Project overview

A1 Complex is a MahaRERA Registered Project bearing MahaRERA Registration Number P99000025038. A1 Complex is located at Kaman Road. This is a New Project being developed by A.1. Real Estate.

A1 Complex has UNIT Apartments with carpet areas ranging from 185 to 215 Sq.ft. Carpet. The Project has total 28 of which 17 are currently available for sale.

A1 Complex is being developed on a total land area of 107640 Sq.ft. out of which 14510 Sq.ft. i.e 13% is reserved for recreational purposes. A1 Complex has 3 Wings / Towers A1 Complex Building No 2,A1 Complex Building No 3,A1 Complex Cfc Building

ProjectDeveloperLocationPossession
Project Details
  • Project:
    A1 Complex
  • Location:
  • Kaman Road
  • Const. Stage:
    New Project
  • Possession:
    30 Mar 2024
Developer Details

  • Developer:
    A.1. Real Estate
  • Phone:
  • Address:
  • 483, Borries Compound, Ram Mandir Road, Kailash Printing Work, Goregaon West, 400062
Project RERA Details
MAHA REARA No: P99000025038
Project Type Commercial
RERA Project Status New Project
Architect Himesh Gupta
Funding Bank SYNDICATE BANK
Proposed Possession 30 Mar 2024
Revised Possession
Extended Possession
Litigations No Litigations
Last Modified 12 Apr 2023
Last Retrived 28 Jul 2025
A1 Complex QR Code
A1 Complex
MahaRERA - P99000025038
Apartment Details & Configuration
TypeArea
UNIT112 Sq.mts. ( 1206 Sq.ft. )
UNIT113.34 Sq.mts. ( 1220 Sq.ft. )
UNIT113.81 Sq.mts. ( 1225 Sq.ft. )
UNIT28.8 Sq.mts. ( 310 Sq.ft. )
UNIT35.77 Sq.mts. ( 385 Sq.ft. )
UNIT17.19 Sq.mts. ( 185 Sq.ft. )
UNIT17.65 Sq.mts. ( 190 Sq.ft. )
UNIT18.12 Sq.mts. ( 195 Sq.ft. )
UNIT19.97 Sq.mts. ( 215 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of A1 Complexlast updated on 28 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
As Per Approved Plan
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station
As Per Msedcl
Energy management
Na
Fire Protection And Fire Safety Requirements
Fire Work As Per Vvcmc
Landscaping & Tree Planting
To Be Provided
Open Parking
As Per Approved Plan
Sewerage (Chamber, Lines, Septic Tank , STP)
To Be Provided
Solid Waste Management And Disposal
As Per Vvcmc
Storm Water Drains
To Be Provided
Street Lighting
Na
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting
To Be Provided
Water Supply
As Per Vvcmc
Buildings / Wings in A1 Complex
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of A1 Complex by A.1. Real Estatelast updated on 28 Jul 2025 as per information obtained from MARA RERA.

107640 Sq. ft.

Project Area

14510 Sq. ft.

Recreational Open Space

Total 3

Wings / Towers in Project

Apartments Statistics

28 apartments in total
Total
28
Booked
11
Available
17

Saleable Area Statistics (Sq. ft.)

15263 Total
Total
15263
Booked
10773
Available
4490
Total 28 apartments in project. 11 apartments booked. 39% apartments booked.
Total 15263 Sq.ft. saleable area. 10773 saleable area booked.
71% area booked.

A1 Complex Building No 2

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
A1 Complex Building No 2Mar 20232100090
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
UNIT112 Sq.mts. ( 1206 Sq.ft. )5
5 Booked100% Booked
100% Booked
UNIT113.34 Sq.mts. ( 1220 Sq.ft. )2
2 Booked100% Booked
100% Booked
UNIT113.81 Sq.mts. ( 1225 Sq.ft. )2
1 Booked50% Booked
50% Booked
9 total apartments / 8 apartments booked. 88% apartments booked.
Work Description in Building A1 Complex Building No 2Completion
Excavation
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress20% done
20% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress60% done
60% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress44% done
44% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
work-in-progress20% done
20% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
work-in-progress20% done
20% Booked
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress20% done
20% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

A1 Complex Building No 3

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
A1 Complex Building No 3Mar 20231100030
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
UNIT28.8 Sq.mts. ( 310 Sq.ft. )1
1 Booked100% Booked
100% Booked
UNIT35.77 Sq.mts. ( 385 Sq.ft. )2
2 Booked100% Booked
100% Booked
3 total apartments / 3 apartments booked. 100% apartments booked.
Work Description in Building A1 Complex Building No 3Completion
Excavation
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

A1 Complex Cfc Building

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
A1 Complex Cfc BuildingMar 202321000160
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
UNIT17.19 Sq.mts. ( 185 Sq.ft. )2
None Booked0% Booked
0% Booked
UNIT17.65 Sq.mts. ( 190 Sq.ft. )3
None Booked0% Booked
0% Booked
UNIT18.12 Sq.mts. ( 195 Sq.ft. )2
None Booked0% Booked
0% Booked
UNIT19.97 Sq.mts. ( 215 Sq.ft. )9
None Booked0% Booked
0% Booked
16 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building A1 Complex Cfc BuildingCompletion
Excavation
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress20% done
20% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Channel Partners
Channel Partners Registered by Developer
A.1. Real Estate
for Project
A1 Complex
last updated on 28 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation