Project overview

Acciano Bianca is a MahaRERA Registered Project bearing MahaRERA Registration Number P99000035182. Acciano Bianca is located at 41/1, 2, 3P, 4, 5, 6. This is a New being developed by M/S. Ideal Enterprises.

Acciano Bianca has Bungalow Apartments with carpet areas ranging from 1060 to 1060 Sq.ft. Carpet. The Project has total 10 of which 6 are currently available for sale.

Acciano Bianca is being developed on a total land area of 31611 Sq.ft. out of which 3161 Sq.ft. i.e 10% is reserved for recreational purposes. Acciano Bianca has 10 Wings / Towers Bungalow No 1,Bungalow No 10,Bungalow No 2,Bungalow No 3,Bungalow No 4,Bungalow No 5,Bungalow No 6,Bungalow No 7,Bungalow No 8,Bungalow No 9

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Acciano Bianca
  • Location:
  • 41/1, 2, 3P, 4, 5, 6
  • Const. Stage:
    New
  • Possession:
    31 Dec 2025
Developer Details

  • Developer:
    M/S. Ideal Enterprises
  • Phone:
  • Address:
  • Furtado Residency
Project RERA Details
MAHA REARA No: P99000035182
Project Type Residential / Group Housing
RERA Project Status New
Architect Megha Urbanscapes
Funding Bank BASSEIN CATHOLIC COOPERATIVE BANK LIMITED
Proposed Possession 31 Dec 2025
Revised Possession
Extended Possession
Litigations No Litigations
Last Modified 10 May 2022
Last Retrived 28 Jul 2025
Acciano Bianca QR Code
Acciano Bianca
MahaRERA - P99000035182
Apartment Details & Configuration
TypeArea
Bungalow96.43 Sq.mts. ( 1038 Sq.ft. )
Bungalow122.69 Sq.mts. ( 1321 Sq.ft. )
Bungalow97.67 Sq.mts. ( 1051 Sq.ft. )
Bungalow106.11 Sq.mts. ( 1142 Sq.ft. )
Bungalow96.42 Sq.mts. ( 1038 Sq.ft. )
Bungalow116.28 Sq.mts. ( 1252 Sq.ft. )
Bungalow98.5 Sq.mts. ( 1060 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Acciano Biancalast updated on 28 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Not Available
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station
Not Available
Energy management
Na
Fire Protection And Fire Safety Requirements
Na
Landscaping & Tree Planting
Not Available
Open Parking
Not Available
Sewerage (Chamber, Lines, Septic Tank , STP)
Not Available
Solid Waste Management And Disposal
Not Available
Storm Water Drains
Not Available
Street Lighting
Not Available
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting
Not Available
Water Supply
Not Available
Buildings / Wings in Acciano Bianca
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Acciano Bianca by M/S. Ideal Enterpriseslast updated on 28 Jul 2025 as per information obtained from MARA RERA.

31611 Sq. ft.

Project Area

3161 Sq. ft.

Recreational Open Space

Total 10

Wings / Towers in Project

Apartments Statistics

10 apartments in total
Total
10
Booked
4
Available
6

Saleable Area Statistics (Sq. ft.)

11029 Total
Total
11029
Booked
4256
Available
6773
Total 10 apartments in project. 4 apartments booked. 40% apartments booked.
Total 11029 Sq.ft. saleable area. 4256 saleable area booked.
39% area booked.

Bungalow No 1

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Bungalow No 1Dec 20252100010
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
Bungalow96.43 Sq.mts. ( 1038 Sq.ft. )1
1 Booked100% Booked
100% Booked
1 total apartments / 1 apartments booked. 100% apartments booked.
Work Description in Building Bungalow No 1Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor

Bungalow No 10

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Bungalow No 10Dec 20252100010
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
Bungalow122.69 Sq.mts. ( 1321 Sq.ft. )1
None Booked0% Booked
0% Booked
1 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Bungalow No 10Completion
Basement (if any)
Excavation
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Plinth
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor

Bungalow No 2

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Bungalow No 2Dec 20252100010
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
Bungalow97.67 Sq.mts. ( 1051 Sq.ft. )1
None Booked0% Booked
0% Booked
1 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Bungalow No 2Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor

Bungalow No 3

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Bungalow No 3Dec 20252100010
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
Bungalow97.67 Sq.mts. ( 1051 Sq.ft. )1
None Booked0% Booked
0% Booked
1 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Bungalow No 3Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor

Bungalow No 4

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Bungalow No 4Dec 20252100010
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
Bungalow106.11 Sq.mts. ( 1142 Sq.ft. )1
1 Booked100% Booked
100% Booked
1 total apartments / 1 apartments booked. 100% apartments booked.
Work Description in Building Bungalow No 4Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor

Bungalow No 5

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Bungalow No 5Dec 20252100010
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
Bungalow96.42 Sq.mts. ( 1038 Sq.ft. )1
1 Booked100% Booked
100% Booked
1 total apartments / 1 apartments booked. 100% apartments booked.
Work Description in Building Bungalow No 5Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor

Bungalow No 6

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Bungalow No 6Dec 20252100010
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
Bungalow96.42 Sq.mts. ( 1038 Sq.ft. )1
None Booked0% Booked
0% Booked
1 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Bungalow No 6Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress50% done
50% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress50% done
50% Booked
Stilt Floor

Bungalow No 7

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Bungalow No 7Dec 20252100010
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
Bungalow96.42 Sq.mts. ( 1038 Sq.ft. )1
1 Booked100% Booked
100% Booked
1 total apartments / 1 apartments booked. 100% apartments booked.
Work Description in Building Bungalow No 7Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress50% done
50% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress50% done
50% Booked
Stilt Floor

Bungalow No 8

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Bungalow No 8Dec 20252100010
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
Bungalow116.28 Sq.mts. ( 1252 Sq.ft. )1
None Booked0% Booked
0% Booked
1 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Bungalow No 8Completion
Basement (if any)
Excavation
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Plinth
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor

Bungalow No 9

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Bungalow No 9Dec 20251100010
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
Bungalow98.5 Sq.mts. ( 1060 Sq.ft. )1
None Booked0% Booked
0% Booked
1 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Bungalow No 9Completion
Basement (if any)
Excavation
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Plinth
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
Channel Partners
Channel Partners Registered by Developer
M/S. Ideal Enterprises
for Project
Acciano Bianca
last updated on 28 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation