Project overview

Aaradhya Nine is a MahaRERA Registered Project bearing MahaRERA Registration Number P51800000229. Aaradhya Nine is located at 194-A/9/6. This is a New being developed by Micl Realty Llp.

Aaradhya Nine has 1 BHK, 1 BHK\REHAB, 1RK & 2 BHK Apartments with carpet areas ranging from 332 to 544 Sq.ft. Carpet. The Project has total 251 of which 5 are currently available for sale.

Aaradhya Nine is being developed on a total land area of 26498 Sq.ft. Aaradhya Nine has 4 Wings / Towers Wing A,Wing B,Wing C,Wing D

ProjectDeveloperLocationPossession
Vinayak Heights Phase 1 Vinayak Associate194A Part Ghatkoper And Cts 1B Part Of Village Vikroli Taluka Kurla Mumbai25-12-2020 00:00:00
Anchor ResidencyAnchor Sky Scrapers Llp3386 To 341431-12-2019 00:00:00
Neelkanth Regent Building 3 - Wing A And Wing BMukesh Patel & Others5686 Pt F P No 265 Of Tps Iii30-11-2018 00:00:00
Kesar ScionKesar Housing & Development Co5692 And 569330-12-2021 00:00:00
Natasha RoyaleNatasha Developers Pvt Ltd567430-12-2021 00:00:00
Integrated ArcadeSadgurukrupa Developers181 And 18231-03-2019 00:00:00
O And S Business SuitesSuchita Orange Hdm ProjectFinal Plot No 11 Cts No 3214 Tps Ii30-12-2025 00:00:00
Sofrance Wing BDaga Developers Private Limited194A Part Of Village Ghatkopar And 1 Part Of Village Vikhroli30-12-2022 00:00:00
Siddh DarshanDeep Associates5105 - 5120 / 30-3131-12-2018 00:00:00
Yashaswati Chs LtdLakshmi Builders And Developers189 Pt, 189/11 To 189/20 Cs No 23631-07-2023 00:00:00
Damji Shamji Corporate Square - A WingCoronate ConstructionsCts No 5635-B31-05-2019 00:00:00
Neelyog VeydaantaRatan Builders4002A, 4000, 3998P, 4001, 3999P30-03-2023 00:00:00
Aaradhya NineMicl Realty Llp194-A/9/630-03-2021 00:00:00
Mahavir AquilaMilestone DevelopersFinal Plot No 163B-131-05-2019 00:00:00
Shree Pinal Project APinal Realty LlpCts No - 4614A, 4615 To 462421-11-2024 00:00:00
Rajshree Eleven EastPanchsheel 1 Upgrade Llp5681 Pt31-12-2024 00:00:00
Antariksh AvalonAntariksh Realtors Private Limited5740 Part31-12-2025 00:00:00
Royal AltezzaShri Ganesh Developers5740 Pt/236A31-08-2025 00:00:00
Prathmesh DarshanJaydeep Mahalaxmi Construction5705/830-12-2023 00:00:00
AnthuriumVibha Propoerties Llp5681 Part30-05-2023 00:00:00
Royal OrchidShri Ganesh DevelopersPt 184, 184/90 To 184/9931-12-2019 00:00:00
Sofrance Wing ADaga Developers Private LimitedKurla, 400075, Mumbai Suburban31-12-2016 00:00:00
Kavya AshwameghKavya Construction Company400075, Mumbai, Mumbai Suburban31-12-2020 00:00:00
Rajas ResidencyPramod Shridhar MohiteGhatkopar, Pant Nagar, Ob No 1 / Cts No 185 Pt / Survey No 236-A31-12-2017 00:00:00
Sai PrajaktaSunil Mangilal JainOld Sno 372 New Sno 79 Hno 231-12-2027 00:00:00
Smita Nagar Chs LtdExcel EnterprisesR.B Mehta Marg18-11-2022 00:00:00
Sai DarshanSai Darshan587830-12-2021 00:00:00
Sips JalaramSips Buildcon353B-32, 353B-3130-06-2025 00:00:00
Drushti EmeraldSamarth Drushti DevelopersMumbai Suburban31-12-2026 00:00:00
Neelyog RegentRatan Builders3997 Pt 3998 Pt 3990 Pt 3996 Pt31-03-2028 00:00:00
Damji Shamji Corporate Square - Wing CCoronate Constructions5635B P30-12-2024 00:00:00
Shree SuryodayaHariyana Developers19330-06-2024 00:00:00
Rishabraj ViciniaH Rishabraj Developers195/10 Of Village Ghatkoper29-02-2024 00:00:00
Aaradhya OneparkMicl Creators Llp353/5, 353/7, 353/8, 353/9, 353/46, 353/17, 353/11, 353/1231-07-2028 00:00:00
Antariksh AlphaAntariksh Lifespaces Private Limited5684 Pt30-06-2028 00:00:00
AurusM/S. B Chopda Realtors195/17831-03-2027 00:00:00
One CrystalGoldnest Spaces LlpFp 149 150 151 Of Tps Iii31-12-2025 00:00:00
One ApolloGoldnest Spaces LlpFp No 149 150 151 Of Tps Iii31-12-2025 00:00:00
Hs AlagHs Alag Realty Llp40007531-12-2024 00:00:00
Rajshree StatusJetalaal Laxmiechand DedhiaBuilding Number 15 Cts No. 5681 Part30-12-2020 00:00:00
Viki HeightsDivij Developers 586730-11-2018 00:00:00
Kashish Park GhatkoparLadam Homes Pvt Ltd.184C Pt/ Cts No. 23130-06-2021 00:00:00
SamarpanHs ConstructionC.T.S.No.184 (Pt.)30-06-2025 00:00:00
Bhoomi AntaraBhoomi LifestylePlot No. 63 Cts 195/11128-02-2027 00:00:00
Alag AnantaAlag Square Llp19730-09-2024 00:00:00
Kevli Plaza – A Wing And Kevli Darshan – B WingM/S R K And Company Pvt Ltd5105 To 5111, F.P No 30 Tps-I Ghatkopar (E) In N Ward, 5120 (Pt) Of Village Ghatkopar Kirol31-12-2028 00:00:00
The LegendEmpire Maitri Flora Constructions Llp5659Pt And 5660Pt Or Fp No 348 And 349 Of Tps Iii30-09-2026 00:00:00
Alag AshtapadContour Developers LlpMumbai Suburban31-12-2024 00:00:00
Alag AranyaAlag Aarchie LlpGhatkopar31-12-2024 00:00:00
Omkaar PrideVardhman DevelopersC.T.S. No. 193A Part31-12-2024 00:00:00
Terraform DwarkaMoney Magnum Nest Pvt Ltd5808Pt Corr Final Plot No274a Pt Of Tpsiii Of Ghatkopar Kirol Adj 60 Ft Wide Jawahar Rd At North30-12-2023 00:00:00
Natasha AvenueNatasha Enterprises568130-12-2023 00:00:00
Terraform DwarkaMoney Magnum Nest Pvt Ltd5808Pt Corr Final Plot No274a Pt Of Tpsiii Of Ghatkopar Kirol Adj 18.3 Mtr Wide Jawahar Rd At North30-12-2023 00:00:00
Shree Basant Vihar Chs LtdAdeshwar Associates And Developers17130-12-2021 00:00:00
Jai Savitri Chs LtdA&Amp;A Aristocrat Realty Private Limited400077, Mumbai Suburban31-03-2019 00:00:00
EmbassyDrushti Realtors Private LimitedCts No 192/1 Pt30-12-2020 00:00:00
Alag ArtisAlag Lifespace LlpGhatkopar East31-12-2024 00:00:00
Drushti SapphireDrushti Realtors Pvt Ltd192 1 Pt30-04-2025 00:00:00
Alag OliveAlag Olive Llp184C31-12-2024 00:00:00
Nav VaniGiriraj Builders And DevelopersPlot No 35328 Tps 3 Cts No 57432030-12-2020 00:00:00
Dream Arihant OasisDream Arihant Infrastructure CompanyF P No 83, Cts No 591330-12-2023 00:00:00
Vishal SagarJ R Properties LlpBldg No 12630-12-2022 00:00:00
Choice Ambe DarshanChoice DeveloperCts No 5661 Survey No 236-A Building No 3931-12-2025 00:00:00
Avani SignatureAvani BuildconF.P No.17, C.T.S. No.3747 To 379731-03-2026 00:00:00
Palazzo 90Blue Crest Developers Llp195/6530-06-2025 00:00:00
Dhoot Sapphire ResidencyDhoot Developers Pvt. Ltd.587231-12-2028 00:00:00
Om PriyadarshaniAakruti Enterprises184(Pt.)30-09-2026 00:00:00
Om Makarand HeightsD D InfraS. No-236(A), Cts No-184(Pt)31-12-2026 00:00:00
Om NeeldharaD. D. Dezines Group228, 229 And 24430-06-2028 00:00:00
Aakruti SolitaireSaptrishi Classic LlpCts No 185 (Part) S No 236A (Part)01-02-2027 00:00:00
Nav Ashish Premises Co-Operative Society LtdS K Developers218 Ghatkopar - Kirol26-04-2029 00:00:00
Divine UltimusShree Dham Developers184 Pt, 236A31-12-2027 00:00:00
Pant Nagar Shri Ram C.H.S. Ltd. Building No.105Dev Reality Corporation400075, Mumbai Suburban31-12-2011 00:00:00
Pant Nagar Shankar Sadan Chs LtdK. Nakrani Associates568131-08-2019 00:00:00
K K SolitaireNavin M Mehta278 Of Tps Iii, Cts Number 570431-07-2019 00:00:00
AashrinaM/S. Vira Realspace LlpCts No. 4731, Plot No. 28, S.S. No. Xviii30-09-2022 00:00:00
Terraform Dwarka - Wing CMoney Magnum Nest Pvt Ltd5808Pt Corr Final Plot No274a Pt Of Tps Iii Of Ghatkopar Kirol Adj 18.3 Mtr Wide Jawahar Rd At North30-12-2024 00:00:00
Kaveri HeightsShree Mishal Sundaram Realty Ventures LlpSant Gyaneshwar Marg, Pant Nagar31-12-2024 00:00:00
Jade Gardens Tower AJairajhappyhomesPlot Nos 160-161 Bldg Nos 182-18331-10-2025 00:00:00
Anand Jeevan Ratna ChslAnand Jeevan Ratna Co-Operative Housing Society LimitedCts No 5741/36 Of Village Ghatkopar Kirol31-03-2024 00:00:00
Jade Gardens Tower BJairajhappyhomesCts No 5685 Part Bldg No 179 & 180 Tower B31-10-2025 00:00:00
Shubham Avalon Co-Operative Housing Society LimitedAvvad Housing LlpFinal Plot No. - 311 (Pt), Plot Bearing Survey No. - 236-A, Cts No. - 5662 (Pt)31-12-2024 00:00:00
Poonam CelestePl7 Realty Pvt. Ltd.583530-11-2024 00:00:00
Ghatkopar Avenue Aaradhya One Earth H Phase ViiMan Realtors And Holding Private LimitedS No 236A Part And Cts 194A30-06-2025 00:00:00
Sidhivinayak OrchidSidhivinayak Developers186 Part31-12-2026 00:00:00
Garodia Nagar Mahavir Dham Chs LtdGarodia Nagar Mahavir Dham Chs Ltd195/4731-12-2025 00:00:00
Hema Apartments Co-Operative Housing Society LimitedHema Appartments Co-Operative Housing Society Limited353B-3831-03-2025 00:00:00
Dynamic Ultima - BlissTriveni Life Style Developers LlpSurvey No. 121 H.No 1,230-12-2020 00:00:00
ShrirangVirendra Natwarlal Sheth194 A Pt29-06-2020 00:00:00
Suyog ChsAdityaraj Builders35128-02-2021 00:00:00
Jade Gardens Tower CJairajhappyhomesCts No 5685 Part Bldg No.173 & 17431-10-2025 00:00:00
Rajshree Forty Three EastRajshree Shivkunj Developers Llp5661 Pt30-06-2025 00:00:00
Tiara By Swastik EmpireM/S Swastik Empire Developers Llp5683 (Pt) Survey No 22931-12-2025 00:00:00
Neelyog AaranaNeelyog Builders Private LimitedFp No.20 Of Tps Ghatkopar No Ii Tps Scheme And Corresponding Cts No 3809 To 3833 Of Village Ghatkopar Kirol At Laxminarayan Lane And Tps Lane No 4 Ghatkopar West Mumbai 40008630-06-2028 00:00:00
Park ViewMontage Infra Developers Private Limited (Earlier Known As Vinayak Developers)195/7931-12-2027 00:00:00
East PointVital Developers Pvt. Ltd.573631-01-2020 00:00:00
Kul TulipKumar Builders Mumbai Realty Pvt Ltd236A And Cts No. 194-A/9/69 Pt Ghatkopar13-12-2019 00:00:00
The MetropoleRaveshia RealtorsF.P No 36 And 37 Of Tps Ii30-03-2024 00:00:00
Project Details
  • Project:
    Aaradhya Nine
  • Location:
  • 194-A/9/6
  • Const. Stage:
    New
  • Possession:
    30 Mar 2021
Developer Details

  • Developer:
    Micl Realty Llp
  • Phone:
  • Address:
  • Krushal Commercial Complex
Project RERA Details
MAHA REARA No: P51800000229
Project Type Residential / Group Housing
RERA Project Status New
Architect Architecture Plus
Funding Bank KOTAK MAHINDRA BANK LIMITED
Proposed Possession 30 Mar 2021
Revised Possession
Extended Possession
Litigations No Litigations
Last Modified 25 May 2018
Last Retrived 26 Jul 2025
Aaradhya Nine QR Code
Aaradhya Nine
MahaRERA - P51800000229
Apartment Details & Configuration
TypeArea
3 BHK79.25 Sq.mts. ( 853 Sq.ft. )
3 BHK90.95 Sq.mts. ( 979 Sq.ft. )
2 BHK56.11 Sq.mts. ( 604 Sq.ft. )
2 BHK66.61 Sq.mts. ( 717 Sq.ft. )
1 BHK\REHAB41.25 Sq.mts. ( 444 Sq.ft. )
1 BHK\REHAB41.43 Sq.mts. ( 446 Sq.ft. )
1 BHK41.53 Sq.mts. ( 447 Sq.ft. )
1RK30.84 Sq.mts. ( 332 Sq.ft. )
2 BHK50.54 Sq.mts. ( 544 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Aaradhya Ninelast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station100% completed
95% Complete
No Receiving Station
Energy management
Na
Fire Protection And Fire Safety Requirements100% completed
95% Complete
-
FITNESS CENTER AT TERRACE OF WING A AND B100% completed
95% Complete
Only For Members Of A And B Wing
Landscaping & Tree Planting100% completed
95% Complete
-
Open Parking
Na
RECREATION AREA AT TERRACE OF WING A AND B100% completed
95% Complete
Only For Members Of A And B Wing
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
95% Complete
No Septic Tank
Solid Waste Management And Disposal100% completed
95% Complete
-
Storm Water Drains100% completed
95% Complete
-
Street Lighting
Na
Treatment And Disposal Of Sewage And Sullage Water100% completed
95% Complete
-
Water Conservation, Rain water Harvesting100% completed
95% Complete
Only Rain Water Harvesting
Water Supply100% completed
95% Complete
-
Buildings / Wings in Aaradhya Nine
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Aaradhya Nine by Micl Realty Llplast updated on 26 Jul 2025 as per information obtained from MARA RERA.

26498 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 4

Wings / Towers in Project

Apartments Statistics

251 apartments in total
Total
251
Booked
246
Available
5

Saleable Area Statistics (Sq. ft.)

151826 Total
Total
151826
Booked
147435
Available
4391
Total 251 apartments in project. 246 apartments booked. 98% apartments booked.
Total 151826 Sq.ft. saleable area. 147435 saleable area booked.
97% area booked.

Wing A

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing ASep 2020161110039
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
3 BHK79.25 Sq.mts. ( 853 Sq.ft. )30
26 Booked86% Booked
86% Booked
3 BHK90.95 Sq.mts. ( 979 Sq.ft. )29
28 Booked96% Booked
96% Booked
59 total apartments / 54 apartments booked. 91% apartments booked.
Work Description in Building Wing ACompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Wing B

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing BSep 2020161110057
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK56.11 Sq.mts. ( 604 Sq.ft. )30
30 Booked100% Booked
100% Booked
2 BHK66.61 Sq.mts. ( 717 Sq.ft. )29
29 Booked100% Booked
100% Booked
59 total apartments / 59 apartments booked. 100% apartments booked.
Work Description in Building Wing BCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Wing C

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing CSep 2020161110029
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK\REHAB41.25 Sq.mts. ( 444 Sq.ft. )15
15 Booked100% Booked
100% Booked
1 BHK\REHAB41.43 Sq.mts. ( 446 Sq.ft. )44
44 Booked100% Booked
100% Booked
59 total apartments / 59 apartments booked. 100% apartments booked.
Work Description in Building Wing CCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Wing D

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing DSep 2020161110029
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK41.43 Sq.mts. ( 446 Sq.ft. )4
4 Booked100% Booked
100% Booked
1 BHK41.53 Sq.mts. ( 447 Sq.ft. )4
4 Booked100% Booked
100% Booked
1 BHK\REHAB41.53 Sq.mts. ( 447 Sq.ft. )11
11 Booked100% Booked
100% Booked
1 BHK\REHAB41.43 Sq.mts. ( 446 Sq.ft. )11
11 Booked100% Booked
100% Booked
1 BHK\REHAB41.25 Sq.mts. ( 444 Sq.ft. )15
15 Booked100% Booked
100% Booked
1RK30.84 Sq.mts. ( 332 Sq.ft. )15
15 Booked100% Booked
100% Booked
2 BHK50.54 Sq.mts. ( 544 Sq.ft. )14
14 Booked100% Booked
100% Booked
74 total apartments / 74 apartments booked. 100% apartments booked.
Work Description in Building Wing DCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Micl Realty Llp
for Project
Aaradhya Nine
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation