Project overview

Anand Basera Wing I And J is a MahaRERA Registered Project bearing MahaRERA Registration Number P99000024152. Anand Basera Wing I And J is located at Sy No-1, H No-5B. This is a New being developed by Pan India Realty.

Anand Basera Wing I And J has 1 BHK & Shop Apartments with carpet areas ranging from 147 to 90 Sq.ft. Carpet. The Project has total 32 of which 25 are currently available for sale.

Anand Basera Wing I And J is being developed on a total land area of 13836 Sq.ft. Anand Basera Wing I And J has 2 Wings / Towers Anand Basera Wing I,Anand Basera Wing J

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Anand Basera Wing I And J
  • Location:
  • Sy No-1, H No-5B
  • Const. Stage:
    New
  • Possession:
    29 Nov 2024
Developer Details

  • Developer:
    Pan India Realty
  • Phone:
  • Address:
  • Shanti Shopping Centre
Project RERA Details
MAHA REARA No: P99000024152
Project Type Others
RERA Project Status New
Architect Vastu Shilp
Funding Bank KARNATAKA BANK LIMITED
Proposed Possession 29 Nov 2024
Revised Possession
Extended Possession
Litigations No Litigations
Last Modified 17 Mar 2025
Last Retrived 28 Jul 2025
Anand Basera Wing I And J QR Code
Anand Basera Wing I And J
MahaRERA - P99000024152
Apartment Details & Configuration
TypeArea
1 BHK32.1 Sq.mts. ( 346 Sq.ft. )
1 BHK34.13 Sq.mts. ( 367 Sq.ft. )
Shop6.57 Sq.mts. ( 71 Sq.ft. )
Shop8.37 Sq.mts. ( 90 Sq.ft. )
Shop13.63 Sq.mts. ( 147 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Anand Basera Wing I And Jlast updated on 28 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station
Electric Meter Room To Be Provided
Energy management
Na
Fire Protection And Fire Safety Requirements
Na
Landscaping & Tree Planting
Tree Planting To Be Provided
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)
Sewerage (Chamber Septic Tank) To Be Provided
Solid Waste Management And Disposal
Na
Storm Water Drains
Storm Water Drains To Be Provided
Street Lighting
Street Lighting To Be Provided
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting
Rain Water Harvesting To Be Provided
Water Supply
Borewell To Be Provided
Buildings / Wings in Anand Basera Wing I And J
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Anand Basera Wing I And J by Pan India Realtylast updated on 28 Jul 2025 as per information obtained from MARA RERA.

13836 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 2

Wings / Towers in Project

Apartments Statistics

32 apartments in total
Total
32
Booked
7
Available
25

Saleable Area Statistics (Sq. ft.)

8359 Total
Total
8359
Booked
1995
Available
6364
Total 32 apartments in project. 7 apartments booked. 21% apartments booked.
Total 8359 Sq.ft. saleable area. 1995 saleable area booked.
24% area booked.

Anand Basera Wing I

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Anand Basera Wing INov 20234101000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK32.1 Sq.mts. ( 346 Sq.ft. )5
1 Booked20% Booked
20% Booked
1 BHK34.13 Sq.mts. ( 367 Sq.ft. )5
2 Booked40% Booked
40% Booked
Shop6.57 Sq.mts. ( 71 Sq.ft. )2
None Booked0% Booked
0% Booked
Shop8.37 Sq.mts. ( 90 Sq.ft. )2
1 Booked50% Booked
50% Booked
Shop13.63 Sq.mts. ( 147 Sq.ft. )2
None Booked0% Booked
0% Booked
16 total apartments / 4 apartments booked. 25% apartments booked.
Work Description in Building Anand Basera Wing ICompletion
Basement (if any)
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress50% done
50% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress50% done
50% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress50% done
50% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
work-in-progress50% done
50% Booked
Sanitary Fittings within the flats / premises
work-in-progress50% done
50% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
work-in-progress75% done
75% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress75% done
75% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress50% done
50% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Anand Basera Wing J

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Anand Basera Wing JNov 20234101000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK32.1 Sq.mts. ( 346 Sq.ft. )5
None Booked0% Booked
0% Booked
1 BHK34.13 Sq.mts. ( 367 Sq.ft. )5
2 Booked40% Booked
40% Booked
Shop6.57 Sq.mts. ( 71 Sq.ft. )2
None Booked0% Booked
0% Booked
Shop8.37 Sq.mts. ( 90 Sq.ft. )2
1 Booked50% Booked
50% Booked
Shop13.63 Sq.mts. ( 147 Sq.ft. )2
None Booked0% Booked
0% Booked
16 total apartments / 3 apartments booked. 18% apartments booked.
Work Description in Building Anand Basera Wing JCompletion
Basement (if any)
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress50% done
50% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress50% done
50% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress50% done
50% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
work-in-progress50% done
50% Booked
Sanitary Fittings within the flats / premises
work-in-progress50% done
50% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
work-in-progress75% done
75% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress75% done
75% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress50% done
50% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Pan India Realty
for Project
Anand Basera Wing I And J
last updated on 28 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation