Project overview

127 Upper East is a MahaRERA Registered Project bearing MahaRERA Registration Number P51800000454. 127 Upper East is located at Cts No. 2059 And 2073 Final Plot No. 127 Of Tps - V. This is a Ongoing being developed by Paranjape Schemes (Construction) Ltd.

127 Upper East has 2 BHK & 4 BHK Apartments with carpet areas ranging from 1461 to 741 Sq.ft. Carpet. The Project has total 28 of which 2 are currently available for sale.

127 Upper East is being developed on a total land area of 19458 Sq.ft. out of which 2821 Sq.ft. i.e 14% is reserved for recreational purposes. 127 Upper East has 2 Wings / Towers Building A,Building B

ProjectDeveloperLocationPossession
Project Details
  • Project:
    127 Upper East
  • Location:
  • Cts No. 2059 And 2073 Final Plot No. 127 Of Tps - V
  • Const. Stage:
    Ongoing
  • Possession:
    31 Dec 2019
Developer Details

  • Developer:
    Paranjape Schemes (Construction) Ltd
  • Phone:
  • Address:
  • Somnath
Project RERA Details
MAHA REARA No: P51800000454
Project Type Residential / Group Housing
RERA Project Status Ongoing
Architect Sanjeev Patki
Funding Bank HDFC BANK
Proposed Possession 31 Dec 2019
Revised Possession 31 Dec 2019
Extended Possession 30 Jun 2024
Litigations No Litigations
Last Modified 21 Nov 2023
Last Retrived 26 Jul 2025
127 Upper East QR Code
127 Upper East
MahaRERA - P51800000454
Apartment Details & Configuration
TypeArea
3 BHK106 Sq.mts. ( 1141 Sq.ft. )
3 BHK110.75 Sq.mts. ( 1192 Sq.ft. )
2 BHK68.72 Sq.mts. ( 740 Sq.ft. )
2 BHK68.8 Sq.mts. ( 741 Sq.ft. )
4 BHK135.75 Sq.mts. ( 1461 Sq.ft. )
4 BHK454.83 Sq.mts. ( 4896 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of 127 Upper Eastlast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
-
Community Buildings
-
Electrical Meter Room, Sub-Station, Receiving Station
-
Energy management
-
Fire Protection And Fire Safety Requirements
-
Fitness Centre
-
Landscaping & Tree Planting
-
Open Parking
-
Sewerage (Chamber, Lines, Septic Tank , STP)
Sewage Lines Have Been Provided
Solid Waste Management And Disposal
Na
Storm Water Drains
-
Street Lighting
Only Building Peripheral Lighting
Swimming Pool
-
Terrace Garden
-
Treatment And Disposal Of Sewage And Sullage Water
-
Water Conservation, Rain water Harvesting
-
Water Supply
-
Buildings / Wings in 127 Upper East
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of 127 Upper East by Paranjape Schemes (Construction) Ltdlast updated on 26 Jul 2025 as per information obtained from MARA RERA.

19458 Sq. ft.

Project Area

2821 Sq. ft.

Recreational Open Space

Total 2

Wings / Towers in Project

Apartments Statistics

28 apartments in total
Total
28
Booked
26
Available
2

Saleable Area Statistics (Sq. ft.)

29601 Total
Total
29601
Booked
26679
Available
2922
Total 28 apartments in project. 26 apartments booked. 92% apartments booked.
Total 29601 Sq.ft. saleable area. 26679 saleable area booked.
90% area booked.

Building A

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building AOct 2022101010014
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
3 BHK106 Sq.mts. ( 1141 Sq.ft. )3
3 Booked100% Booked
100% Booked
3 BHK110.75 Sq.mts. ( 1192 Sq.ft. )3
3 Booked100% Booked
100% Booked
6 total apartments / 6 apartments booked. 100% apartments booked.
Work Description in Building Building ACompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress25% done
25% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress30% done
30% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress30% done
30% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress52% done
52% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
work-in-progress20% done
20% Booked
Sanitary Fittings within the flats / premises
work-in-progress20% done
20% Booked
Slabs of Super Structure
work-in-progress80% done
80% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
work-in-progress65% done
65% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress65% done
65% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress25% done
25% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
work-in-progress80% done
80% Booked

Building B

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building BOct 2022101010040
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK68.72 Sq.mts. ( 740 Sq.ft. )9
9 Booked100% Booked
100% Booked
2 BHK68.8 Sq.mts. ( 741 Sq.ft. )9
9 Booked100% Booked
100% Booked
4 BHK135.75 Sq.mts. ( 1461 Sq.ft. )3
1 Booked33% Booked
33% Booked
4 BHK454.83 Sq.mts. ( 4896 Sq.ft. )1
1 Booked100% Booked
100% Booked
22 total apartments / 20 apartments booked. 90% apartments booked.
Work Description in Building Building BCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress30% done
30% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress30% done
30% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress30% done
30% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress52% done
52% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
work-in-progress80% done
80% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
work-in-progress65% done
65% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress65% done
65% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress30% done
30% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
work-in-progress80% done
80% Booked
Channel Partners
Channel Partners Registered by Developer
Paranjape Schemes (Construction) Ltd
for Project
127 Upper East
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation