Project overview

Aadarsh Chs is a MahaRERA Registered Project bearing MahaRERA Registration Number P51800006807. Aadarsh Chs is located at Mumbai Suburban, 400083. This is a On-Going Project being developed by Aditya Enterprises.

Aadarsh Chs has 1 BHK, 2 BHK & SHOP Apartments with carpet areas ranging from 111 to 85 Sq.ft. Carpet. The Project has total 101 of which 11 are currently available for sale.

Aadarsh Chs is being developed on a total land area of 9192 Sq.ft. Aadarsh Chs has 1 Wings / Towers Bldg No 54

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Aadarsh Chs
  • Location:
  • Mumbai Suburban, 400083
  • Const. Stage:
    On-Going Project
  • Possession:
    30 Sep 2016
Developer Details

  • Developer:
    Aditya Enterprises
  • Phone:
  • Address:
  • 101, 1St Floor,, Purnima Chs Ltd.,Bldg No 3,, Ramakant Deshmukh Marg,Tagore Nagar, Near Pmc Bank, Vikhroli East, 400083
Project RERA Details
MAHA REARA No: P51800006807
Project Type Others
RERA Project Status On-Going Project
Funding Bank YES BANK LTD
Proposed Possession 30 Sep 2016
Revised Possession 30 Aug 2019
Extended Possession 28 Feb 2021
Litigations No Litigations
Last Modified 06 Mar 2024
Last Retrived 28 Jul 2025
Aadarsh Chs QR Code
Aadarsh Chs
MahaRERA - P51800006807
Apartment Details & Configuration
TypeArea
1 BHK30 Sq.mts. ( 323 Sq.ft. )
1 BHK30.25 Sq.mts. ( 326 Sq.ft. )
2 BHK43.77 Sq.mts. ( 471 Sq.ft. )
2 BHK43.83 Sq.mts. ( 472 Sq.ft. )
2 BHK43.88 Sq.mts. ( 472 Sq.ft. )
2 BHK46.18 Sq.mts. ( 497 Sq.ft. )
2 BHK46.27 Sq.mts. ( 498 Sq.ft. )
2 BHK46.3 Sq.mts. ( 498 Sq.ft. )
SHOP32.87 Sq.mts. ( 354 Sq.ft. )
SHOP7.49 Sq.mts. ( 81 Sq.ft. )
SHOP7.6 Sq.mts. ( 82 Sq.ft. )
SHOP7.67 Sq.mts. ( 83 Sq.ft. )
SHOP7.87 Sq.mts. ( 85 Sq.ft. )
SHOP10.27 Sq.mts. ( 111 Sq.ft. )
SHOP15 Sq.mts. ( 161 Sq.ft. )
SHOP15.71 Sq.mts. ( 169 Sq.ft. )
SHOP16.6 Sq.mts. ( 179 Sq.ft. )
SHOP24.84 Sq.mts. ( 267 Sq.ft. )
SHOP26.07 Sq.mts. ( 281 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Aadarsh Chslast updated on 28 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station65% completed
65% Complete
Only Meter Room Provided
Energy management
Na
Fire Protection And Fire Safety Requirements65% completed
65% Complete
Work In Progress
Landscaping & Tree Planting
Only Tree Plantation
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)64% completed
64% Complete
Only Within Plot
Solid Waste Management And Disposal
Na
Storm Water Drains100% completed
95% Complete
Only Within Plot
Street Lighting
Na
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting
Only Rain Water Harvesting
Water Supply64% completed
64% Complete
Work In Progress
Buildings / Wings in Aadarsh Chs
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Aadarsh Chs by Aditya Enterpriseslast updated on 28 Jul 2025 as per information obtained from MARA RERA.

9192 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 1

Wings / Towers in Project

Apartments Statistics

101 apartments in total
Total
101
Booked
90
Available
11

Saleable Area Statistics (Sq. ft.)

39640 Total
Total
39640
Booked
34511
Available
5129
Total 101 apartments in project. 90 apartments booked. 89% apartments booked.
Total 39640 Sq.ft. saleable area. 34511 saleable area booked.
87% area booked.

Bldg No 54

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Bldg No 54Jan 190019101001
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK30 Sq.mts. ( 323 Sq.ft. )20
19 Booked95% Booked
95% Booked
1 BHK30.25 Sq.mts. ( 326 Sq.ft. )18
17 Booked94% Booked
94% Booked
2 BHK43.77 Sq.mts. ( 471 Sq.ft. )4
4 Booked100% Booked
100% Booked
2 BHK43.83 Sq.mts. ( 472 Sq.ft. )8
8 Booked100% Booked
100% Booked
2 BHK43.88 Sq.mts. ( 472 Sq.ft. )4
4 Booked100% Booked
100% Booked
2 BHK46.18 Sq.mts. ( 497 Sq.ft. )14
10 Booked71% Booked
71% Booked
2 BHK46.27 Sq.mts. ( 498 Sq.ft. )8
8 Booked100% Booked
100% Booked
2 BHK46.3 Sq.mts. ( 498 Sq.ft. )14
9 Booked64% Booked
64% Booked
SHOP32.87 Sq.mts. ( 354 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP7.49 Sq.mts. ( 81 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP7.6 Sq.mts. ( 82 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP7.67 Sq.mts. ( 83 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP7.87 Sq.mts. ( 85 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP10.27 Sq.mts. ( 111 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP15 Sq.mts. ( 161 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP15.71 Sq.mts. ( 169 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP16.6 Sq.mts. ( 179 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP24.84 Sq.mts. ( 267 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP26.07 Sq.mts. ( 281 Sq.ft. )1
1 Booked100% Booked
100% Booked
101 total apartments / 90 apartments booked. 89% apartments booked.
Work Description in Building Bldg No 54Completion
Excavation
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress60% done
60% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress61% done
61% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
work-in-progress61% done
61% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
work-in-progress55% done
55% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress46% done
46% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
work-in-progress61% done
61% Booked
Channel Partners
Channel Partners Registered by Developer
Aditya Enterprises
for Project
Aadarsh Chs
last updated on 28 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation