Project overview

Amantra Phase 2 is a MahaRERA Registered Project bearing MahaRERA Registration Number P51700000308. Amantra Phase 2 is located at Sno 49Part, Hissano 1To9, 50 Part,51 Part,52 Part, Hissano 2, 4/2, 53 Part. This is a Ongoing being developed by Tata Housing Development Company Limited.

Amantra Phase 2 has 2 BHK & 3 BHK Apartments with carpet areas ranging from 579 to 927 Sq.ft. Carpet. The Project has total 825 of which 428 are currently available for sale.

Amantra Phase 2 is being developed on a total land area of 224919 Sq.ft. Amantra Phase 2 has 6 Wings / Towers A 10,A 11,A 8,A 9,C 1,D 7

ProjectDeveloperLocationPossession
Padmadisha Paradise - Building 2Padmadisha Paradise133/2/2, 133/2/330-12-2026 00:00:00
Godrej UpavanPrakhhyat Dwellings Llp40/1/2 40/2 40/3 40/4 40/5 40/640/740/840/940/1040/11 40/12 40/13/1/A 40/13/2 42 43/1 43/2 43/3 44/1/1 44/1/2 44/2/1 44/2/2 44/2/3 44/3/1 44/3/2 44/4 44/5 44/6 45/2/1 45/3/1 45/4 45/7 45/8 45/9 58/20/1 58/20/2 58/21 58/22 84 128/3/4 128/3/5 129/1 18130-06-2028 00:00:00
Project Details
  • Project:
    Amantra Phase 2
  • Location:
  • Sno 49Part, Hissano 1To9, 50 Part,51 Part,52 Part, Hissano 2, 4/2, 53 Part
  • Const. Stage:
    Ongoing
  • Possession:
    31 Mar 2018
Developer Details

  • Developer:
    Tata Housing Development Company Limited
  • Phone:
  • Address:
  • Voltas Premises
Project RERA Details
MAHA REARA No: P51700000308
Project Type Residential / Group Housing
RERA Project Status Ongoing
Architect M/S Iag - Design Architect
Funding Bank STATE BANK OF INDIA
Proposed Possession 31 Mar 2018
Revised Possession 31 Mar 2018
Extended Possession
Litigations No Litigations
Last Modified 15 Jul 2017
Last Retrived 26 Jul 2025
Amantra Phase 2 QR Code
Amantra Phase 2
MahaRERA - P51700000308
Apartment Details & Configuration
TypeArea
2 BHK53.8 Sq.mts. ( 579 Sq.ft. )
2 BHK57.35 Sq.mts. ( 617 Sq.ft. )
2 BHK59.3 Sq.mts. ( 638 Sq.ft. )
2 BHK62.89 Sq.mts. ( 677 Sq.ft. )
3 BHK79.22 Sq.mts. ( 853 Sq.ft. )
3 BHK85.62 Sq.mts. ( 922 Sq.ft. )
3 BHK86.44 Sq.mts. ( 930 Sq.ft. )
3 BHK87.67 Sq.mts. ( 944 Sq.ft. )
3 BHK90.01 Sq.mts. ( 969 Sq.ft. )
2 BHK70.39 Sq.mts. ( 758 Sq.ft. )
2 BHK73.74 Sq.mts. ( 794 Sq.ft. )
3 BHK84.64 Sq.mts. ( 911 Sq.ft. )
3 BHK86.1 Sq.mts. ( 927 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Amantra Phase 2last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
Community Buildings100% completed
95% Complete
Club House Completed
Electrical Meter Room, Sub-Station, Receiving Station100% completed
95% Complete
Completed
Energy management100% completed
95% Complete
Completed
Fire Protection And Fire Safety Requirements100% completed
95% Complete
Completed
Landscaping & Tree Planting100% completed
95% Complete
Completed
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
95% Complete
Completed
Solid Waste Management And Disposal100% completed
95% Complete
Completed
Storm Water Drains100% completed
95% Complete
Completed
Street Lighting100% completed
95% Complete
Completed
Treatment And Disposal Of Sewage And Sullage Water100% completed
95% Complete
Completed
Water Conservation, Rain water Harvesting100% completed
95% Complete
Completed
Water Supply100% completed
95% Complete
Completed
Buildings / Wings in Amantra Phase 2
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Amantra Phase 2 by Tata Housing Development Company Limitedlast updated on 26 Jul 2025 as per information obtained from MARA RERA.

224919 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 6

Wings / Towers in Project

Apartments Statistics

825 apartments in total
Total
825
Booked
397
Available
428

Saleable Area Statistics (Sq. ft.)

607529 Total
Total
607529
Booked
278623
Available
328905
Total 825 apartments in project. 397 apartments booked. 48% apartments booked.
Total 607529 Sq.ft. saleable area. 278623 saleable area booked.
46% area booked.

A 10

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
A 10Mar 20182910130154
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK53.8 Sq.mts. ( 579 Sq.ft. )28
26 Booked92% Booked
92% Booked
2 BHK57.35 Sq.mts. ( 617 Sq.ft. )29
7 Booked24% Booked
24% Booked
2 BHK59.3 Sq.mts. ( 638 Sq.ft. )24
20 Booked83% Booked
83% Booked
2 BHK62.89 Sq.mts. ( 677 Sq.ft. )29
17 Booked58% Booked
58% Booked
3 BHK79.22 Sq.mts. ( 853 Sq.ft. )29
10 Booked34% Booked
34% Booked
139 total apartments / 80 apartments booked. 57% apartments booked.
Work Description in Building A 10Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked

A 11

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
A 11Mar 20182910130154
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK53.8 Sq.mts. ( 579 Sq.ft. )28
24 Booked85% Booked
85% Booked
2 BHK57.35 Sq.mts. ( 617 Sq.ft. )24
12 Booked50% Booked
50% Booked
2 BHK59.3 Sq.mts. ( 638 Sq.ft. )29
7 Booked24% Booked
24% Booked
2 BHK62.89 Sq.mts. ( 677 Sq.ft. )29
25 Booked86% Booked
86% Booked
3 BHK79.22 Sq.mts. ( 853 Sq.ft. )29
18 Booked62% Booked
62% Booked
139 total apartments / 86 apartments booked. 61% apartments booked.
Work Description in Building A 11Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked

A 8

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
A 8Mar 20182910130154
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK53.8 Sq.mts. ( 579 Sq.ft. )28
10 Booked35% Booked
35% Booked
2 BHK57.35 Sq.mts. ( 617 Sq.ft. )29
2 BHK59.3 Sq.mts. ( 638 Sq.ft. )24
18 Booked75% Booked
75% Booked
2 BHK62.89 Sq.mts. ( 677 Sq.ft. )29
20 Booked68% Booked
68% Booked
3 BHK79.22 Sq.mts. ( 853 Sq.ft. )29
139 total apartments / 55 apartments booked. 39% apartments booked.
Work Description in Building A 8Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked

A 9

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
A 9Mar 20182910130154
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK53.8 Sq.mts. ( 579 Sq.ft. )28
24 Booked85% Booked
85% Booked
2 BHK57.35 Sq.mts. ( 617 Sq.ft. )24
9 Booked37% Booked
37% Booked
2 BHK59.3 Sq.mts. ( 638 Sq.ft. )29
8 Booked27% Booked
27% Booked
2 BHK62.89 Sq.mts. ( 677 Sq.ft. )29
26 Booked89% Booked
89% Booked
3 BHK79.22 Sq.mts. ( 853 Sq.ft. )29
11 Booked37% Booked
37% Booked
139 total apartments / 78 apartments booked. 56% apartments booked.
Work Description in Building A 9Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked

C 1

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
C 1Mar 20183410130195
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
3 BHK85.62 Sq.mts. ( 922 Sq.ft. )34
14 Booked41% Booked
41% Booked
3 BHK86.44 Sq.mts. ( 930 Sq.ft. )34
25 Booked73% Booked
73% Booked
3 BHK87.67 Sq.mts. ( 944 Sq.ft. )34
9 Booked26% Booked
26% Booked
3 BHK90.01 Sq.mts. ( 969 Sq.ft. )28
10 Booked35% Booked
35% Booked
130 total apartments / 58 apartments booked. 44% apartments booked.
Work Description in Building C 1Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked

D 7

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
D 7Mar 20182910130166
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK53.8 Sq.mts. ( 579 Sq.ft. )28
26 Booked92% Booked
92% Booked
2 BHK70.39 Sq.mts. ( 758 Sq.ft. )29
2 BHK73.74 Sq.mts. ( 794 Sq.ft. )29
6 Booked20% Booked
20% Booked
3 BHK84.64 Sq.mts. ( 911 Sq.ft. )24
3 BHK86.1 Sq.mts. ( 927 Sq.ft. )29
139 total apartments / 40 apartments booked. 28% apartments booked.
Work Description in Building D 7Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Tata Housing Development Company Limited
for Project
Amantra Phase 2
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation