushti Builders & DevelopersSurvey No-99/A/202-09-2019 00:00:00
SKY VISTAM/s. Divine ConstructionCts No.2646/B/4/3, & Cts No.2647, S. No.1P/431-12-2026 00:00:00
KASHI ARCADEVEDIT ENTERPRISESS.No.55 A H No 1 (Pt),S.No. 63,S.No.68H No 1 And 231-10-2024 00:00:00
LIBERTY INDUSTRIAL PARKGURUNANAK DEVELOPERS132/A 132/B 224/230-06-2025 00:00:00
Shiv DarshanM/s. Prathmesh Builders & DevelopersSurvey No. 23/1/A Plot No. 1001-04-2022 00:00:00
POONAM PARK VIEW PHASE IIPOONAM HOMEMAKER LLPS No. 5, 5B30-06-2021 00:00:00
CELLO DECENT HOMES PHASE 3DECENT HOMES14,15/1/1A Paiki, 15 B Plot No 330-12-2022 00:00:00
Rudra SaiRudra Sai AppartmentGut No-222 Pt31-12-2018 00:00:00
Maple Terraces Building No. B-11Messrs. Axis Dwellings LLPSurvey No. 12/131-03-2018 00:00:00
SHANTI VISTASHAH REALTY AND INFRA52 And 54 Of Village Khaira31-07-2018 00:00:00
INDRAPRASTH COMPLEXSWASTIK DEVELOPERSPlot No 18,19,20,21,2231-01-2019 00:00:00
TULIP RESIDENCYBRRIGHT REALTORS11/1P/0331-03-2018 00:00:00
SNEH KUNJ APARTMENTS.K.DEVELOPERSS.No. 114/6Bpt31-12-2017 00:00:00
AMIN COMPLEXGAJARYA ASSOCIATESS No 169 Pt Gut No 39/2 Plot No 231-03-2022 00:00:00
SYMPHONY HEIGHTSKreate Space LLPSurvey No-155 Pt. Cts No-87831-03-2025 00:00:00
PARAMOUNT ENCLAVE PHASE -1KAVITA REALTY HOUSING LLP1023/9 And 1023/9/130-11-2024 00:00:00
VIVANTSUNSHINE DEVELOPERS122/1/1/1A31-12-2025 00:00:00
SOLITAIRE HEIGHTAFFAK ARIF MOTIWALAGut No 66 Hissa No 131-12-2025 00:00:00
MADHAV VATIKA VIIIR M N H DEVELOPERS LLPS.No. 23/3/A/13 , 23/1/A/43 , 23/1/A/4431-12-2025 00:00:00
Gopikisan Patil Complex Bldg No 1Sumatinath EnterprisesNaigaon Station Road, Palghar31-12-2027 00:00:00
SHREE GANESH HERITAGEHIMANSHU SHAM TENDULKAR831 A31-10-2024 00:00:00
GOLDEN OAKGREENSPACE CONSTRUCTION PVT LTDSurvey No 9 Hissa No 131-12-2024 00:00:00
SHREE BALAJI PRIDE BUILDING NO 01SHREE BALAJI AFFORDABLE HOMESPalghar East31-12-2027 00:00:00
Rameshwar ArcadeLevel Up Realtors70/1/131-12-2024 00:00:00
Arihant ResidencyAditya Deepak Karnawat63/6, 63/8, 63/2930-04-2024 00:00:00
FIA CONSTRUCTION COMPANY FIA ORION - GRANDENIMISH LAXMICHAND PASADPlot No 1731-12-2025 00:00:00
JB ENTERPRISESRAJU BHERULAL JAINS No 38/1/331-12-2025 00:00:00
SANYUKTA REALTORSKHATUSHYAM REALTYS. No. 15A, H. No. 231-10-2028 00:00:00
SHREE KURLAI COMPLEXSHREE MANGALMURTI ASSOCIATESNear Kurlai Temple30-06-2025 00:00:00
Kotak RoyaleKotak Sons94/1 125/101-12-2020 00:00:00
FIA REGENCY ANIMISH LAXMICHAND PASADSurvey No 923 Plot No 330-12-2022 00:00:00
DATTAGANGAGanesh LAnd Developers and Construction Private LimitedS N83/4 P Plot No115-02-2021 00:00:00
GALAXY ABHINANDANAAKAR DEVELOPERSurvey No. 45/2/A/6 Cts No. 465/B30-11-2023 00:00:00
BACHRAJ LEGEND WING ABCBACHRAJ DEVELOPERSPlot B / 24 B/3, B/401-12-2027 00:00:00
BACHRAJ LEGEND WING DBACHRAJ DEVELOPERSPlot B / 24 B/3, B/401-12-2027 00:00:00
RADHA KRISHNA APARTMENTG/P/No./831-12-2026 00:00:00
DURVANKUR HEIGHTSHIMANSHU SHAM TENDULKAR244,245,246,247,248,249,250,251,252,25331-05-2028 00:00:00
GOLDEN BLISSMAHALAXMI HOMESG No 227/Pt31-12-2027 00:00:00
RUBY GOLDSHAKEEL ABDULREHMAN MUNSHIRAZA KHANSurvey No.380 Plot No.60 And Plot No.7028-02-2026 00:00:00
JEEVIKA HEIGHTSFia Developers Pvt. Ltd.Survey No. 101/1/B31-12-2026 00:00:00
DECENT EVOQDECENT EVOQS.No. 90/1/6/A, 90/1/6/B Cts No.- 1957/A, 1957/B31-12-2026 00:00:00
SAMAIRA RESIDENCYAV CRYSTAL SPACESurvey No 7531-12-2026 00:00:00
KT ASPIRE INDUSTRIAL HUBKT 3D SCAPESS.No 95B H.No 1,31-03-2023 00:00:00
YASHWANT COUNTYVIMAL INFRA235/4 And 235/11/131-12-2025 00:00:00
DREAM AURACLEMENT REGENCY DEVELOPERS48/15+1330-12-2025 00:00:00
OSTWAL PALACESHREE OSTWAL BUILDERS LTDSurvey No.67 Hissa No.7331-03-2027 00:00:00
Anant AakashPravinkumar Lalchand JainSurvey No 2/530-10-2020 00:00:00
KESHAV SRUSHTISRUSHTI REALTORS377/0130-12-2022 00:00:00
DANDEKAR RESIDENCYJAYANT VISHNU DANDEKAR101/4/A Or 101/4 Pt And 101/D30-03-2022 00:00:00
Riddhi Siddhi GreensRiddhi Siddhi RealtorsSurvey No 134, Plot No 131-12-2018 00:00:00
OCEAN PEARLOCEAN DEVELOPERS162/1/1Pt31-12-2018 00:00:00
SPRING FIELDM/S. SHYAM SAGAR DEVELOPERSGut No 70, Plot No 1 To 1130-12-2023 00:00:00
OSTWAL WOODSSHREE OSTWAL BUILDERS LTDSurvey No 148/B/1/130-12-2024 00:00:00
Vakratund HeightsShivanjali InfrastructureSr. No. 77/3/230-12-2022 00:00:00
DECENT LIFE SPACE 1ADINATH ASSOCIATES70/A/1, 51/A/530-12-2023 00:00:00
FIA EKDANTAMYSTIQUE DEVELOPERSPlot No 7, S No 143 3 Part 343 B1, 343 B230-12-2023 00:00:00
WONDER RESIDENCY C WING BUILDING NO 2NEW GALAXY ENTERPRISESSn 256 Hn3,830-03-2022 00:00:00
RAJYOG HEIGHTSRAJYOG BUILDERS & DEVELOPERSPlot No.2 ,S.No. 101A, Hissa No.3/231-12-2026 00:00:00
Sai Riddhi ComplexSwami Neem Karoli HomesPalghar31-12-2025 00:00:00
Imperial Paradise Building No.10Aditi Builders &Amp; DevelopersBetegaon Village31-12-2025 00:00:00
YASHODA HERITAGEOM NITYANAND CONSTRUCTION67(19)31-12-2025 00:00:00
CRESCENTPOINT-IIK K CONSTRUCTION106/1/1 , 106/7, 107/231-12-2022 00:00:00
Ostwal Empire M1 And M2Samta EnterprisesBoisar, Opp. Gurudwara30-12-2024 00:00:00
NEMI SOLITAIRENEMI REALTORS826 Plot No.430-03-2023 00:00:00
RAJYOG ELANZAARAJYOG INFRAPlot 3 And 1631-12-2018 00:00:00
PARMAR JEWEL RESIDENCYPARMARBUILDTECH20 H No 4,21 Hno 1/2A, 1/2B, 1/2C 1/2D31-07-2020 00:00:00
Riddhi Siddhi ParkRiddhi Siddhi BuildersGut No-212 Plot No. 3 To 1431-03-2019 00:00:00
Maple Terraces Building No. A-15Messrs. Axis Dwellings LLPSurvey No 12/131-03-2018 00:00:00
I.K. GROUPI K GROUP7/E20-12-2018 00:00:00
Apex WildernestApex CreatorsSurvey No. 28, 29, 30.31-03-2018 00:00:00
Shraddha MansionSaroj Kirtikumar Bafna216/19/A30-06-2022 00:00:00
Aadinath Complex Bldg No 1 and 2Chamunda DevelopersCts No 19031-12-2018 00:00:00
YASHAPARTMENTKWINGBHAVESH SHANTILAL PAREKH82/601-12-2019 00:00:00
SAI BHAKTI COMPLEXSAI BHAKTI DEVELOPERSS No 1023 H No 1 And 2/1930-12-2023 00:00:00
SAI AARTISAI THIYA DEVELOPERSSurvey No-125 Pt. Final Plot No-1631-12-2026 00:00:00
MADHU NEEM BUILDING NO. ONE TYPE AMadhavi Constructions92/A/3/10 And 92/A/3/1230-09-2028 00:00:00
KIARANIWAS LIFESPACES LLPS.No. - 128/2/A And 128/2/2B30-06-2029 00:00:00
Sadaram 9National Life Space31-12-2027 00:00:00
VASTUSRUSHTIVASTUSRUSHTI REALTORS LLPPlot No 2 Survey No 91/2A Village Navali West Palghar31-12-2018 00:00:00
Project Details
  • Project:
    Arihant Residency
  • Location:
  • 63/6, 63/8, 63/29
  • Const. Stage:
    New
  • Possession:
    30 Apr 2024
Developer Details

  • Developer:
    Aditya Deepak Karnawat
  • Phone:
  • Address:
  • Deepak Karnawat
Project RERA Details
MAHA REARA No: P99000032477
Project Type Others
RERA Project Status New
Architect Narendra Sharma
Funding Bank HDFC BANK
Proposed Possession 30 Apr 2024
Revised Possession
Extended Possession
Litigations No Litigations
Last Modified 06 May 2024
Last Retrived 14 Feb 2026
Arihant Residency QR Code
Arihant Residency
MahaRERA - P99000032477
Apartment Details & Configuration
TypeArea
Comm and Resi543.32 Sq.mts. ( 5848 Sq.ft. )
1 BHK35.64 Sq.mts. ( 384 Sq.ft. )
1 BHK40.36 Sq.mts. ( 434 Sq.ft. )
1 BHK41.27 Sq.mts. ( 444 Sq.ft. )
2 BHK63.03 Sq.mts. ( 678 Sq.ft. )
3 BHK79.09 Sq.mts. ( 851 Sq.ft. )
3 BHK84.01 Sq.mts. ( 904 Sq.ft. )
1RK115.92 Sq.mts. ( 1248 Sq.ft. )
1RK0 Sq.mts. ( 0 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Arihant Residencylast updated on 14 Feb 2026 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station100% completed
95% Complete
Na
Energy management
Na
Fire Protection And Fire Safety Requirements
Na
Landscaping & Tree Planting
Na
Open Parking100% completed
95% Complete
Na
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
95% Complete
Na
Solid Waste Management And Disposal100% completed
95% Complete
Na
Storm Water Drains
Na
Street Lighting70% completed
70% Complete
Na
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting100% completed
95% Complete
Na
Water Supply100% completed
95% Complete
Na
Buildings / Wings in Arihant Residency
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Arihant Residency by Aditya Deepak Karnawatlast updated on 14 Feb 2026 as per information obtained from MARA RERA.

15048 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 4

Wings / Towers in Project

Apartments Statistics

28 apartments in total
Total
28
Booked
16
Available
12

Saleable Area Statistics (Sq. ft.)

83110 Total
Total
83110
Booked
52785
Available
30325
Total 28 apartments in project. 16 apartments booked. 57% apartments booked.
Total 83110 Sq.ft. saleable area. 52785 saleable area booked.
64% area booked.

A - Wing

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
A - WingApr 20243100000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
Comm and Resi543.32 Sq.mts. ( 5848 Sq.ft. )12
8 Booked66% Booked
66% Booked
12 total apartments / 8 apartments booked. 66% apartments booked.
Work Description in Building A - WingCompletion
Basement (if any)
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress95% done
95% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress95% done
95% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Plinth
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

B - Wing

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
B - WingApr 20244101006
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK35.64 Sq.mts. ( 384 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK40.36 Sq.mts. ( 434 Sq.ft. )4
3 Booked75% Booked
75% Booked
1 BHK41.27 Sq.mts. ( 444 Sq.ft. )2
1 Booked50% Booked
50% Booked
2 BHK63.03 Sq.mts. ( 678 Sq.ft. )1
None Booked0% Booked
0% Booked
3 BHK79.09 Sq.mts. ( 851 Sq.ft. )1
1 Booked100% Booked
100% Booked
3 BHK84.01 Sq.mts. ( 904 Sq.ft. )1
1 Booked100% Booked
100% Booked
10 total apartments / 6 apartments booked. 60% apartments booked.
Work Description in Building B - WingCompletion
Basement (if any)
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress95% done
95% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress70% done
70% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress70% done
70% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Plinth
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
work-in-progress80% done
80% Booked
Sanitary Fittings within the flats / premises
work-in-progress80% done
80% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress95% done
95% Booked
X number of Basement(s) and Plinth
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

C - Wing

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
C - WingApr 20243100000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1RK115.92 Sq.mts. ( 1248 Sq.ft. )6
2 Booked33% Booked
33% Booked
6 total apartments / 2 apartments booked. 33% apartments booked.
Work Description in Building C - WingCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress80% done
80% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Not Applicable

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Not ApplicableApr 20240000000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1RK0 Sq.mts. ( 0 Sq.ft. )0
None Booked0% Booked
0% Booked
Work Description in Building Not ApplicableCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress90% done
90% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress90% done
90% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress90% done
90% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress90% done
90% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress90% done
90% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress82% done
82% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
work-in-progress50% done
50% Booked
Sanitary Fittings within the flats / premises
work-in-progress50% done
50% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress90% done
90% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Aditya Deepak Karnawat
for Project
Arihant Residency
last updated on 14 Feb 2026 as per information obtained from MARA RERA.
Name Company Location Mobile Designation