Project overview

Arihant Anaika Phase Ii is a MahaRERA Registered Project bearing MahaRERA Registration Number P52000014892. Arihant Anaika Phase Ii is located at 35/04 And 36/01. This is a New being developed by Arihant Vatika Realty Private Limited.

Arihant Anaika Phase Ii has 1 BHK, 1 BHK TYPE 1, 2 BHK & 2 BHK TYPE 1 Apartments with carpet areas ranging from 344 to 542 Sq.ft. Carpet. The Project has total 267 of which 0 are currently available for sale.

Arihant Anaika Phase Ii is being developed on a total land area of 119089 Sq.ft. out of which 11497 Sq.ft. i.e 10% is reserved for recreational purposes. Arihant Anaika Phase Ii has 5 Wings / Towers C,D,G,H,I

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Arihant Anaika Phase Ii
  • Location:
  • 35/04 And 36/01
  • Const. Stage:
    New
  • Possession:
    30 Dec 2023
Developer Details

  • Developer:
    Arihant Vatika Realty Private Limited
  • Phone:
  • Address:
  • "Arihant Aura"
Project RERA Details
MAHA REARA No: P52000014892
Project Type Residential / Group Housing
RERA Project Status New
Architect Kiran Awhale
Funding Bank ICICI BANK LIMITED
Proposed Possession 30 Dec 2023
Revised Possession
Extended Possession
Litigations No Litigations
Last Modified 09 Jan 2018
Last Retrived 28 Jul 2025
Arihant Anaika Phase Ii QR Code
Arihant Anaika Phase Ii
MahaRERA - P52000014892
Apartment Details & Configuration
TypeArea
1 BHK29.7 Sq.mts. ( 320 Sq.ft. )
2 BHK48.13 Sq.mts. ( 518 Sq.ft. )
1 BHK31.92 Sq.mts. ( 344 Sq.ft. )
1 BHK TYPE 132.63 Sq.mts. ( 351 Sq.ft. )
2 BHK TYPE 150.36 Sq.mts. ( 542 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Arihant Anaika Phase Iilast updated on 28 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Wip
Community Buildings60% completed
60% Complete
Wip
Electrical Meter Room, Sub-Station, Receiving Station50% completed
50% Complete
Wip (Common For Phase I &Amp; Ii)
Energy management
Wip
Fire Protection And Fire Safety Requirements
Na
Landscaping & Tree Planting
Work Not Started
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)95% completed
95% Complete
Stp Treated
Solid Waste Management And Disposal
Wip
Storm Water Drains70% completed
70% Complete
Wip
Street Lighting
Work Not Started
Treatment And Disposal Of Sewage And Sullage Water98% completed
98% Complete
Wip (Common For Phase I &Amp; Ii)
Water Conservation, Rain water Harvesting50% completed
50% Complete
Wip
Water Supply90% completed
90% Complete
Water Line
Buildings / Wings in Arihant Anaika Phase Ii
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Arihant Anaika Phase Ii by Arihant Vatika Realty Private Limitedlast updated on 28 Jul 2025 as per information obtained from MARA RERA.

119089 Sq. ft.

Project Area

11497 Sq. ft.

Recreational Open Space

Total 5

Wings / Towers in Project

Apartments Statistics

267 apartments in total
Total
267
Booked
267
Available
0

Saleable Area Statistics (Sq. ft.)

99906 Total
Total
99906
Booked
99906
Available
0
Total 267 apartments in project. 267 apartments booked. 100% apartments booked.
Total 99906 Sq.ft. saleable area. 99906 saleable area booked.
100% area booked.

C

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
CDec 202241010060
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK29.7 Sq.mts. ( 320 Sq.ft. )64
64 Booked100% Booked
100% Booked
2 BHK48.13 Sq.mts. ( 518 Sq.ft. )16
16 Booked100% Booked
100% Booked
80 total apartments / 80 apartments booked. 100% apartments booked.
Work Description in Building CCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress97% done
97% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress86% done
86% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
work-in-progress55% done
55% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress80% done
80% Booked
Stilt Floor
Completed 100% done
100% Booked

D

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
DDec 202241010026
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK29.7 Sq.mts. ( 320 Sq.ft. )32
32 Booked100% Booked
100% Booked
2 BHK48.13 Sq.mts. ( 518 Sq.ft. )16
16 Booked100% Booked
100% Booked
48 total apartments / 48 apartments booked. 100% apartments booked.
Work Description in Building DCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress97% done
97% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress24% done
24% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress86% done
86% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
work-in-progress57% done
57% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress92% done
92% Booked
Stilt Floor
Completed 100% done
100% Booked

G

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
GDec 202241010020
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK29.7 Sq.mts. ( 320 Sq.ft. )32
32 Booked100% Booked
100% Booked
2 BHK48.13 Sq.mts. ( 518 Sq.ft. )12
12 Booked100% Booked
100% Booked
44 total apartments / 44 apartments booked. 100% apartments booked.
Work Description in Building GCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress97% done
97% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress37% done
37% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress87% done
87% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
work-in-progress59% done
59% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress92% done
92% Booked
Stilt Floor
Completed 100% done
100% Booked

H

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
HDec 202241010029
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK29.7 Sq.mts. ( 320 Sq.ft. )32
32 Booked100% Booked
100% Booked
2 BHK48.13 Sq.mts. ( 518 Sq.ft. )16
16 Booked100% Booked
100% Booked
48 total apartments / 48 apartments booked. 100% apartments booked.
Work Description in Building HCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress97% done
97% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress37% done
37% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress87% done
87% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
work-in-progress59% done
59% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress92% done
92% Booked
Stilt Floor
Completed 100% done
100% Booked

I

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
IDec 202241010034
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK31.92 Sq.mts. ( 344 Sq.ft. )35
35 Booked100% Booked
100% Booked
1 BHK TYPE 132.63 Sq.mts. ( 351 Sq.ft. )4
4 Booked100% Booked
100% Booked
2 BHK48.13 Sq.mts. ( 518 Sq.ft. )4
4 Booked100% Booked
100% Booked
2 BHK TYPE 150.36 Sq.mts. ( 542 Sq.ft. )4
4 Booked100% Booked
100% Booked
47 total apartments / 47 apartments booked. 100% apartments booked.
Work Description in Building ICompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress40% done
40% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress86% done
86% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
work-in-progress58% done
58% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress86% done
86% Booked
Stilt Floor
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Arihant Vatika Realty Private Limited
for Project
Arihant Anaika Phase Ii
last updated on 28 Jul 2025 as per information obtained from MARA RERA.