Project overview
Mangaldeep Chsl. is a MahaRERA Registered Project bearing MahaRERA Registration Number P51800010018. Mangaldeep Chsl. is located at 88Pt. This is a Ongoing being developed by Dhariwal Constructions (India) Private Limited.
Mangaldeep Chsl. has 2 BHK & 3 BHK Apartments with carpet areas ranging from 570 to 826 Sq.ft. Carpet. The Project has total 65 of which 25 are currently available for sale.
Mangaldeep Chsl. is being developed on a total land area of 9187 Sq.ft. Mangaldeep Chsl. has 1 Wings / Towers Mangaldeep Chsl
| Project | Developer | Location | Possession |
| Sky City Towers A To D | Incline Realty Private Limited | Cts No 107/E Pt Of Village Magathane | 30-12-2023 00:00:00 |
| Rustomjee Summit | Keystone Realtors Limited | Cts No 88 Pt | 31-12-2021 00:00:00 |
| Pushp Vinod-3 | Vas Infrastructure Ltd. | Mumbai Suburban, 400092 | 15-12-2015 00:00:00 |
| Sanghvi Solitaire | Sanghvi Premises Private Limited | Cts No 31B Part | 31-12-2018 00:00:00 |
| Paarijat Chs Ltd | Maan Housing Development | 945 | 31-12-2018 00:00:00 |
| Rooprajat Enclave | Siddhivinayak Developers | 55 57 | 30-12-2021 00:00:00 |
| Om Sarjan Chsl | Glasswood Realty Private Limited | 777/9 149A Fp No 680/A/1/2 | 31-12-2019 00:00:00 |
| Madhuban Heights | Wadhwana Housing Development And Infrastructure Co | 740/41 | 31-08-2018 00:00:00 |
| Target The Mall | Mahendra Jamnadas Kara | 590/1 To 6 F P No 33, Cts No 590 | 31-12-2017 00:00:00 |
| Redevlopment Of Rajendra Nagar - Shree Ganesh Chs Ltd. | Kaustubh Construction Private Limited | 88 Pt | 31-12-2018 00:00:00 |
| Rustomjee Pinnacle | Keystone Realtors Limited | Cts No 88 Pt | 31-12-2018 00:00:00 |
| Sbi Ragvihar Chs | Tuvin Consultancy Llp | 412 | 10-12-2020 00:00:00 |
-
Project:
Mangaldeep Chsl.
-
Location:
-
88Pt
-
Const. Stage:
Ongoing
-
Possession:
31 Dec 2018
| MAHA REARA No: |
P51800010018 |
| Project Type |
Residential / Group Housing |
| RERA Project Status |
Ongoing |
| Architect |
Ashok Damani |
| Funding Bank |
BANK OF BARODA |
| Proposed Possession |
31 Dec 2018 |
| Revised Possession |
31 Dec 2018 |
| Extended Possession |
30 Dec 2019 |
| Litigations |
No Litigations |
| Last Modified |
05 Mar 2019 |
| Last Retrived |
26 Jul 2025 |
Mangaldeep Chsl. QR Code
Mangaldeep Chsl.
MahaRERA - P51800010018
| Type | Area |
| 2 BHK | 52.97 Sq.mts. ( 570 Sq.ft. ) |
| 2 BHK | 53.84 Sq.mts. ( 580 Sq.ft. ) |
| 2 BHK | 53.92 Sq.mts. ( 580 Sq.ft. ) |
| 2 BHK | 53.93 Sq.mts. ( 581 Sq.ft. ) |
| 2 BHK | 54.12 Sq.mts. ( 583 Sq.ft. ) |
| 2 BHK | 55.05 Sq.mts. ( 593 Sq.ft. ) |
| 2 BHK | 55.14 Sq.mts. ( 594 Sq.ft. ) |
| 2 BHK | 60.38 Sq.mts. ( 650 Sq.ft. ) |
| 3 BHK | 76.77 Sq.mts. ( 826 Sq.ft. ) |
Facilities & Amenities
Facilities, Amenities & Common areas details of Mangaldeep Chsl.last updated on 26 Jul 2025 as per information obtained from MARA RERA.
| Project Facilities & Amenities |
Available |
Details |
Aggregate area of recreational Open Space
|
|
Na |
|
|
|
Na |
Electrical Meter Room, Sub-Station, Receiving Station100% completed
|
|
Work Completed |
|
|
|
Na |
Fire Protection And Fire Safety
Requirements100% completed
|
|
Work Completed |
Landscaping & Tree Planting
|
|
Na |
Open Parking100% completed
|
|
Work Completed |
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
|
|
Work Completed |
Solid Waste Management And Disposal100% completed
|
|
Work Completed |
Storm Water Drains100% completed
|
|
Work Completed |
|
|
|
Na |
Treatment And Disposal Of Sewage And Sullage Water
|
|
Na |
Water Conservation, Rain water Harvesting100% completed
|
|
Work Completed |
Water Supply100% completed
|
|
Work Completed |
Buildings / Wings in Mangaldeep Chsl.
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Mangaldeep Chsl. by Dhariwal Constructions (India) Private Limitedlast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Apartments Statistics
65
apartments in total
Saleable Area Statistics (Sq. ft.)
38014
Total
Total 65 apartments in project. 40 apartments booked. 61% apartments booked.
Total 38014 Sq.ft. saleable area. 23155 saleable area booked.
61% area booked.
| Wing | Proposed Date of Completion | Number of Slabs | Plinth | Basement's | Stilts | Podium's | Open Parkings | Closed Parkings |
| Mangaldeep Chsl | Jan 1900 | 18 | 1 | 0 | 1 | 0 | 8 | 1 |
| Apartment Type | Carpet Area | Number of Apartments | Booked Apartments |
| 2 BHK | 52.97 Sq.mts. ( 570 Sq.ft. ) | 20 | |
| 2 BHK | 53.84 Sq.mts. ( 580 Sq.ft. ) | 7 | |
| 2 BHK | 53.92 Sq.mts. ( 580 Sq.ft. ) | 1 | |
| 2 BHK | 53.93 Sq.mts. ( 581 Sq.ft. ) | 10 | |
| 2 BHK | 54.12 Sq.mts. ( 583 Sq.ft. ) | 13 | |
| 2 BHK | 55.05 Sq.mts. ( 593 Sq.ft. ) | 3 | |
| 2 BHK | 55.14 Sq.mts. ( 594 Sq.ft. ) | 9 | |
| 2 BHK | 60.38 Sq.mts. ( 650 Sq.ft. ) | 1 | |
| 3 BHK | 76.77 Sq.mts. ( 826 Sq.ft. ) | 1 | |
65 total apartments / 40 apartments booked. 61% apartments booked. |
| Work Description in Building Mangaldeep Chsl | Completion |
| Basement (if any) | |
| Excavation | |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | |
| Plinth | |
| Podiums (if any) | |
| Sanitary Fittings within the flats / premises | |
| Slabs of Super Structure | |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | |
| Stilt Floor | |
Channel Partners Registered by Developer
Dhariwal Constructions (India) Private Limited
for Project
Mangaldeep Chsl.
last updated on
26 Jul 2025 as per information obtained from MARA RERA.
| Name |
Company |
Location |
Mobile |
Designation |