Project overview

Ananda Residency is a MahaRERA Registered Project bearing MahaRERA Registration Number P51800000204. Ananda Residency is located at Fp No-383, Tps-Iii. This is a Ongoing being developed by Paradigm Ambit Buildcon.

Ananda Residency has 2 BHK & 3 BHK Apartments with carpet areas ranging from 153172 to 18331 Sq.ft. Carpet. The Project has total 255 of which 9 are currently available for sale.

Ananda Residency is being developed on a total land area of 35181 Sq.ft. out of which 6296 Sq.ft. i.e 18% is reserved for recreational purposes. Ananda Residency has 1 Wings / Towers Ananda Residency

ProjectDeveloperLocationPossession
Sanskriti SignatureDivisha Developers Llp240 Pt31-12-2019 00:00:00
Om Sarjan ChslGlasswood Realty Private Limited777/9 149A Fp No 680/A/1/231-12-2019 00:00:00
Soham RegencyLaxmikant Ramchandra SawantCts No 195B31-12-2017 00:00:00
Sakshat NavkarNavkar Infra ProjectsFinal Plot No 4930-09-2019 00:00:00
Navkar ParadiseNavkar Infra Projects65415-06-2021 00:00:00
Sajag ChsNavkar Infra ProjectsFp No 719/324-06-2019 00:00:00
Madhuban HeightsWadhwana Housing Development And Infrastructure Co740/4131-08-2018 00:00:00
The ZoneMs Amann Raj Housing And Development CorporationCts No 655, 663, 664, 656Pt, 659, 662, 665Pt31-01-2021 00:00:00
Soham ResidencyLaxmikant Ramchandra SawantFp-41531-12-2017 00:00:00
Rite AspireRite Developers Pvt. Ltd.Cts No 4/A30-06-2021 00:00:00
Shreeyog ChslKosmos Developer288A31-12-2019 00:00:00
VrindavanRight Channel Construction Pvt LtdCarter Road No 331-12-2017 00:00:00
Balaji Arcade Wing BShikhar DevelopersSurvey No 7 Hissa No 10,13/2/1 Old Survey No 10 Part And 13 Part31-12-2019 00:00:00
Sai Laxmi ChslShreejani Developers136/A 1To6, 136/A31-12-2017 00:00:00
Avenue 641Dimple CreationsFinal Plot No 64130-09-2020 00:00:00
Komal Kounteya ChslRander Bandhu Corporation Llp37030-06-2026 00:00:00
Ashirwad ChslKranvis Realty Llp21901-08-2025 00:00:00
Vir EnclaveJkd Engineers And Infrastructure Private Limited27530-06-2025 00:00:00
Rishabh HeightAdinath Enterprise40009231-07-2018 00:00:00
Paarijat Chs LtdMaan Housing Development94531-12-2018 00:00:00
Modispaces AmazonModispaces Real Estate Pvt LtdFp No. 628 Of Village Borivali31-12-2019 00:00:00
DhanrajAneisha Livings LlpFp No.31128-02-2025 00:00:00
Kedar DarshanKosmos Developer275/811-04-2027 00:00:00
The Jambli Galli Chs LtdMahavir CorporationsFp No 8331-03-2024 00:00:00
Helicon HeightsSahakar Realtors439 - 445 Part30-06-2018 00:00:00
Borivali Ranjee ChsAditya Developers400092, Mumbai Suburban27-12-2018 00:00:00
Adinath ChsAditya Developers400092, Mumbai Suburban22-04-2020 00:00:00
Avyukta RajhansShivoham Infrahomes Llp31-A/231-12-2024 00:00:00
Rishabraj RameshwarH Rishabraj Realty275 Part31-08-2024 00:00:00
Manusmruti ChslGoyal Wedevelopment Pvt LtdFp36131-03-2024 00:00:00
Ananda ResidencyParadigm Ambit BuildconFp No-383, Tps-Iii31-12-2019 00:00:00
Rashmi SquareModi's Navnirman Limited258 A28-05-2026 00:00:00
House Of Shreeji SharanMiles Infra Llp620/2630-09-2026 00:00:00
Kcd RidgewoodKcd Heritage Pvt LtdBorivali, 400092, Mumbai Suburban29-02-2020 00:00:00
Neelkamal HeightsOsho Developers620/1031-12-2017 00:00:00
New Anamika Triveni FortuneTriveni DevelopersMumbai Suburban, 40009230-09-2017 00:00:00
Maya MamtaGreenbuilding Lifescapes Llp15907-10-2025 00:00:00
TreviAshirwad Nice Developers72131-12-2025 00:00:00
New Abhiram Chs LtdPeerless Constructions Pvt. Ltd.62030-06-2025 00:00:00
Ramkrupa ChslKosmos&Amp;T-CreationL T Road30-03-2024 00:00:00
Himat Mansion Chs LtdBhatia Builders And Developers Pvt LtdcF.P.No.3130-06-2027 00:00:00
Krishna KoynaJkd Engineers And Infrastructure Private LimitedFp 620 Plot No 415-05-2024 00:00:00
Satra ParkShreenivas DevelopersFp 17930-12-2021 00:00:00
Pushp Vinod - 15Vas Infrastructure Ltd.F.P. No.64830-12-2021 00:00:00
Sunrise Orlem 2A Phase 1Dhaval Housing Aop439, 438B31-12-2019 00:00:00
Om Satyam Niwas Chs LtdGreenfield Developers & Realtors LlpF. P. No. 680/A/1/3 Of T.P.S. Iii Village Borivali31-07-2020 00:00:00
Dlh KesleyDlh Pansn Developers LlpCts No 4 C31-03-2019 00:00:00
Mahalaxmi Prasad BuildingSudheer Dadarkar565-569-57031-12-2018 00:00:00
Bella VistaSidharth EnterprisesCts No.64231-12-2026 00:00:00
Supreme ImperialSupreme Real Estate Developer541 And 545 Tps Iii30-04-2025 00:00:00
Rbies Jaidatta ChslRbies Jaidatta Chsl719C31-12-2023 00:00:00
Jay KrishnaThe Green Venturez31331-12-2025 00:00:00
Rishabraj MangaleshRishabraj Infra Llp275A31-12-2026 00:00:00
Rashmi CelestiaModi's Navnirman Limited12511-08-2025 00:00:00
Redevelopment Of Ulka ChslPranav Constructions LimitedCts No 116 Village Eksar Tps Borivali Iii Fp 32031-12-2019 00:00:00
Ostwal TowerUnnati BuildersFp No. 37931-12-2018 00:00:00
Manek Terrace Chs LtdK T GroupMumbai Suburban, 40009228-02-2017 00:00:00
New Vandana Co-Op Hsg. Soc. Ltd.Bhoomi Associates26A And 25C30-12-2022 00:00:00
SwashrayShanti Enterprise347 Plus Fp 28930-05-2022 00:00:00
SamtaGreen Tree Lifescapes LlpFp No 14401-08-2022 00:00:00
Rashmi VasudeoModi's Navnirman Limited620/2511-08-2025 00:00:00
Bank Of India Employees Sukhada ChslM/S Hirani Realtors31610-06-2026 00:00:00
Kasturi MilanH Rishabraj Realty620D28-02-2025 00:00:00
Supreme MadhukarSupreme EnterpriseTps Iii Borivali At Kastur Park, Cts No 620/17 Of Village Borivali05-01-2025 00:00:00
VrindavanDinesh Amrutlal ThakkarFp No 37731-12-2025 00:00:00
Rishabraj Park VistasH Rishabraj RealtyFp No 71431-12-2025 00:00:00
One AquariaMessrs Src And AssociatesCts No. 23830-12-2023 00:00:00
Priya ApartmentJasmina Constructions Pvt. Ltd.263/A15-06-2019 00:00:00
Rajal - Veer Abhimanyu Chs LtdNisar Properties Pvt. Ltd.Plot No 275, Cts No 511/330-06-2023 00:00:00
Sai Signature SpacesRamachandran Munisawmy Narayan501$#$ 501/1 To 430-09-2025 00:00:00
DreamsvilleParadiso Builders Private Limited630A31-05-2024 00:00:00
AureateNext Space Realty LlpF P No 684 Of Tps Iii Corresponding To Cts No. 67/S Of Village Shimpoli, Borivali30-06-2027 00:00:00
Casa RareGeopreneur Corp Pvt Ltd68331-03-2019 00:00:00
Jyoti ChslOssia Developers305/1, 305/4, 305/330-06-2018 00:00:00
Redevelopment Of Nahar ChslRishubh Developers544, 544/1 To 425-12-2021 00:00:00
Adarsh Garden Grove Wing BAdarsh Enterprises374B/3/B31-12-2028 00:00:00
Gautam PrabhuH Rishabraj Realty65730-04-2027 00:00:00
Vira AvenueVira Realty India Private Limited100 ,10131-12-2026 00:00:00
Dollars Avenue ChslM/S Hirani Realtors73602-11-2027 00:00:00
Royal EksarKosmos DeveloperBorivali West09-04-2026 00:00:00
Kamla Prasanna Jeevan Building1Kamla Homes And Lifestyles Pvt LtdPlot 32C31-03-2025 00:00:00
Kamla Prasanna Jeevan Building 2Kamla Homes And Lifestyles Pvt LtdPlot No 32A31-03-2025 00:00:00
Dps AishwaryaBp Infra Kalindi DevelopersCts No 143 A And 143 B28-02-2022 00:00:00
Ankur PalaceOsho Developers719/815-08-2019 00:00:00
Ganesh Siddhi 2Shanti Enterprise400092, Mumbai Suburban08-01-2018 00:00:00
Anjani TirthGeeta Space RealtorsBorivali, Tps Iii, 69131-12-2024 00:00:00
Auris Business CentreDev Pooja Builders Pvt Ltd169B31-12-2024 00:00:00
Borivali Veer DhavalShree Durga Vastu Makers Llp43, 222/1 To 5, 45, 44, 222, 225, 226 And 22931-05-2024 00:00:00
Proposed Red On Plot Bearing Fp No 40 Of Tps Iii Village Borivali West MumbaiSurbhi Midas Construction4031-05-2025 00:00:00
Rishabraj AradhanaH Rishabraj RealtyIii31-07-2026 00:00:00
Redevelopment Of Lakshman Tower ChslPranav Constructions Limited51413-03-2027 00:00:00
Project Details
  • Project:
    Ananda Residency
  • Location:
  • Fp No-383, Tps-Iii
  • Const. Stage:
    Ongoing
  • Possession:
    31 Dec 2019
Developer Details

  • Developer:
    Paradigm Ambit Buildcon
  • Phone:
  • Address:
  • Nivan
Project RERA Details
MAHA REARA No: P51800000204
Project Type Residential / Group Housing
RERA Project Status Ongoing
Architect Manoj Vishwakarma
Funding Bank HDFC BANK
Proposed Possession 31 Dec 2019
Revised Possession 31 Dec 2019
Extended Possession 30 Dec 2021
Litigations No Litigations
Last Modified 09 Sep 2021
Last Retrived 26 Jul 2025
Ananda Residency QR Code
Ananda Residency
MahaRERA - P51800000204
Apartment Details & Configuration
TypeArea
2 BHK14230 Sq.mts. ( 153172 Sq.ft. )
3 BHK1702.97 Sq.mts. ( 18331 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Ananda Residencylast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space10% completed
10% Complete
Commenced
Amphi Theatre75% completed
75% Complete
Commenced
Community Buildings
Commenced
Electrical Meter Room, Sub-Station, Receiving Station50% completed
50% Complete
Commenced
Energy management60% completed
60% Complete
Commenced
Fire Protection And Fire Safety Requirements60% completed
60% Complete
Commenced
Fitness Centre75% completed
75% Complete
Commenced
Jogging Track and Children Play Area80% completed
80% Complete
Commenced
Landscaping & Tree Planting60% completed
60% Complete
Commenced
Multi Purpose Court80% completed
80% Complete
Commenced
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)90% completed
90% Complete
Commenced
Sky Garden at Terrace30% completed
30% Complete
Commenced
Solid Waste Management And Disposal
Commenced
Storm Water Drains70% completed
70% Complete
Commenced
Street Lighting
Commenced
Swimming Pool and Kids Pool70% completed
70% Complete
Commenced
Treatment And Disposal Of Sewage And Sullage Water60% completed
60% Complete
Commenced
Water Conservation, Rain water Harvesting60% completed
60% Complete
Commenced
Water Supply85% completed
85% Complete
Commenced
Buildings / Wings in Ananda Residency
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Ananda Residency by Paradigm Ambit Buildconlast updated on 26 Jul 2025 as per information obtained from MARA RERA.

35181 Sq. ft.

Project Area

6296 Sq. ft.

Recreational Open Space

Total 1

Wings / Towers in Project

Apartments Statistics

255 apartments in total
Total
255
Booked
246
Available
9

Saleable Area Statistics (Sq. ft.)

36496811 Total
Total
36496811
Booked
35522788
Available
974023
Total 255 apartments in project. 246 apartments booked. 96% apartments booked.
Total 36496811 Sq.ft. saleable area. 35522788 saleable area booked.
97% area booked.

Ananda Residency

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Ananda ResidencyJun 20212110110216
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK14230 Sq.mts. ( 153172 Sq.ft. )236
230 Booked97% Booked
97% Booked
3 BHK1702.97 Sq.mts. ( 18331 Sq.ft. )19
16 Booked84% Booked
84% Booked
255 total apartments / 246 apartments booked. 96% apartments booked.
Work Description in Building Ananda ResidencyCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress97% done
97% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress85% done
85% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress85% done
85% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress95% done
95% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress95% done
95% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
work-in-progress80% done
80% Booked
Sanitary Fittings within the flats / premises
work-in-progress80% done
80% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
work-in-progress96% done
96% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress96% done
96% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress97% done
97% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
Completed 100% done
100% Booked
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Paradigm Ambit Buildcon
for Project
Ananda Residency
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation