Project overview

Apeksha Complex is a MahaRERA Registered Project bearing MahaRERA Registration Number P99000009883. Apeksha Complex is located at 9B. This is a Ongoing being developed by Kothari Construction Co.

Apeksha Complex has 1 BHK Apartments with carpet areas ranging from 352 to 352 Sq.ft. Carpet. The Project has total 208 of which 38 are currently available for sale.

Apeksha Complex is being developed on a total land area of 61626 Sq.ft. out of which 7721 Sq.ft. i.e 13% is reserved for recreational purposes. Apeksha Complex has 4 Wings / Towers A,B,C,D

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Apeksha Complex
  • Location:
  • 9B
  • Const. Stage:
    Ongoing
  • Possession:
    30 Dec 2022
Developer Details

  • Developer:
    Kothari Construction Co
  • Phone:
  • Address:
  • Jagmani Shantinagar Chs Ltd
Project RERA Details
MAHA REARA No: P99000009883
Project Type Residential / Group Housing
RERA Project Status Ongoing
Architect Sanjay S Narang
Funding Bank INDUSIND BANK
Proposed Possession 30 Dec 2022
Revised Possession 30 Dec 2022
Extended Possession 30 Dec 2026
Litigations No Litigations
Last Modified 03 Jan 2024
Last Retrived 28 Jul 2025
Apeksha Complex QR Code
Apeksha Complex
MahaRERA - P99000009883
Apartment Details & Configuration
TypeArea
1 BHK32.79 Sq.mts. ( 353 Sq.ft. )
2 BHK49.8 Sq.mts. ( 536 Sq.ft. )
Shop85.93 Sq.mts. ( 925 Sq.ft. )
2 BHK50.17 Sq.mts. ( 540 Sq.ft. )
Shop203.64 Sq.mts. ( 2192 Sq.ft. )
1 BHK32.7 Sq.mts. ( 352 Sq.ft. )
SHOP80.64 Sq.mts. ( 868 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Apeksha Complexlast updated on 28 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station70% completed
70% Complete
By Developer
Energy management
Na
Fire Protection And Fire Safety Requirements70% completed
70% Complete
By Developer
Landscaping & Tree Planting70% completed
70% Complete
By Developer
Open Parking70% completed
70% Complete
By Developer
Sewerage (Chamber, Lines, Septic Tank , STP)70% completed
70% Complete
By Developer
Solid Waste Management And Disposal70% completed
70% Complete
By Developer
Storm Water Drains70% completed
70% Complete
By Developer
Street Lighting70% completed
70% Complete
By Vvcmc
Treatment And Disposal Of Sewage And Sullage Water70% completed
70% Complete
By Developer
Water Conservation, Rain water Harvesting70% completed
70% Complete
By Developer
Water Supply70% completed
70% Complete
By Vvcmc
Buildings / Wings in Apeksha Complex
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Apeksha Complex by Kothari Construction Colast updated on 28 Jul 2025 as per information obtained from MARA RERA.

61626 Sq. ft.

Project Area

7721 Sq. ft.

Recreational Open Space

Total 4

Wings / Towers in Project

Apartments Statistics

208 apartments in total
Total
208
Booked
170
Available
38

Saleable Area Statistics (Sq. ft.)

108250 Total
Total
108250
Booked
77993
Available
30256
Total 208 apartments in project. 170 apartments booked. 81% apartments booked.
Total 108250 Sq.ft. saleable area. 77993 saleable area booked.
72% area booked.

A

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
ADec 202181010151
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK32.79 Sq.mts. ( 353 Sq.ft. )28
21 Booked75% Booked
75% Booked
2 BHK49.8 Sq.mts. ( 536 Sq.ft. )14
6 Booked42% Booked
42% Booked
Shop85.93 Sq.mts. ( 925 Sq.ft. )8
4 Booked50% Booked
50% Booked
50 total apartments / 31 apartments booked. 62% apartments booked.
Work Description in Building ACompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress98% done
98% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress98% done
98% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress75% done
75% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress65% done
65% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
work-in-progress98% done
98% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
work-in-progress95% done
95% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress98% done
98% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress70% done
70% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

B

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
BDec 202181010151
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK32.79 Sq.mts. ( 353 Sq.ft. )42
36 Booked85% Booked
85% Booked
2 BHK50.17 Sq.mts. ( 540 Sq.ft. )14
14 Booked100% Booked
100% Booked
Shop203.64 Sq.mts. ( 2192 Sq.ft. )12
6 Booked50% Booked
50% Booked
68 total apartments / 56 apartments booked. 82% apartments booked.
Work Description in Building BCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress98% done
98% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress90% done
90% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress98% done
98% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress98% done
98% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress90% done
90% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress85% done
85% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
work-in-progress90% done
90% Booked
Sanitary Fittings within the flats / premises
work-in-progress98% done
98% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
work-in-progress90% done
90% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress98% done
98% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress90% done
90% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

C

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
CDec 202181010151
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK32.7 Sq.mts. ( 352 Sq.ft. )42
41 Booked97% Booked
97% Booked
SHOP80.64 Sq.mts. ( 868 Sq.ft. )6
2 Booked33% Booked
33% Booked
48 total apartments / 43 apartments booked. 89% apartments booked.
Work Description in Building CCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress98% done
98% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress95% done
95% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress98% done
98% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress98% done
98% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress95% done
95% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
work-in-progress95% done
95% Booked
Sanitary Fittings within the flats / premises
work-in-progress98% done
98% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
work-in-progress95% done
95% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress98% done
98% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress95% done
95% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

D

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
DDec 202181010151
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK32.7 Sq.mts. ( 352 Sq.ft. )42
40 Booked95% Booked
95% Booked
42 total apartments / 40 apartments booked. 95% apartments booked.
Work Description in Building DCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress98% done
98% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress95% done
95% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress98% done
98% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress98% done
98% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress95% done
95% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
work-in-progress95% done
95% Booked
Sanitary Fittings within the flats / premises
work-in-progress98% done
98% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
work-in-progress95% done
95% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress98% done
98% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress95% done
95% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Kothari Construction Co
for Project
Apeksha Complex
last updated on 28 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation