Project overview

Osians Garden is a MahaRERA Registered Project bearing MahaRERA Registration Number P51700006805. Osians Garden is located at 5 , 85/2. This is a Ongoing being developed by Osian Dwellings Private Limited.

Osians Garden has 1 BHK Apartments with carpet areas ranging from 432 to 444 Sq.ft. Carpet. The Project has total 495 of which 379 are currently available for sale.

Osians Garden is being developed on a total land area of 203438 Sq.ft. out of which 51079 Sq.ft. i.e 25% is reserved for recreational purposes. Osians Garden has 10 Wings / Towers 1,2A,2B,2C,3,4A,4B,4C,4D,4E

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Osians Garden
  • Location:
  • 5 , 85/2
  • Const. Stage:
    Ongoing
  • Possession:
    31 Dec 2017
Developer Details

  • Developer:
    Osian Dwellings Private Limited
  • Phone:
  • Address:
  • Kamal Mansion
Project RERA Details
MAHA REARA No: P51700006805
Project Type Residential / Group Housing
RERA Project Status Ongoing
Architect Fouzi & Associates
Funding Bank CENTRAL BANK OF INDIA
Proposed Possession 31 Dec 2017
Revised Possession 31 Dec 2017
Extended Possession
Litigations No Litigations
Last Modified 16 Aug 2017
Last Retrived 26 Jul 2025
Osians Garden QR Code
Osians Garden
MahaRERA - P51700006805
Apartment Details & Configuration
TypeArea
2 BHK75.81 Sq.mts. ( 816 Sq.ft. )
2 BHK76.64 Sq.mts. ( 825 Sq.ft. )
3 BHK101.63 Sq.mts. ( 1094 Sq.ft. )
SHOP20.44 Sq.mts. ( 220 Sq.ft. )
SHOP22.48 Sq.mts. ( 242 Sq.ft. )
SHOP25.58 Sq.mts. ( 275 Sq.ft. )
SHOP25.89 Sq.mts. ( 279 Sq.ft. )
SHOP26.38 Sq.mts. ( 284 Sq.ft. )
SHOP30.47 Sq.mts. ( 328 Sq.ft. )
SHOP20.48 Sq.mts. ( 220 Sq.ft. )
SHOP25.27 Sq.mts. ( 272 Sq.ft. )
1 BHK40.13 Sq.mts. ( 432 Sq.ft. )
1 BHK41.25 Sq.mts. ( 444 Sq.ft. )
1 BHK65.03 Sq.mts. ( 700 Sq.ft. )
2 BHK65.96 Sq.mts. ( 710 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Osians Gardenlast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space30% completed
30% Complete
Provided
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station100% completed
95% Complete
As Required By Cfo
Energy management100% completed
95% Complete
Solar Panel For Lighting And Water Heater
Fire Protection And Fire Safety Requirements100% completed
95% Complete
Installed
Landscaping & Tree Planting100% completed
95% Complete
Trees &Amp; Plants Grown
Open Parking100% completed
95% Complete
Full Upon Completion Of Entire Project
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
95% Complete
Stp Installed
Solid Waste Management And Disposal100% completed
95% Complete
Installed
Storm Water Drains100% completed
95% Complete
Completed
Street Lighting100% completed
95% Complete
Provided
Treatment And Disposal Of Sewage And Sullage Water100% completed
95% Complete
Installed
Water Conservation, Rain water Harvesting100% completed
95% Complete
Provided
Water Supply100% completed
95% Complete
Completed.Municipal Connection On Oc
Buildings / Wings in Osians Garden
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Osians Garden by Osian Dwellings Private Limitedlast updated on 26 Jul 2025 as per information obtained from MARA RERA.

203438 Sq. ft.

Project Area

51079 Sq. ft.

Recreational Open Space

Total 10

Wings / Towers in Project

Apartments Statistics

495 apartments in total
Total
495
Booked
116
Available
379

Saleable Area Statistics (Sq. ft.)

340100 Total
Total
340100
Booked
70930
Available
269170
Total 495 apartments in project. 116 apartments booked. 23% apartments booked.
Total 340100 Sq.ft. saleable area. 70930 saleable area booked.
21% area booked.

1

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
1Jan 19001210103216
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK75.81 Sq.mts. ( 816 Sq.ft. )12
6 Booked50% Booked
50% Booked
2 BHK76.64 Sq.mts. ( 825 Sq.ft. )12
8 Booked66% Booked
66% Booked
3 BHK101.63 Sq.mts. ( 1094 Sq.ft. )24
13 Booked54% Booked
54% Booked
48 total apartments / 27 apartments booked. 56% apartments booked.
Work Description in Building 1Completion
Basement (if any)
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Podiums (if any)
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked

2A

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
2AJan 1900111010426
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK75.81 Sq.mts. ( 816 Sq.ft. )11
8 Booked72% Booked
72% Booked
2 BHK76.64 Sq.mts. ( 825 Sq.ft. )11
6 Booked54% Booked
54% Booked
3 BHK101.63 Sq.mts. ( 1094 Sq.ft. )22
9 Booked40% Booked
40% Booked
SHOP20.44 Sq.mts. ( 220 Sq.ft. )2
1 Booked50% Booked
50% Booked
SHOP22.48 Sq.mts. ( 242 Sq.ft. )2
2 Booked100% Booked
100% Booked
SHOP25.58 Sq.mts. ( 275 Sq.ft. )4
4 Booked100% Booked
100% Booked
SHOP25.89 Sq.mts. ( 279 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP26.38 Sq.mts. ( 284 Sq.ft. )2
1 Booked50% Booked
50% Booked
SHOP30.47 Sq.mts. ( 328 Sq.ft. )2
2 Booked100% Booked
100% Booked
57 total apartments / 34 apartments booked. 59% apartments booked.
Work Description in Building 2ACompletion
Basement (if any)
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Podiums (if any)
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked

2B

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
2BJan 1900111010426
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK75.81 Sq.mts. ( 816 Sq.ft. )11
None Booked0% Booked
0% Booked
2 BHK76.64 Sq.mts. ( 825 Sq.ft. )11
None Booked0% Booked
0% Booked
3 BHK101.63 Sq.mts. ( 1094 Sq.ft. )22
None Booked0% Booked
0% Booked
SHOP20.44 Sq.mts. ( 220 Sq.ft. )2
1 Booked50% Booked
50% Booked
SHOP20.48 Sq.mts. ( 220 Sq.ft. )2
2 Booked100% Booked
100% Booked
SHOP25.89 Sq.mts. ( 279 Sq.ft. )2
2 Booked100% Booked
100% Booked
SHOP26.38 Sq.mts. ( 284 Sq.ft. )2
1 Booked50% Booked
50% Booked
SHOP30.47 Sq.mts. ( 328 Sq.ft. )2
2 Booked100% Booked
100% Booked
54 total apartments / 8 apartments booked. 14% apartments booked.
Work Description in Building 2BCompletion
Basement (if any)
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
Completed 100% done
100% Booked

2C

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
2CJan 1900111010426
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK75.81 Sq.mts. ( 816 Sq.ft. )11
None Booked0% Booked
0% Booked
2 BHK76.64 Sq.mts. ( 825 Sq.ft. )11
None Booked0% Booked
0% Booked
3 BHK101.63 Sq.mts. ( 1094 Sq.ft. )22
None Booked0% Booked
0% Booked
SHOP20.44 Sq.mts. ( 220 Sq.ft. )2
1 Booked50% Booked
50% Booked
SHOP22.48 Sq.mts. ( 242 Sq.ft. )2
2 Booked100% Booked
100% Booked
SHOP25.27 Sq.mts. ( 272 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP25.58 Sq.mts. ( 275 Sq.ft. )4
4 Booked100% Booked
100% Booked
SHOP26.38 Sq.mts. ( 284 Sq.ft. )2
1 Booked50% Booked
50% Booked
SHOP30.47 Sq.mts. ( 328 Sq.ft. )2
1 Booked50% Booked
50% Booked
57 total apartments / 10 apartments booked. 17% apartments booked.
Work Description in Building 2CCompletion
Basement (if any)
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
Completed 100% done
100% Booked

3

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
3Jan 19001110102816
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK75.81 Sq.mts. ( 816 Sq.ft. )11
None Booked0% Booked
0% Booked
2 BHK76.64 Sq.mts. ( 825 Sq.ft. )11
None Booked0% Booked
0% Booked
3 BHK101.63 Sq.mts. ( 1094 Sq.ft. )22
None Booked0% Booked
0% Booked
44 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building 3Completion
Basement (if any)
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Plinth
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
Completed 100% done
100% Booked

4A

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
4AJan 1900121010111
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK40.13 Sq.mts. ( 432 Sq.ft. )33
17 Booked51% Booked
51% Booked
1 BHK41.25 Sq.mts. ( 444 Sq.ft. )12
45 total apartments / 19 apartments booked. 42% apartments booked.
Work Description in Building 4ACompletion
Basement (if any)
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Podiums (if any)
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked

4B

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
4BJan 1900121010111
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK40.13 Sq.mts. ( 432 Sq.ft. )36
17 Booked47% Booked
47% Booked
1 BHK41.25 Sq.mts. ( 444 Sq.ft. )11
47 total apartments / 18 apartments booked. 38% apartments booked.
Work Description in Building 4BCompletion
Basement (if any)
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Podiums (if any)
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked

4C

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
4CJan 19001310101214
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK65.03 Sq.mts. ( 700 Sq.ft. )26
None Booked0% Booked
0% Booked
2 BHK65.96 Sq.mts. ( 710 Sq.ft. )25
None Booked0% Booked
0% Booked
51 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building 4CCompletion
Basement (if any)
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Plinth
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
Completed 100% done
100% Booked

4D

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
4DJan 1900121010111
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK40.13 Sq.mts. ( 432 Sq.ft. )36
None Booked0% Booked
0% Booked
1 BHK41.25 Sq.mts. ( 444 Sq.ft. )11
None Booked0% Booked
0% Booked
47 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building 4DCompletion
Basement (if any)
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Plinth
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor

4E

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
4EJan 1900121010111
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK40.13 Sq.mts. ( 432 Sq.ft. )34
None Booked0% Booked
0% Booked
1 BHK41.25 Sq.mts. ( 444 Sq.ft. )11
None Booked0% Booked
0% Booked
45 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building 4ECompletion
Basement (if any)
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Plinth
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
Channel Partners
Channel Partners Registered by Developer
Osian Dwellings Private Limited
for Project
Osians Garden
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation