Project overview

Orovia Phase 1 is a MahaRERA Registered Project bearing MahaRERA Registration Number P51700005653. Orovia Phase 1 is located at Sno 106/1/1Pt, 106/2Pt. This is a Ongoing being developed by Vijay Suraksha Realty Llp.

Orovia Phase 1 has 2 BHK SMART & 2 BHK SPACIO Apartments with carpet areas ranging from 497 to 601 Sq.ft. Carpet. The Project has total 716 of which 73 are currently available for sale.

Orovia Phase 1 is being developed on a total land area of 43949 Sq.ft. out of which 31119 Sq.ft. i.e 71% is reserved for recreational purposes. Orovia Phase 1 has 6 Wings / Towers Fern,Indigo,Ivy,Marigold East End,Marigold West End,Periwinkle

ProjectDeveloperLocationPossession
Unnathi Woods Phase Vii AUnnathi Estates246 247/1 247/230-12-2025 00:00:00
SolusRoma Builders Private Limited72/4, 72/6 And 72/530-12-2024 00:00:00
Solitaire BRoma Builders Private Limited117/1, 116/2 Pt30-12-2024 00:00:00
Tropical Lagoon - 5 - Di VitaSoham Estates240/2 Pt, 240/3, 240/6, 240/7, 240/9, 240/10 Pt31-07-2022 00:00:00
Jangid Galaxy Tower 2Jangid Contructions199/730-04-2019 00:00:00
Pataskar Eclat Building No 3Pataskar Developers Pvt. Ltd40060231-12-2017 00:00:00
Jangid Galaxy Tower 7Jangid Contructions400607, Thane30-12-2022 00:00:00
Hill Spring Phase 1Velocity185/2, 185/330-06-2018 00:00:00
Palacia Phase-IiShree Sachdhanand DevelopersS No 226 Hissa No 1,2,330-12-2019 00:00:00
Orovia Phase 1Vijay Suraksha Realty LlpSno 106/1/1Pt, 106/2Pt30-03-2023 00:00:00
Vijay Vatika -5Vijay Suraksha Realty LlpSurvey No 231 Hissa No 5 Pt30-09-2018 00:00:00
Project Details
  • Project:
    Orovia Phase 1
  • Location:
  • Sno 106/1/1Pt, 106/2Pt
  • Const. Stage:
    Ongoing
  • Possession:
    30 Mar 2023
Developer Details

  • Developer:
    Vijay Suraksha Realty Llp
  • Phone:
  • Address:
  • Marine Chambers
Project RERA Details
MAHA REARA No: P51700005653
Project Type Others
RERA Project Status Ongoing
Funding Bank YES BANK
Proposed Possession 30 Mar 2023
Revised Possession 30 Mar 2023
Extended Possession
Litigations No Litigations
Last Modified 11 Aug 2017
Last Retrived 26 Jul 2025
Orovia Phase 1 QR Code
Orovia Phase 1
MahaRERA - P51700005653
Apartment Details & Configuration
TypeArea
1 BHK SMART35.57 Sq.mts. ( 383 Sq.ft. )
1 BHK SMART35.7 Sq.mts. ( 384 Sq.ft. )
1 BHK SPACIO36.6 Sq.mts. ( 394 Sq.ft. )
2 BHK LUXURY57.55 Sq.mts. ( 619 Sq.ft. )
2 BHK LUXURY60.67 Sq.mts. ( 653 Sq.ft. )
2.5 BHK64.42 Sq.mts. ( 693 Sq.ft. )
3 BHK68.4 Sq.mts. ( 736 Sq.ft. )
Office space20.36 Sq.mts. ( 219 Sq.ft. )
Office space27.4 Sq.mts. ( 295 Sq.ft. )
Office space30.62 Sq.mts. ( 330 Sq.ft. )
Office space30.63 Sq.mts. ( 330 Sq.ft. )
Office space30.64 Sq.mts. ( 330 Sq.ft. )
Office space30.67 Sq.mts. ( 330 Sq.ft. )
Office space30.87 Sq.mts. ( 332 Sq.ft. )
Office space30.88 Sq.mts. ( 332 Sq.ft. )
Office space30.78 Sq.mts. ( 331 Sq.ft. )
Office space30.8 Sq.mts. ( 332 Sq.ft. )
Office space30.99 Sq.mts. ( 334 Sq.ft. )
Office space31.61 Sq.mts. ( 340 Sq.ft. )
Office space31.88 Sq.mts. ( 343 Sq.ft. )
Office space32 Sq.mts. ( 344 Sq.ft. )
Office space33.37 Sq.mts. ( 359 Sq.ft. )
Office space34.62 Sq.mts. ( 373 Sq.ft. )
Office space103.71 Sq.mts. ( 1116 Sq.ft. )
Office space81.96 Sq.mts. ( 882 Sq.ft. )
RESTAURANT54.67 Sq.mts. ( 588 Sq.ft. )
SHOP81.7 Sq.mts. ( 879 Sq.ft. )
SHOP34.06 Sq.mts. ( 367 Sq.ft. )
SHOP34.27 Sq.mts. ( 369 Sq.ft. )
SHOP32.16 Sq.mts. ( 346 Sq.ft. )
SHOP31.1 Sq.mts. ( 335 Sq.ft. )
SHOP31.52 Sq.mts. ( 339 Sq.ft. )
SHOP30.82 Sq.mts. ( 332 Sq.ft. )
SHOP30.9 Sq.mts. ( 333 Sq.ft. )
SHOP30.91 Sq.mts. ( 333 Sq.ft. )
SHOP30.92 Sq.mts. ( 333 Sq.ft. )
SHOP30.71 Sq.mts. ( 331 Sq.ft. )
SHOP27.45 Sq.mts. ( 295 Sq.ft. )
SHOP20.1 Sq.mts. ( 216 Sq.ft. )
SHOP103.62 Sq.mts. ( 1115 Sq.ft. )
SHOP103.64 Sq.mts. ( 1116 Sq.ft. )
Office space23.93 Sq.mts. ( 258 Sq.ft. )
Office space26.86 Sq.mts. ( 289 Sq.ft. )
Office space22.99 Sq.mts. ( 247 Sq.ft. )
Office space30.86 Sq.mts. ( 332 Sq.ft. )
Office space27.6 Sq.mts. ( 297 Sq.ft. )
Office space34.53 Sq.mts. ( 372 Sq.ft. )
SHOP34.58 Sq.mts. ( 372 Sq.ft. )
SHOP27.64 Sq.mts. ( 298 Sq.ft. )
SHOP23.04 Sq.mts. ( 248 Sq.ft. )
SHOP23.91 Sq.mts. ( 257 Sq.ft. )
SHOP26.91 Sq.mts. ( 290 Sq.ft. )
2 BHK SMART46.13 Sq.mts. ( 497 Sq.ft. )
2 BHK SPACIO53.83 Sq.mts. ( 579 Sq.ft. )
2 BHK SPACIO55.86 Sq.mts. ( 601 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Orovia Phase 1last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space25% completed
25% Complete
Rg Will Be Shared By Layout
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station60% completed
60% Complete
Elec.Meter Room Proposed &Amp; Substan Shared Bylayout
Energy management50% completed
50% Complete
Energy Efficient Lightings &Amp; Dg For Common Area
Fire Protection And Fire Safety Requirements100% completed
95% Complete
As Per Cfo Noc
Landscaping & Tree Planting100% completed
95% Complete
Shared By Entire Layout
Open Parking
Na
OTHER COMMON AMENITIES LIKE COMMON ROOM WOODEN FLOORING GAMES ROOM READING ROOM SMALL AREA PARTY80% completed
80% Complete
Shared By Entire Layout
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
95% Complete
Stp To Be Given As Shared Amenity As Approved Tmc
SOCIETY OFFICE100% completed
95% Complete
To Be Provided As Per Approved Plan By Muni. Corp.
Solid Waste Management And Disposal100% completed
95% Complete
Owc Shall Be Provided &Amp; Shared By Entire Layout
Storm Water Drains100% completed
95% Complete
To Be Given As Approved By Tmc
Street Lighting20% completed
20% Complete
Shared By Entire Layout
Treatment And Disposal Of Sewage And Sullage Water100% completed
95% Complete
Water Shall Be Used For Toilet Flushing And Garden
Water Conservation, Rain water Harvesting100% completed
95% Complete
Rwh Pit To Be Given As Approved By Tmc
Water Supply100% completed
95% Complete
To Be Given By Municipal Corporation After Oc
Buildings / Wings in Orovia Phase 1
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Orovia Phase 1 by Vijay Suraksha Realty Llplast updated on 26 Jul 2025 as per information obtained from MARA RERA.

43949 Sq. ft.

Project Area

31119 Sq. ft.

Recreational Open Space

Total 6

Wings / Towers in Project

Apartments Statistics

716 apartments in total
Total
716
Booked
643
Available
73

Saleable Area Statistics (Sq. ft.)

353142 Total
Total
353142
Booked
312246
Available
40896
Total 716 apartments in project. 643 apartments booked. 89% apartments booked.
Total 353142 Sq.ft. saleable area. 312246 saleable area booked.
88% area booked.

Fern

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
FernMar 20222811120157
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK SMART35.57 Sq.mts. ( 383 Sq.ft. )49
44 Booked89% Booked
89% Booked
1 BHK SMART35.7 Sq.mts. ( 384 Sq.ft. )54
53 Booked98% Booked
98% Booked
1 BHK SPACIO36.6 Sq.mts. ( 394 Sq.ft. )54
51 Booked94% Booked
94% Booked
157 total apartments / 148 apartments booked. 94% apartments booked.
Work Description in Building FernCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
Completed 100% done
100% Booked
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Indigo

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
IndigoMar 20222811120157
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK LUXURY57.55 Sq.mts. ( 619 Sq.ft. )22
13 Booked59% Booked
59% Booked
2 BHK LUXURY60.67 Sq.mts. ( 653 Sq.ft. )27
26 Booked96% Booked
96% Booked
2.5 BHK64.42 Sq.mts. ( 693 Sq.ft. )54
44 Booked81% Booked
81% Booked
3 BHK68.4 Sq.mts. ( 736 Sq.ft. )54
53 Booked98% Booked
98% Booked
157 total apartments / 136 apartments booked. 86% apartments booked.
Work Description in Building IndigoCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
Completed 100% done
100% Booked
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Ivy

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
IvyMar 20222811120141
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK SMART35.57 Sq.mts. ( 383 Sq.ft. )49
46 Booked93% Booked
93% Booked
1 BHK SPACIO36.6 Sq.mts. ( 394 Sq.ft. )54
54 Booked100% Booked
100% Booked
1 BHKSMART35.7 Sq.mts. ( 384 Sq.ft. )54
50 Booked92% Booked
92% Booked
157 total apartments / 150 apartments booked. 95% apartments booked.
Work Description in Building IvyCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
Completed 100% done
100% Booked
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Marigold East End

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Marigold East EndMar 202221110050
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
Office space20.36 Sq.mts. ( 219 Sq.ft. )1
1 Booked100% Booked
100% Booked
Office space27.4 Sq.mts. ( 295 Sq.ft. )1
1 Booked100% Booked
100% Booked
Office space30.62 Sq.mts. ( 330 Sq.ft. )1
None Booked0% Booked
0% Booked
Office space30.63 Sq.mts. ( 330 Sq.ft. )2
2 Booked100% Booked
100% Booked
Office space30.64 Sq.mts. ( 330 Sq.ft. )2
2 Booked100% Booked
100% Booked
Office space30.67 Sq.mts. ( 330 Sq.ft. )1
None Booked0% Booked
0% Booked
Office space30.87 Sq.mts. ( 332 Sq.ft. )3
1 Booked33% Booked
33% Booked
Office space30.88 Sq.mts. ( 332 Sq.ft. )3
1 Booked33% Booked
33% Booked
Office space30.78 Sq.mts. ( 331 Sq.ft. )1
None Booked0% Booked
0% Booked
Office space30.8 Sq.mts. ( 332 Sq.ft. )1
1 Booked100% Booked
100% Booked
Office space30.99 Sq.mts. ( 334 Sq.ft. )1
1 Booked100% Booked
100% Booked
Office space31.61 Sq.mts. ( 340 Sq.ft. )1
1 Booked100% Booked
100% Booked
Office space31.88 Sq.mts. ( 343 Sq.ft. )1
1 Booked100% Booked
100% Booked
Office space32 Sq.mts. ( 344 Sq.ft. )1
1 Booked100% Booked
100% Booked
Office space33.37 Sq.mts. ( 359 Sq.ft. )1
None Booked0% Booked
0% Booked
Office space34.62 Sq.mts. ( 373 Sq.ft. )1
1 Booked100% Booked
100% Booked
Office space103.71 Sq.mts. ( 1116 Sq.ft. )3
None Booked0% Booked
0% Booked
Office space81.96 Sq.mts. ( 882 Sq.ft. )1
None Booked0% Booked
0% Booked
RESTAURANT54.67 Sq.mts. ( 588 Sq.ft. )2
None Booked0% Booked
0% Booked
SHOP81.7 Sq.mts. ( 879 Sq.ft. )1
None Booked0% Booked
0% Booked
SHOP34.06 Sq.mts. ( 367 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP34.27 Sq.mts. ( 369 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP32.16 Sq.mts. ( 346 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP31.1 Sq.mts. ( 335 Sq.ft. )2
2 Booked100% Booked
100% Booked
SHOP31.52 Sq.mts. ( 339 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP30.82 Sq.mts. ( 332 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP30.9 Sq.mts. ( 333 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP30.91 Sq.mts. ( 333 Sq.ft. )3
2 Booked66% Booked
66% Booked
SHOP30.92 Sq.mts. ( 333 Sq.ft. )6
6 Booked100% Booked
100% Booked
SHOP30.71 Sq.mts. ( 331 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP27.45 Sq.mts. ( 295 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP20.1 Sq.mts. ( 216 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP103.62 Sq.mts. ( 1115 Sq.ft. )2
None Booked0% Booked
0% Booked
SHOP103.64 Sq.mts. ( 1116 Sq.ft. )1
None Booked0% Booked
0% Booked
52 total apartments / 33 apartments booked. 63% apartments booked.
Work Description in Building Marigold East EndCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
Completed 100% done
100% Booked
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Marigold West End

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Marigold West EndMar 202221110046
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
Office space23.93 Sq.mts. ( 258 Sq.ft. )1
1 Booked100% Booked
100% Booked
Office space26.86 Sq.mts. ( 289 Sq.ft. )1
1 Booked100% Booked
100% Booked
Office space22.99 Sq.mts. ( 247 Sq.ft. )1
1 Booked100% Booked
100% Booked
Office space30.62 Sq.mts. ( 330 Sq.ft. )1
1 Booked100% Booked
100% Booked
Office space30.64 Sq.mts. ( 330 Sq.ft. )4
4 Booked100% Booked
100% Booked
Office space30.86 Sq.mts. ( 332 Sq.ft. )1
None Booked0% Booked
0% Booked
Office space30.88 Sq.mts. ( 332 Sq.ft. )6
3 Booked50% Booked
50% Booked
Office space27.6 Sq.mts. ( 297 Sq.ft. )1
None Booked0% Booked
0% Booked
Office space30.92 Sq.mts. ( 333 Sq.ft. )1
1 Booked100% Booked
100% Booked
Office space34.53 Sq.mts. ( 372 Sq.ft. )1
1 Booked100% Booked
100% Booked
RESTAURANT54.67 Sq.mts. ( 588 Sq.ft. )2
None Booked0% Booked
0% Booked
SHOP34.58 Sq.mts. ( 372 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP30.92 Sq.mts. ( 333 Sq.ft. )10
9 Booked90% Booked
90% Booked
SHOP27.64 Sq.mts. ( 298 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP30.88 Sq.mts. ( 332 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP23.04 Sq.mts. ( 248 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP23.91 Sq.mts. ( 257 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP26.91 Sq.mts. ( 290 Sq.ft. )1
1 Booked100% Booked
100% Booked
36 total apartments / 28 apartments booked. 77% apartments booked.
Work Description in Building Marigold West EndCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
Completed 100% done
100% Booked
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Periwinkle

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
PeriwinkleMar 20222811120157
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK SMART46.13 Sq.mts. ( 497 Sq.ft. )54
52 Booked96% Booked
96% Booked
2 BHK SPACIO53.83 Sq.mts. ( 579 Sq.ft. )54
47 Booked87% Booked
87% Booked
2 BHK SPACIO55.86 Sq.mts. ( 601 Sq.ft. )49
49 Booked100% Booked
100% Booked
157 total apartments / 148 apartments booked. 94% apartments booked.
Work Description in Building PeriwinkleCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
Completed 100% done
100% Booked
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Vijay Suraksha Realty Llp
for Project
Orovia Phase 1
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation