Project overview

Aquaria Grande, Wing B Floor 33-38 is a MahaRERA Registered Project bearing MahaRERA Registration Number P51800007959. Aquaria Grande, Wing B Floor 33-38 is located at Sxfbpbhq/Yemdbceg6+Jqat7q+Rk+8Idrv7rihvut7q=. This is a Ongoing being developed by Club Aquaria Enterprises.

Aquaria Grande, Wing B Floor 33-38 has 3 BHK, 3 point 5 BHK & 4 BHK Apartments with carpet areas ranging from 1639 to 2298 Sq.ft. Carpet. The Project has total 17 of which 6 are currently available for sale.

Aquaria Grande, Wing B Floor 33-38 is being developed on a total land area of 9774 Sq.ft. Aquaria Grande, Wing B Floor 33-38 has 1 Wings / Towers Wing B Floor 33-38

ProjectDeveloperLocationPossession
One AquariaMessrs Src And AssociatesSax6ji4rh1do1m3afi2n+A==30-12-2023 00:00:00
Ossia EnclaveR B Developers8Nc78bqtjpxb0tbip0hirq5cyzylggotp4d+Tr8ysckunepthrqhw8lvworrks9w30-06-2018 00:00:00
Priya ApartmentJasmina Constructions Pvt. Ltd.Tipq958kip8nwsw5zezuua==15-06-2019 00:00:00
Krishna PalacePantagon BuiltEksar Road31-12-2021 00:00:00
Gorai Laxmi Chsl Casa Bellisimo B WingJaydev Realtors Private Limited7Xac+Wtqya0ca6z5y+Vs6qcnyjd89kwocdljtxfp+H8=31-10-2019 00:00:00
Kalpataru AvenueNeo Pharma Private LimitedPrxbq/Ii0qx38sxzty9jiyqsstmmn3qqwvyxg6c4zjw=30-06-2021 00:00:00
Grande EdificeV6 EnterprisesA2q3g4vecjfziihmlcscla==30-12-2026 00:00:00
Uptown Wing BRuchi Priya Developers Private Limited400101, Mumbai Suburban31-12-2018 00:00:00
Sanskriti SignatureDivisha Developers LlpCum1ncqzfq/B3jqrbcyfgw==31-12-2019 00:00:00
Soham RegencyLaxmikant Ramchandra SawantQkf934sifiuzrurhymyucg==31-12-2017 00:00:00
Oasis - Tower 1Glomore Constructions91+Bnn2vsrb0ytql8st4nw==31-12-2019 00:00:00
Shri Ganesh Krupa Sra Chs LtdAnil Sawant400101, Mumbai Suburban31-08-2017 00:00:00
Soham ResidencyLaxmikant Ramchandra SawantKctrpqmrdqt02xfuahcslg==31-12-2017 00:00:00
Helicon HeightsSahakar RealtorsIawdf0uxbnhcgp3fvtzzcg==30-06-2018 00:00:00
Shri JayA J ConstructionY952fgkpiugafyyhu0ut7w==31-12-2018 00:00:00
White City Phase 2 Wing BRajesh Real Estate Developers Private LimitedGnvfcdsgygb1puvvj6dmvw==30-06-2019 00:00:00
Jyoti ChslOssia DevelopersSyoqvpafc2yzdqgh+Apx2v1oqx8vuwgxmjorjy/Gqezvbsfgpcdjxjskybday2+F30-06-2018 00:00:00
Eksar Kavita ChsAditya Developers400092, Mumbai Suburban22-03-2018 00:00:00
Laxmi Krupa Chs Ltd.M/S. Shreepad DevelopersDcvg5msh0egmiegae0z9f7hjzmhjy+6Xpb00d1pjamw=31-12-2019 00:00:00
AspireM/S Radheshyam DevelopersPmcwpgpshw3o+H9pddg/Wq==30-12-2023 00:00:00
Vilas Vaibhav ChsAditya Developers400092, Mumbai Suburban25-12-2019 00:00:00
Rishabh HeightAdinath Enterprise40009231-07-2018 00:00:00
Uptown Wing CRuchi Priya Developers Private LimitedMumbai Suburban, 40010131-12-2018 00:00:00
Virangula Chs LtdRishabraj HousingCl9mbo3qf89cxigbkvf9ig==31-12-2018 00:00:00
Kamla Prasanna Jeevan Building1Kamla Homes And Lifestyles Pvt LtdHhv6jbdyqgau7jf7xusghq==31-03-2025 00:00:00
Kamla Prasanna Jeevan Building 2Kamla Homes And Lifestyles Pvt LtdMmdlderjpu455woxfdsgka==31-03-2025 00:00:00
Avyukta RajhansShivoham Infrahomes LlpPstqroatyst/Z2r8muzgmw==31-12-2024 00:00:00
Borivali Sangram Chs LtdK T GroupMumbai Suburban, 40009231-08-2016 00:00:00
Brindavan Silverpark ChsAditya DevelopersMumbai Suburban, 40009225-04-2020 00:00:00
Redevelopment Of Saraswati ChslRawoolnath Infrastructure Private LimitedSofnrrygxz9nwon8jgpwxgflhq3398hrsfouyhj24ic=30-12-2023 00:00:00
Redevelopment Of Ulka ChslPranav Constructions LimitedVzxaazrzecxydaicme6xfxvofdngevlwggzkzuamy/+Paiiqp6t5w62xx6guhsnpqcyi3voutlc9guvgxkm7ta==31-12-2019 00:00:00
Vastu PinnacleSanwar M KhandelwalEl2q7e/72Y+Jajr+Ga5vblasb438hg3hfl+Mcanml1k=31-03-2020 00:00:00
Aafcon Developers Ashokanand ChslAafcon DevelopersTmwwucibhcximn+Qxmkalg==30-12-2021 00:00:00
Whitecity Phase 1 Wing ARajesh Real Estate Developers Private LimitedGnvfcdsgygb1puvvj6dmvw==30-06-2019 00:00:00
Aquaria Grande, Wing B Floor 33-38 Club Aquaria EnterprisesSxfbpbhq/Yemdbceg6+Jqat7q+Rk+8Idrv7rihvut7q=30-12-2021 00:00:00
GavdevikrupaPeteresa RealtorsMumbai Suburban, 40009231-12-2017 00:00:00
Shree Matruchhaya Chs LtdK T GroupMumbai Suburban, 40009120-09-2015 00:00:00
Hiraco Eminence Phase 2KASHIMIRA CERAMIC PRODUCTS LLP1723 To 1726, 179330-09-2020 00:00:00
Pushkar ApartmentSayalee Sanjesh Patkar8Az/04Vn9mx3qarbffg15ki9ovx0mpazqjuy8g82sfxenfpt+G9djunbuuk/J8lo31-03-2019 00:00:00
The WindsorGadiraju Subramanyam Raju Proprietor Of Tirupathi EnterprisesApzylzrksqitluaab9ypsk3a121fofsvgs+Xxymtrni=31-12-2019 00:00:00
Oasis - Tower 2Acme Housing India Private Limited91+Bnn2vsrb0ytql8st4nw==31-12-2019 00:00:00
Hiraco Eminence Phase 1KASHIMIRA CERAMIC PRODUCTS LLP1442 To 1446, 1491 To 1511, 1586, 1589 To 1600, 1629, 1630, 1646 To 165230-09-2020 00:00:00
Breeze 91Kaustubh Construction Private LimitedWaymkuwhlwcs07viu5jpnrxg1zocu4h34qtzb/3H8zu=31-03-2030 00:00:00
Rls 280Adelphi Estates Private LimitedZjqnr/Km5neajn0he2ue5g==31-03-2029 00:00:00
Rbi Employees Siddhivinayak Chs LtdVasundhara Builders4Fgifstanxecgtzmgtdvtq==30-12-2020 00:00:00
Bhushan Enclave ChslBhushan Enterprises2+Fu/Jw1doouayv7dupsdw==30-06-2018 00:00:00
ElementBharat Manubhai PatelOs/Sov48nkubxyus+Nxne+Bj3xtw6suc5x2tpnhtr08ae6+Imk3tzx21qlz4ribrwuuzdpozmrlbusoymjwdvw==31-03-2018 00:00:00
Bhavna KunjVinod Infrastructure Private LimitedCgfishyicmwtbbqww9okp4zpue1fpoiygrw+Ozdpa6a=31-12-2018 00:00:00
Alpha ResidencyKonark Shakti Group Of CompaniesU2ycs0clbpvd407ml/Dcha==31-10-2019 00:00:00
Ganesh Chhaya ChslVasundhara Develocus Llp+Sdsu3zzulwfly5ihqhc7q==31-12-2028 00:00:00
Acharya Ashram Sahakari Griha Rachana Sanstha MaryaditVastu Darshan Developers LlpMdzlerzhhxdfeeoxikorgzlh2a4whbgqnswlwi39ycxabfvkecptbaepnhcvbictvob/Fedn9dieo1ybvugh+J6kmferxg/Me0t6fnyrfurgsqdypk+4Yw/Abvay8poxwez8lrmyxh+Uqcxt6iqg0a==30-10-2023 00:00:00
Royal EksarKosmos DeveloperBorivali West09-04-2026 00:00:00
Ankit ChsAditya Developers0Sgcdvlzu8+K52bvn2in+Q==25-12-2019 00:00:00
Prithvi Residency Prithvi Build HomesSy5yje3aj+Mfob6altbgyd+Ymf1nlx/Akeyxnrygcw+K6nhhcn6omv5tgbiijijubgbc8w+Zujlomf6famuyja==31-12-2018 00:00:00
Shreeyog ChslKosmos DevelopersVzkvgomyken11a1gik4ohq==31-12-2019 00:00:00
Komal Kounteya CHSLRander Bandhu Corporation LLP37030-06-2026 00:00:00
AKSHAYA AND JAYSHREE REDEVELOPMENTNHI DEVELOPERS LLP263/B31-12-2026 00:00:00
Jay KrishnaThe Green VenturezJbhhsmkrydpsdqb7r5jtsw==31-12-2025 00:00:00
Borivali Veer DhavalShree Durga Vastu Makers LlpNwe1z7hxr1oq3x8j9m3+Zhtgn3chc2wtzab4xy2dkgkuwcjhndbdrfucnn4wsldq3pyys/Chvmeqrkqfkljzaxuhktpfpcwcxbp4+Wf/Sxy=31-05-2024 00:00:00
Shila Bina Chs LtdMs InfrastructurePjuk7lekopavfyrwjri6ew==31-12-2025 00:00:00
VishramJeevandeep DevelopersSljzagdtbby3t4srxdaw0ozl5fagl2oks30iosbmagbpaalmiacxplirvtne59jv31-03-2019 00:00:00
Shri Yamai KrupaJeevandeep DevelopersT0+Zwnlw7h3not+Vbamrobzhoxtre2llhbjm5ngfbc0muivet0g//Gzwslaz4ndc31-03-2018 00:00:00
Om Sai Vinayak Co-Operative Housing Society LtdSai Omkar DevelopersThane, 40061531-12-2022 00:00:00
Arihant EnclaveKds Developers Pvt. Ltd.Iskxpr8y7gfjsy3vhywvaur6o84tov6cyp8evcd5h1a=31-12-2018 00:00:00
Royal AccordViva Homes Private LimitedL T Road30-06-2020 00:00:00
RudraShree Dps Project And Services Pvt. Ltd.Klxrvdse0kkwvwbqpxncog==31-12-2019 00:00:00
Govind Nagar Sra Chs Ltd.Drishti Developers IiR/2Lv+Rjiw4/Tbafbgspiqm2v4pnbbvpent1b6lbkiemuqoxutam0hwi8do65hte01-09-2022 00:00:00
Shastri NagarNewtech Land Developers Pvt LtdMumbai Suburban, 40010131-12-2021 00:00:00
West AvenueM/S Dhabalia EnterprisesMm+Dfprai5yoquos0qk/Cg==31-03-2026 00:00:00
Bank Of India Employees Sukhada ChslM/S Hirani RealtorsUsnslvhjld7oary6qgmrgq==10-06-2026 00:00:00
Rashmi SquareModi's Navnirman LimitedAy3lvm9dqciq2xsqjaja1g==28-05-2026 00:00:00
Vira AvenueVira Realty India Private LimitedV1qvn1nkcezsd8mko81n1a==31-12-2026 00:00:00
SheetalC H Patil And Sons Sheetal Project4Qf6co52fyc5pmu71mez9a==31-03-2029 00:00:00
Dynamix 36Nakasha Dynamix LlpKwltkmpismlibax/Sdnehjeohm9psgb/Scj9lhakzsy=30-06-2028 00:00:00
GagansagarHum Developers Private LimitedL5cun8pqwkdmfj1bzztvda==31-12-2026 00:00:00
Rashmi CelestiaModi's Navnirman LimitedJqumxfuyex+Ic1dpcmloaa==11-08-2025 00:00:00
Jaykant BlissChitalia BuildersGlloqtuc2vtuung1wgdetw==17-12-2026 00:00:00
Manusmruti ChslGoyal Wedevelopment Pvt LtdMzqqpk3vif7pkdpo1yulla==31-03-2024 00:00:00
Redevelopment Of Prateeksha Chs LtdAshiana Enterprises1Cf0wggxugbbiydrs5khnsractlyy0hzg1uni/Zjgtn2nd6znp6xia7dttlpet+L30-09-2018 00:00:00
New Vandana Co-Op Hsg. Soc. Ltd.Bhoomi Associates0Ulnmwwrtxwpewn6zkwl1a==30-12-2022 00:00:00
AurumRd Brothers Realty Llp01-06-2028 00:00:00
DhanrajAneisha Livings LlpFzqcpm7tnfeufr347btlvw==28-02-2025 00:00:00
Sai Signature SpacesRamachandran Munisawmy Narayan8Gqxiykrrknevyocbt5c57mbxmjthakxorojxiqzlci=30-09-2025 00:00:00
Aafcon HarmonyAafcon Builders Llp31-12-2029 00:00:00
I.C. Maitri MenorahRamas Realty31-03-2029 00:00:00
Kaustubh Altura 91Kaustubh Construction Private Limited30-09-2030 00:00:00
Sanjay Abode – Shree Vijay C-D Wing Chsl Sanjay Habitats Llp31-12-2027 00:00:00
New Aakanksha ChslHirani Realty23-02-2028 00:00:00
Jalkirti Chs Ltd Redevelopment ProjectBalajee Homes And Realtors Llp31-12-2029 00:00:00
SurylokMahavir Land Developer31-12-2029 00:00:00
Project Details
  • Project:
    Aquaria Grande, Wing B Floor 33-38
  • Location:
  • Sxfbpbhq/Yemdbceg6+Jqat7q+Rk+8Idrv7rihvut7q=
  • Const. Stage:
    Ongoing
  • Possession:
    30 Dec 2021
Developer Details

  • Developer:
    Club Aquaria Enterprises
  • Phone:
  • Address:
  • Platina
Project RERA Details
MAHA REARA No: P51800007959
Project Type Residential / Group Housing
RERA Project Status Ongoing
Architect Teearch
Funding Bank INDUSIND BANK
Proposed Possession 30 Dec 2021
Revised Possession 30 Dec 2021
Extended Possession
Litigations No Litigations
Last Modified 19 Mar 2020
Last Retrived 13 Feb 2026
Aquaria Grande, Wing B Floor 33-38 QR Code
Aquaria Grande, Wing B Floor 33-38
MahaRERA - P51800007959
Apartment Details & Configuration
TypeArea
3 BHK152.26 Sq.mts. ( 1639 Sq.ft. )
3 point 5 BHK172.78 Sq.mts. ( 1860 Sq.ft. )
4 BHK202.97 Sq.mts. ( 2185 Sq.ft. )
4 BHK213.48 Sq.mts. ( 2298 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Aquaria Grande, Wing B Floor 33-38 last updated on 13 Feb 2026 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space90% completed
90% Complete
Provided
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station90% completed
90% Complete
Transformer
Energy management95% completed
95% Complete
Transformer
Fire Protection And Fire Safety Requirements100% completed
95% Complete
As Per Cfo Noc
Landscaping & Tree Planting95% completed
95% Complete
On Ground And Podium Top
Open Parking90% completed
90% Complete
Provided
Sewerage (Chamber, Lines, Septic Tank , STP)90% completed
90% Complete
Stp
Solid Waste Management And Disposal82% completed
82% Complete
Garbage Chute Provision
Storm Water Drains100% completed
95% Complete
As Per Swd Remarks
Street Lighting
Na
Treatment And Disposal Of Sewage And Sullage Water90% completed
90% Complete
Stp
Water Conservation, Rain water Harvesting90% completed
90% Complete
Rwh As Per Consultant
Water Supply82% completed
82% Complete
Connection After Oc By Bmc
Buildings / Wings in Aquaria Grande, Wing B Floor 33-38
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Aquaria Grande, Wing B Floor 33-38 by Club Aquaria Enterpriseslast updated on 13 Feb 2026 as per information obtained from MARA RERA.

9774 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 1

Wings / Towers in Project

Apartments Statistics

17 apartments in total
Total
17
Booked
11
Available
6

Saleable Area Statistics (Sq. ft.)

33028 Total
Total
33028
Booked
22090
Available
10938
Total 17 apartments in project. 11 apartments booked. 64% apartments booked.
Total 33028 Sq.ft. saleable area. 22090 saleable area booked.
67% area booked.

Wing B Floor 33-38

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing B Floor 33-38Dec 202071000043
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
3 BHK152.26 Sq.mts. ( 1639 Sq.ft. )5
4 Booked80% Booked
80% Booked
3 point 5 BHK172.78 Sq.mts. ( 1860 Sq.ft. )6
4 BHK202.97 Sq.mts. ( 2185 Sq.ft. )1
1 Booked100% Booked
100% Booked
4 BHK213.48 Sq.mts. ( 2298 Sq.ft. )5
5 Booked100% Booked
100% Booked
17 total apartments / 11 apartments booked. 64% apartments booked.
Work Description in Building Wing B Floor 33-38Completion
Basement (if any)
Excavation
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress60% done
60% Booked
Plinth
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Club Aquaria Enterprises
for Project
Aquaria Grande, Wing B Floor 33-38
last updated on 13 Feb 2026 as per information obtained from MARA RERA.