Project overview

Myzo Suites is a MahaRERA Registered Project bearing MahaRERA Registration Number P99000045683. Myzo Suites is located at 49/1. This is a New being developed by Myzo Infra Private Limited.

Myzo Suites has 1RK Apartments with carpet areas ranging from 289 to 323 Sq.ft. Carpet. The Project has total 80 of which 80 are currently available for sale.

Myzo Suites is being developed on a total land area of 76791 Sq.ft. out of which 7341 Sq.ft. i.e 10% is reserved for recreational purposes. Myzo Suites has 3 Wings / Towers Building No -1 Type-A,Building No-2 Type-A,Building No-4 Wing A And B Type-B

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Myzo Suites
  • Location:
  • 49/1
  • Const. Stage:
    New
  • Possession:
    31 Dec 2027
Developer Details

  • Developer:
    Myzo Infra Private Limited
  • Phone:
  • Address:
  • Myzo Club And Resort
Project RERA Details
MAHA REARA No: P99000045683
Project Type Residential / Group Housing
RERA Project Status New
Architect Sanjay Maloo
Funding Bank IDFC First Bank Ltd
Proposed Possession 31 Dec 2027
Revised Possession
Extended Possession
Litigations No Litigations
Last Modified 07 Jun 2022
Last Retrived 28 Jul 2025
Myzo Suites QR Code
Myzo Suites
MahaRERA - P99000045683
Apartment Details & Configuration
TypeArea
1 BHK38.12 Sq.mts. ( 410 Sq.ft. )
1RK26.87 Sq.mts. ( 289 Sq.ft. )
1RK27.32 Sq.mts. ( 294 Sq.ft. )
1RK29.5 Sq.mts. ( 318 Sq.ft. )
1RK29.99 Sq.mts. ( 323 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Myzo Suiteslast updated on 28 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space25% completed
25% Complete
As Per Layout
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station
Meter Room To Be Provided
Energy management
Na
Fire Protection And Fire Safety Requirements
Na
Landscaping & Tree Planting50% completed
50% Complete
As Per Landscape Design
Open Parking25% completed
25% Complete
As Per Layout
Sewerage (Chamber, Lines, Septic Tank , STP)25% completed
25% Complete
Septic Tank To Be Provided
Solid Waste Management And Disposal
Na
Storm Water Drains
As Per Layout
Street Lighting25% completed
25% Complete
As Per Landscape Design
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting
Na
Water Supply25% completed
25% Complete
To Be Provided
Buildings / Wings in Myzo Suites
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Myzo Suites by Myzo Infra Private Limitedlast updated on 28 Jul 2025 as per information obtained from MARA RERA.

76791 Sq. ft.

Project Area

7341 Sq. ft.

Recreational Open Space

Total 3

Wings / Towers in Project

Apartments Statistics

80 apartments in total
Total
80
Booked
0
Available
80

Saleable Area Statistics (Sq. ft.)

28280 Total
Total
28280
Booked
0
Available
28280
Total 80 apartments in project. 0 apartments booked. 0% apartments booked.
Total 28280 Sq.ft. saleable area. 0 saleable area booked.
0% area booked.

Building No -1 Type-A

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building No -1 Type-ADec 20275100020
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK38.12 Sq.mts. ( 410 Sq.ft. )20
None Booked0% Booked
0% Booked
20 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Building No -1 Type-ACompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
work-in-progress25% done
25% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
X number of Podiums
X number of Slabs of Super Structure

Building No-2 Type-A

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building No-2 Type-ADec 20275100020
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK38.12 Sq.mts. ( 410 Sq.ft. )20
None Booked0% Booked
0% Booked
20 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Building No-2 Type-ACompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
work-in-progress45% done
45% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
X number of Podiums
X number of Slabs of Super Structure

Building No-4 Wing A And B Type-B

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building No-4 Wing A And B Type-BDec 20275100020
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1RK26.87 Sq.mts. ( 289 Sq.ft. )7
None Booked0% Booked
0% Booked
1RK27.32 Sq.mts. ( 294 Sq.ft. )28
None Booked0% Booked
0% Booked
1RK29.5 Sq.mts. ( 318 Sq.ft. )1
None Booked0% Booked
0% Booked
1RK29.99 Sq.mts. ( 323 Sq.ft. )4
None Booked0% Booked
0% Booked
40 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Building No-4 Wing A And B Type-BCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress20% done
20% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Channel Partners
Channel Partners Registered by Developer
Myzo Infra Private Limited
for Project
Myzo Suites
last updated on 28 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation