Project overview

Akshar Business Park- Phase Iii is a MahaRERA Registered Project bearing MahaRERA Registration Number P51700024978. Akshar Business Park- Phase Iii is located at Plot No. 3, Sector-25. This is a New being developed by Akshar Developers.

Akshar Business Park- Phase Iii has Office space Apartments with carpet areas ranging from 150 to 407 Sq.ft. Carpet. The Project has total 202 of which 61 are currently available for sale.

Akshar Business Park- Phase Iii is being developed on a total land area of 99617 Sq.ft. out of which 10764 Sq.ft. i.e 11% is reserved for recreational purposes. Akshar Business Park- Phase Iii has 6 Wings / Towers Wing W- Block D,Wing X- Block D,Wing Y- Block D,Wing Z- Block D,Wing Z1- Block D,Wing Z2- Block D

ProjectDeveloperLocationPossession
Dipti Sky City Phase 2Dipti Home Makers Pvt Ltd54/3/B, 54/3/D, 57/1 Part30-06-2023 00:00:00
Snehal Paradise Wing AM/S Krishna DevelopersS No 2A H No 2B31-01-2020 00:00:00
Shree RajRajententerprisesSr No 39 H No 530-04-2019 00:00:00
Master BuildconMaster BuildconGut No 27 Plot No 1630-03-2022 00:00:00
Sai Tirth Phase IPinnacle CorporationS No. 2 H No 4/B Joveli Village Badlapur East 42150330-12-2023 00:00:00
J K KasturiJ.K.InfraS R No 130 Hissa No 330-12-2024 00:00:00
Bhakti ParkShivkrupa Enterprises730-03-2023 00:00:00
Priti ApartmentMahesh Mahadu Tare579 To 583 , 604 A And B30-12-2022 00:00:00
Raj Regalia Phase-1AAmrut Laxmi DevelopersS No. 54/3/E, 55/2, 55/330-06-2023 00:00:00
Sai PurabWestern Arch Developers9/1/230-09-2023 00:00:00
Akshar EvannaM/S Akshar Om ConstructionPlot No 137 Sector 53 Dronagiri Navi Mumbai28-02-2024 00:00:00
Rassaz Green Tower B And B1Rassaz Infrastructure Private Limited369/New69/Hn 1P 5A 370/New74/Hn2 3 4 5 6 7 371/New73/Hn5 377/New75/ 4P 7P 8P 9 10 11 12 1330-12-2026 00:00:00
Mohankheda GreensRajeshkumar Moolchand RupawatSurvey No 38 Hissa No 330-12-2023 00:00:00
Ozone GalaxyHallmark Infra Realty Llp64/10, 65/1, 65/3A, 65/3B, 66/530-12-2025 00:00:00
Shubham Galaxy - B WingNavkar Associates4948 4949 4950 4954 A B And 4969 A B30-12-2023 00:00:00
Shafique Khatimiti TowerRameez Shahnawaz MajeedCts 126430-12-2021 00:00:00
ElementsUma RealtyC. S. No. 27/130-12-2023 00:00:00
Shree Siddhivinayak Park Wing A1 And A2Satyashiv DevelopersS No 66 H No 7 S No76 H No 5 Part30-12-2022 00:00:00
Siyara IconShakti Realty1/34/35/36/44/79/3/80/131-12-2025 00:00:00
SpectrumKulin Enterprises3445-3454, 3455-347401-12-2024 00:00:00
Liana CMacrotech Developers Limited65 /15 A (Pt)31-03-2026 00:00:00
Sai LeelaSaijyotbuilders&DevelopersPlot No 20 Sector 30D30-06-2024 00:00:00
Shiv HeightsBalaji DevelopersSurvey No.15 Hissa No 731-03-2023 00:00:00
Shree Sai Saburi Apartment-Building BShree Saishraddha EnterprisesSurvey No 9/3 And 16/131-03-2025 00:00:00
PadmanabhYash Govinda Build Infra LlpTika No.10, C.T.S No.222B24-10-2023 00:00:00
Orchid A To LPalava Dwellers Pvt Ltd27Pt And 139/2 Pt30-06-2018 00:00:00
Tanisha HeightsM/S. Balaji DevelopersCts No. 1962-197230-03-2023 00:00:00
Mount CasaNagraj Mutha108B,112A/3, 113B31-12-2026 00:00:00
Upper Thane-Casa EdenMacrotech Developers Limited55/12 A31-03-2026 00:00:00
Omkar HeightsOmkar Builders & DevelopersCts No 114831-03-2024 00:00:00
Swami Samarth ApartmentMhatre Developers1231A30-03-2023 00:00:00
Yashoghar ChsBhalchandra Vinayak Wadnerkar6616 To 6619 , 6623 To 662630-12-2021 00:00:00
Vishwajeet Precious Phase IAbhijeet PrideSurvey No 32, Suryve No 33/1(P), Survey No 30, Hissa No 12 A02-03-2025 00:00:00
Vimal ShreeRitesh Ramesh JainOld Sno 215 Hno 1 New Sno 198 Hno 130-12-2023 00:00:00
Sai PalacePravin Narasi Manani3630-06-2022 00:00:00
Saishiv ComplexSaishiv ConstructionSurvey No 54 By 3 Hissa No 1 And 230-12-2023 00:00:00
Jay ResidencyMukesh Vithal GiteS.No. 111/H.No. 2/1/3/531-12-2024 00:00:00
Seven HeightsOvais Mudabbir BardiS No 15/1 20/2 Plot No 4 And Cts No 383831-12-2025 00:00:00
Jardino AMacrotech Developers Limited62/2 P, 62/3 P And 65/5C P31-08-2027 00:00:00
Mhatre CompoundLodha Developers Limited85/2 Pt30-06-2018 00:00:00
Aastha River ViewAastha Buildcon3 And 4 / Sec 1830-12-2022 00:00:00
Patels Prayosha - Pramukh SadanSahajanand DevelopersSurvey No 39A Hissa No 1A And 1B30-12-2023 00:00:00
Regency Park Iii Building No 2Johar Hasan ZojwallaCts No 575 S No 2 H No 9 And S No 2 H No 1/F/130-04-2024 00:00:00
Seasons SaharaSamarth Sai Builders & DevelopersS No 34 H No 14 S No 34 H No 1530-12-2023 00:00:00
IndrayaniM/S Vedant Chetana Enterprises NxS No.380, Cts No 133230-12-2023 00:00:00
Upper Thane-Iris Wing AMacrotech Developers Limited293/1 And 293/331-12-2027 00:00:00
Jivdani BuildingMildstone Enterprises Llp133231-12-2024 00:00:00
Yashraj HeightsVikrant Vikas Raikar731-01-2025 00:00:00
Vardhaman Tower Building Nos. 6 & 7Vardhaman Property DevelopersPlot Bearing Surveyno.26Hissa No1(Part)31-12-2023 00:00:00
Zircon HeightsIqbal Abdul Rauf Punjabi59/1, 83/5 Paiki, Cts No 482931-12-2024 00:00:00
Navare PlazaOm Developers8028 8029 803028-08-2022 00:00:00
Sai HeritageMitra HomesSurvey No 59 Hissa No 1 B30-03-2023 00:00:00
Shree Girijatmak Co Op Hou Soc LtdShree Saraswati DevelopersOld Survey No 47 Hissa No 2 Part Plot No 4 And 5 New Survey No 2/A/730-12-2021 00:00:00
Joshi ArcadeMeera DevelopersSurvey No 34-1/12, Hissa No. 3, Plot No. 731-03-2026 00:00:00
Sai Narayana ResidencyMm Landmark Realty LlpS.No.1431-12-2025 00:00:00
TiaraSagar EnterpriseS No 20 And Chalta No 2430-03-2024 00:00:00
Metro Aangan Phase - IMetro CreatorsS No 78 H No 7 P And 8 P30-12-2028 00:00:00
Prakruti SparshAvishkar BuildconS No 49, H No 10D30-12-2022 00:00:00
HarmonyBuildman Construction225/831-12-2019 00:00:00
N G Valencia Phase IiRna Builders (Ng)S No 335/3 Part Old 338/10 New30-09-2020 00:00:00
VandanamMetro BuildconSurvey No 68Plot No 28 Hissa No 1P 3P 4P30-12-2021 00:00:00
Shree Ram Co Operative Housing Society LimitedSantosh Vasant ChitnisS No 704/2 706/6 Old , 286/2 294/6 Cts No 821 And 82231-03-2025 00:00:00
Yashshree Co.Op.Hsg.SocNitant Narendra DesaiSurvey No. 28, Hissa No. 3/2/K30-09-2025 00:00:00
Vaishnavi HightsVaishnavi Builders & Developers58,H No.1 P.No. 1 & 224-06-2024 00:00:00
Anantam HeightsKanak RealtyS.No.101, C.T.S No.328030-06-2024 00:00:00
Capmatrix SquareCapmatrix Buildcon LlpB-33, 33 Part15-12-2022 00:00:00
Lodha Panacea IiMacrotech Developers Limited240/5A Pt30-09-2023 00:00:00
Sheth SupremeSheth Builders Private LimitedOld Survey No 159 Pt And New Survey No 20 Pt30-12-2024 00:00:00
One AksharAkshar RealtorsPlot No 730-12-2026 00:00:00
Vedant KalashShivalik DevelopersSurvey No 48 Hissa No 2 Plot No 5 And 630-03-2022 00:00:00
Fatima Enclave- C WingRais Aziz Qureshi46/4 , 46/531-12-2025 00:00:00
Shree Prabhucharan Chs.LtdShree Prabhucharan Co-Op Housing Society66/5/6731-03-2024 00:00:00
Aastha OmkarAastha RealtorsS. No. 56, H. No. 35/D/2B/1 To 35/D/2B/14 And H. No. 35/D/2B/15/131-12-2026 00:00:00
Sadguru Nakshtra Phase ISadguru DevelopersSurvey No 1204A And Survey No 118330-12-2023 00:00:00
Banjara Hills Sector 7Seema Developers127, 408/1, 407/230-12-2022 00:00:00
Lodha Panacea IMacrotech Developers Limited55Pt31-12-2021 00:00:00
Shreeram ResidencyRaghunath Kedari Phadtare690/330-12-2025 00:00:00
Jagjeet EnclaveJagjeet Shrusti Realtors29/1/C04-05-2024 00:00:00
Zunera Heights786 Micron Builders & Developers101/ 2 3 4 5 1230-12-2022 00:00:00
Fiora EMacrotech Developers Limited260/1A (Pt)31-03-2026 00:00:00
Savaliya HeightsShree Savaliya Homes LlpOld Sno 477 New Sno 119 Hno 131-12-2026 00:00:00
Ramakant ArcadeVastu EnterprisesCts No. 244, 25431-05-2023 00:00:00
Vedant Palacia Phase Iv Wing B-BrutusTharwani PropertiesSr.No.16,Hissa No.431-12-2026 00:00:00
Delta StellarNoble Organics Pvt. Ltd.Plot No D-43/3 And D-43/431-12-2028 00:00:00
Mauli SadanMauli ConstructionCts 9039 To 904304-02-2024 00:00:00
Shivaay AvyaanShreeram BuildconNew Survey 7,281(Old), Hissa No.230-11-2025 00:00:00
Dosti Desire - Phase 2D.D. Associates85/731-08-2027 00:00:00
Shubh Mangalam Phase IiShubh RealitySr No 106 Hissa No 125-12-2026 00:00:00
Gami Industrial Park - C BuildingGolden Falcon Pacific LtdPlot No C-39A31-12-2024 00:00:00
Shreeji CloudShreeji Lifespaces InfrastructurePlot No 78, Sector 21 At Ulwe30-06-2026 00:00:00
Priyal AumShree Mauli Chs LtdPlot No 47 Sector 2601-06-2024 00:00:00
Cyber Square - 1Greenscape It Park LlpD-102,D-103 &D-10431-03-2027 00:00:00
Delta LuxuriaShreenathji Organisers Pvt LtdPlot No 6130-04-2027 00:00:00
Giriraj SparshDura Vida Associates77 Tika No 18 Naupada30-06-2025 00:00:00
Sai CityOm Sai Builders & DevelopersSurvey No.3/1/E,3/1/D,3/1/C31-12-2031 00:00:00
Marathon Nextown JasperMarathon Ener-Gen140,141/2,141/1,142/3,220/1B31-12-2027 00:00:00
Shyam ParkVishnu Shyamlal SachdevCts . No. 2077031-12-2025 00:00:00
The Universe Neptune - BGayasuddin Riyazuddin KhanS No 112/130-06-2024 00:00:00
Siyara Fortune Building A Wing BShakti Realty8145, 8146, 8153, 8172, 8176 To 820231-12-2027 00:00:00
Satyaneelayam Co Op Hsg SocietyYash Infra749 B31-12-2025 00:00:00
Krishna GalaxyKrishna Builders & DevelopersSurvey No 42 Hissa No 230-06-2023 00:00:00
Villa SmaranOm Villa Buildtech LlpCts No 1194E And Cts No 1194A Sector 2930-03-2024 00:00:00
Virat MansionNeelyog DevelopersCts No 9907,9908 To 991330-12-2022 00:00:00
Chandrakant ResidencyAmogh ConstructionC.T.S No- 2 To 8 & C.T.S No- 169 To 178, C.T.S No- 295 To 30031-12-2027 00:00:00
Project Details
  • Project:
    Akshar Business Park- Phase Iii
  • Location:
  • Plot No. 3, Sector-25
  • Const. Stage:
    New
  • Possession:
    31 Jul 2022
Developer Details

  • Developer:
    Akshar Developers
  • Phone:
  • Address:
  • Big Splash
Project RERA Details
MAHA REARA No: P51700024978
Project Type Commercial
RERA Project Status New
Funding Bank HDFC BANK
Proposed Possession 31 Jul 2022
Revised Possession
Extended Possession
Litigations No Litigations
Last Modified 01 Apr 2023
Last Retrived 26 Jul 2025
Akshar Business Park- Phase Iii QR Code
Akshar Business Park- Phase Iii
MahaRERA - P51700024978
Apartment Details & Configuration
TypeArea
1 BHK15.87 Sq.mts. ( 171 Sq.ft. )
1 BHK24.07 Sq.mts. ( 259 Sq.ft. )
1 BHK30.34 Sq.mts. ( 327 Sq.ft. )
1 BHK31.4 Sq.mts. ( 338 Sq.ft. )
1 BHK37.55 Sq.mts. ( 404 Sq.ft. )
1 BHK37.82 Sq.mts. ( 407 Sq.ft. )
1 BHK55.09 Sq.mts. ( 593 Sq.ft. )
1 BHK82.37 Sq.mts. ( 887 Sq.ft. )
Office space29.94 Sq.mts. ( 322 Sq.ft. )
Office space30.46 Sq.mts. ( 328 Sq.ft. )
Office space30.48 Sq.mts. ( 328 Sq.ft. )
Office space44.9 Sq.mts. ( 483 Sq.ft. )
Office space17.89 Sq.mts. ( 193 Sq.ft. )
Office space18.13 Sq.mts. ( 195 Sq.ft. )
Office space26.12 Sq.mts. ( 281 Sq.ft. )
Office space37.81 Sq.mts. ( 407 Sq.ft. )
Office space17.78 Sq.mts. ( 191 Sq.ft. )
Office space17.98 Sq.mts. ( 194 Sq.ft. )
Office space25.9 Sq.mts. ( 279 Sq.ft. )
Office space25.93 Sq.mts. ( 279 Sq.ft. )
Office space30.61 Sq.mts. ( 329 Sq.ft. )
Office space30.62 Sq.mts. ( 330 Sq.ft. )
Office space45.13 Sq.mts. ( 486 Sq.ft. )
Office space13.94 Sq.mts. ( 150 Sq.ft. )
Office space14.02 Sq.mts. ( 151 Sq.ft. )
Office space18.12 Sq.mts. ( 195 Sq.ft. )
Office space21.13 Sq.mts. ( 227 Sq.ft. )
Office space29.67 Sq.mts. ( 319 Sq.ft. )
Office space29.68 Sq.mts. ( 319 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Akshar Business Park- Phase Iiilast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space100% completed
95% Complete
Completed
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station100% completed
95% Complete
Completed
Energy management100% completed
95% Complete
Completed
Fire Protection And Fire Safety Requirements100% completed
95% Complete
Completed
Landscaping & Tree Planting100% completed
95% Complete
Completed
Open Parking100% completed
95% Complete
Completed
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
95% Complete
Completed
Solid Waste Management And Disposal
Na
Storm Water Drains100% completed
95% Complete
Completed
Street Lighting100% completed
95% Complete
Completed
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting100% completed
95% Complete
Completed
Water Supply100% completed
95% Complete
Completed
Buildings / Wings in Akshar Business Park- Phase Iii
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Akshar Business Park- Phase Iii by Akshar Developerslast updated on 26 Jul 2025 as per information obtained from MARA RERA.

99617 Sq. ft.

Project Area

10764 Sq. ft.

Recreational Open Space

Total 6

Wings / Towers in Project

Apartments Statistics

202 apartments in total
Total
202
Booked
141
Available
61

Saleable Area Statistics (Sq. ft.)

67301 Total
Total
67301
Booked
44344
Available
22957
Total 202 apartments in project. 141 apartments booked. 69% apartments booked.
Total 67301 Sq.ft. saleable area. 44344 saleable area booked.
66% area booked.

Wing W- Block D

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing W- Block DJul 20214110000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK15.87 Sq.mts. ( 171 Sq.ft. )3
3 Booked100% Booked
100% Booked
1 BHK24.07 Sq.mts. ( 259 Sq.ft. )3
2 Booked66% Booked
66% Booked
1 BHK30.34 Sq.mts. ( 327 Sq.ft. )8
6 Booked75% Booked
75% Booked
1 BHK31.4 Sq.mts. ( 338 Sq.ft. )4
3 Booked75% Booked
75% Booked
1 BHK37.55 Sq.mts. ( 404 Sq.ft. )3
2 Booked66% Booked
66% Booked
1 BHK37.82 Sq.mts. ( 407 Sq.ft. )3
None Booked0% Booked
0% Booked
1 BHK55.09 Sq.mts. ( 593 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK82.37 Sq.mts. ( 887 Sq.ft. )1
None Booked0% Booked
0% Booked
26 total apartments / 16 apartments booked. 61% apartments booked.
Work Description in Building Wing W- Block DCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
Completed 100% done
100% Booked
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Wing X- Block D

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing X- Block DJul 20214110000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
Office space29.94 Sq.mts. ( 322 Sq.ft. )8
7 Booked87% Booked
87% Booked
Office space30.34 Sq.mts. ( 327 Sq.ft. )16
14 Booked87% Booked
87% Booked
Office space30.46 Sq.mts. ( 328 Sq.ft. )1
1 Booked100% Booked
100% Booked
Office space30.48 Sq.mts. ( 328 Sq.ft. )3
2 Booked66% Booked
66% Booked
Office space44.9 Sq.mts. ( 483 Sq.ft. )4
4 Booked100% Booked
100% Booked
32 total apartments / 28 apartments booked. 87% apartments booked.
Work Description in Building Wing X- Block DCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
Completed 100% done
100% Booked
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Wing Y- Block D

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing Y- Block DJul 20214110000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
Office space17.89 Sq.mts. ( 193 Sq.ft. )1
None Booked0% Booked
0% Booked
Office space18.13 Sq.mts. ( 195 Sq.ft. )3
2 Booked66% Booked
66% Booked
Office space26.12 Sq.mts. ( 281 Sq.ft. )4
1 Booked25% Booked
25% Booked
Office space29.94 Sq.mts. ( 322 Sq.ft. )8
8 Booked100% Booked
100% Booked
Office space30.34 Sq.mts. ( 327 Sq.ft. )16
14 Booked87% Booked
87% Booked
Office space30.46 Sq.mts. ( 328 Sq.ft. )1
1 Booked100% Booked
100% Booked
Office space30.48 Sq.mts. ( 328 Sq.ft. )3
1 Booked33% Booked
33% Booked
Office space37.55 Sq.mts. ( 404 Sq.ft. )4
1 Booked25% Booked
25% Booked
Office space37.81 Sq.mts. ( 407 Sq.ft. )1
None Booked0% Booked
0% Booked
Office space37.82 Sq.mts. ( 407 Sq.ft. )3
1 Booked33% Booked
33% Booked
Office space44.9 Sq.mts. ( 483 Sq.ft. )4
2 Booked50% Booked
50% Booked
48 total apartments / 31 apartments booked. 64% apartments booked.
Work Description in Building Wing Y- Block DCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
Completed 100% done
100% Booked
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Wing Z- Block D

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing Z- Block DJul 20214110000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
Office space17.78 Sq.mts. ( 191 Sq.ft. )1
1 Booked100% Booked
100% Booked
Office space17.98 Sq.mts. ( 194 Sq.ft. )3
3 Booked100% Booked
100% Booked
Office space25.9 Sq.mts. ( 279 Sq.ft. )3
2 Booked66% Booked
66% Booked
Office space25.93 Sq.mts. ( 279 Sq.ft. )1
None Booked0% Booked
0% Booked
Office space29.94 Sq.mts. ( 322 Sq.ft. )8
6 Booked75% Booked
75% Booked
Office space30.34 Sq.mts. ( 327 Sq.ft. )16
12 Booked75% Booked
75% Booked
Office space30.61 Sq.mts. ( 329 Sq.ft. )1
1 Booked100% Booked
100% Booked
Office space30.62 Sq.mts. ( 330 Sq.ft. )3
1 Booked33% Booked
33% Booked
Office space45.13 Sq.mts. ( 486 Sq.ft. )4
None Booked0% Booked
0% Booked
40 total apartments / 26 apartments booked. 65% apartments booked.
Work Description in Building Wing Z- Block DCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
Completed 100% done
100% Booked
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Wing Z1- Block D

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing Z1- Block DJul 20214110000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
Office space29.94 Sq.mts. ( 322 Sq.ft. )8
7 Booked87% Booked
87% Booked
Office space30.34 Sq.mts. ( 327 Sq.ft. )16
13 Booked81% Booked
81% Booked
Office space30.46 Sq.mts. ( 328 Sq.ft. )1
1 Booked100% Booked
100% Booked
Office space30.48 Sq.mts. ( 328 Sq.ft. )3
2 Booked66% Booked
66% Booked
Office space44.9 Sq.mts. ( 483 Sq.ft. )4
None Booked0% Booked
0% Booked
32 total apartments / 23 apartments booked. 71% apartments booked.
Work Description in Building Wing Z1- Block DCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
Completed 100% done
100% Booked
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Wing Z2- Block D

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing Z2- Block DJul 20214110000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
Office space13.94 Sq.mts. ( 150 Sq.ft. )3
3 Booked100% Booked
100% Booked
Office space14.02 Sq.mts. ( 151 Sq.ft. )1
1 Booked100% Booked
100% Booked
Office space18.12 Sq.mts. ( 195 Sq.ft. )3
3 Booked100% Booked
100% Booked
Office space21.13 Sq.mts. ( 227 Sq.ft. )3
3 Booked100% Booked
100% Booked
Office space29.67 Sq.mts. ( 319 Sq.ft. )3
3 Booked100% Booked
100% Booked
Office space29.68 Sq.mts. ( 319 Sq.ft. )1
1 Booked100% Booked
100% Booked
Office space30.34 Sq.mts. ( 327 Sq.ft. )4
2 Booked50% Booked
50% Booked
Office space37.55 Sq.mts. ( 404 Sq.ft. )3
1 Booked33% Booked
33% Booked
Office space37.82 Sq.mts. ( 407 Sq.ft. )3
None Booked0% Booked
0% Booked
24 total apartments / 17 apartments booked. 70% apartments booked.
Work Description in Building Wing Z2- Block DCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
Completed 100% done
100% Booked
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Akshar Developers
for Project
Akshar Business Park- Phase Iii
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation