Hdil Paradise City Sector 5 is a MahaRERA Registered Project bearing MahaRERA Registration Number P99000012466. Hdil Paradise City Sector 5 is located at S No 942 Pt. This is a Ongoing being developed by Housing Development And Infrastructure Ltd.
Hdil Paradise City Sector 5 has RESIDENTIAL Apartments with carpet areas ranging from 202 to 281 Sq.ft. Carpet. The Project has total 418 of which 102 are currently available for sale.
Hdil Paradise City Sector 5 is being developed on a total land area of 102896 Sq.ft. out of which 46095 Sq.ft. i.e 45% is reserved for recreational purposes. Hdil Paradise City Sector 5 has 6 Wings / Towers Building No 1,Building No 2,Building No 3,Building No 4,Building No 5,Building No 6
| Project | Developer | Location | Possession |
| MAHA REARA No: |
P99000012466 |
| Project Type |
Others |
| RERA Project Status |
Ongoing |
| Architect |
Ajay Wade & Assocites |
| Funding Bank |
|
| Proposed Possession |
30 Jun 2019 |
| Revised Possession |
30 Jun 2019 |
| Extended Possession |
|
| Litigations |
No Litigations |
| Last Modified |
01 Sep 2017 |
| Last Retrived |
28 Jul 2025 |
Hdil Paradise City Sector 5 QR Code
Hdil Paradise City Sector 5
MahaRERA - P99000012466
| Type | Area |
| RESIDENTIAL | 24.34 Sq.mts. ( 262 Sq.ft. ) |
| RESIDENTIAL | 29.41 Sq.mts. ( 317 Sq.ft. ) |
| RESIDENTIAL | 29.86 Sq.mts. ( 321 Sq.ft. ) |
| RESIDENTIAL | 34.07 Sq.mts. ( 367 Sq.ft. ) |
| RESIDENTIAL | 18.72 Sq.mts. ( 202 Sq.ft. ) |
| RESIDENTIAL | 20.97 Sq.mts. ( 226 Sq.ft. ) |
| RESIDENTIAL | 23.3 Sq.mts. ( 251 Sq.ft. ) |
| RESIDENTIAL | 26.13 Sq.mts. ( 281 Sq.ft. ) |
Facilities & Amenities
Facilities, Amenities & Common areas details of Hdil Paradise City Sector 5last updated on 28 Jul 2025 as per information obtained from MARA RERA.
| Project Facilities & Amenities |
Available |
Details |
Aggregate area of recreational Open Space
|
|
Yet To Commence |
|
|
|
Na |
Electrical Meter Room, Sub-Station, Receiving Station
|
|
Yet To Commence |
|
|
|
Yet To Commence |
Fire Protection And Fire Safety
Requirements
|
|
Na |
Landscaping & Tree Planting
|
|
Yet To Commence |
|
|
|
Na |
Sewerage (Chamber, Lines, Septic Tank , STP)
|
|
Yet To Commence |
Solid Waste Management And Disposal
|
|
Yet To Commence |
|
|
|
Yet To Commence |
|
|
|
Yet To Commence |
Treatment And Disposal Of Sewage And Sullage Water
|
|
Yet To Commence |
Water Conservation, Rain water Harvesting
|
|
Yet To Commence |
|
|
|
Yet To Commence |
Buildings / Wings in Hdil Paradise City Sector 5
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Hdil Paradise City Sector 5 by Housing Development And Infrastructure Ltdlast updated on 28 Jul 2025 as per information obtained from MARA RERA.
Apartments Statistics
418
apartments in total
Saleable Area Statistics (Sq. ft.)
108105
Total
Total 418 apartments in project. 316 apartments booked. 75% apartments booked.
Total 108105 Sq.ft. saleable area. 81082 saleable area booked.
75% area booked.
| Wing | Proposed Date of Completion | Number of Slabs | Plinth | Basement's | Stilts | Podium's | Open Parkings | Closed Parkings |
| Building No 1 | Jan 1900 | 5 | 1 | 0 | 1 | 0 | 0 | 0 |
| Apartment Type | Carpet Area | Number of Apartments | Booked Apartments |
| RESIDENTIAL | 24.34 Sq.mts. ( 262 Sq.ft. ) | 24 | |
| RESIDENTIAL | 29.41 Sq.mts. ( 317 Sq.ft. ) | 6 | |
| RESIDENTIAL | 29.86 Sq.mts. ( 321 Sq.ft. ) | 24 | |
| RESIDENTIAL | 34.07 Sq.mts. ( 367 Sq.ft. ) | 3 | |
57 total apartments / 42 apartments booked. 73% apartments booked. |
| Work Description in Building Building No 1 | Completion |
| Basement (if any) | |
| Excavation | |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | |
| Plinth | |
| Podiums (if any) | |
| Sanitary Fittings within the flats / premises | |
| Slabs of Super Structure | |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | |
| Stilt Floor | |
| Wing | Proposed Date of Completion | Number of Slabs | Plinth | Basement's | Stilts | Podium's | Open Parkings | Closed Parkings |
| Building No 2 | Jan 1900 | 5 | 1 | 0 | 1 | 0 | 0 | 0 |
| Apartment Type | Carpet Area | Number of Apartments | Booked Apartments |
| RESIDENTIAL | 24.34 Sq.mts. ( 262 Sq.ft. ) | 24 | |
| RESIDENTIAL | 29.41 Sq.mts. ( 317 Sq.ft. ) | 6 | |
| RESIDENTIAL | 29.86 Sq.mts. ( 321 Sq.ft. ) | 24 | |
| RESIDENTIAL | 34.07 Sq.mts. ( 367 Sq.ft. ) | 3 | |
57 total apartments / 39 apartments booked. 68% apartments booked. |
| Work Description in Building Building No 2 | Completion |
| Basement (if any) | |
| Excavation | |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | |
| Plinth | |
| Podiums (if any) | |
| Sanitary Fittings within the flats / premises | |
| Slabs of Super Structure | |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | |
| Stilt Floor | |
| Wing | Proposed Date of Completion | Number of Slabs | Plinth | Basement's | Stilts | Podium's | Open Parkings | Closed Parkings |
| Building No 3 | Jan 1900 | 5 | 1 | 0 | 1 | 0 | 0 | 0 |
| Apartment Type | Carpet Area | Number of Apartments | Booked Apartments |
| RESIDENTIAL | 24.34 Sq.mts. ( 262 Sq.ft. ) | 24 | |
| RESIDENTIAL | 29.41 Sq.mts. ( 317 Sq.ft. ) | 6 | |
| RESIDENTIAL | 29.86 Sq.mts. ( 321 Sq.ft. ) | 24 | |
| RESIDENTIAL | 34.07 Sq.mts. ( 367 Sq.ft. ) | 3 | |
57 total apartments / 43 apartments booked. 75% apartments booked. |
| Work Description in Building Building No 3 | Completion |
| Basement (if any) | |
| Excavation | |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | |
| Plinth | |
| Podiums (if any) | |
| Sanitary Fittings within the flats / premises | |
| Slabs of Super Structure | |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | |
| Stilt Floor | |
| Wing | Proposed Date of Completion | Number of Slabs | Plinth | Basement's | Stilts | Podium's | Open Parkings | Closed Parkings |
| Building No 4 | Jan 1900 | 5 | 1 | 0 | 1 | 0 | 0 | 0 |
| Apartment Type | Carpet Area | Number of Apartments | Booked Apartments |
| RESIDENTIAL | 18.72 Sq.mts. ( 202 Sq.ft. ) | 40 | |
| RESIDENTIAL | 20.97 Sq.mts. ( 226 Sq.ft. ) | 20 | |
| RESIDENTIAL | 23.3 Sq.mts. ( 251 Sq.ft. ) | 15 | |
| RESIDENTIAL | 26.13 Sq.mts. ( 281 Sq.ft. ) | 20 | |
95 total apartments / 72 apartments booked. 75% apartments booked. |
| Work Description in Building Building No 4 | Completion |
| Basement (if any) | |
| Excavation | |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | |
| Plinth | |
| Podiums (if any) | |
| Sanitary Fittings within the flats / premises | |
| Slabs of Super Structure | |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | |
| Stilt Floor | |
| Wing | Proposed Date of Completion | Number of Slabs | Plinth | Basement's | Stilts | Podium's | Open Parkings | Closed Parkings |
| Building No 5 | Jan 1900 | 5 | 1 | 0 | 1 | 0 | 0 | 0 |
| Apartment Type | Carpet Area | Number of Apartments | Booked Apartments |
| RESIDENTIAL | 18.72 Sq.mts. ( 202 Sq.ft. ) | 32 | |
| RESIDENTIAL | 20.97 Sq.mts. ( 226 Sq.ft. ) | 16 | |
| RESIDENTIAL | 23.3 Sq.mts. ( 251 Sq.ft. ) | 12 | |
| RESIDENTIAL | 26.13 Sq.mts. ( 281 Sq.ft. ) | 16 | |
76 total apartments / 61 apartments booked. 80% apartments booked. |
| Work Description in Building Building No 5 | Completion |
| Basement (if any) | |
| Excavation | |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | |
| Plinth | |
| Podiums (if any) | |
| Sanitary Fittings within the flats / premises | |
| Slabs of Super Structure | |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | |
| Stilt Floor | |
| Wing | Proposed Date of Completion | Number of Slabs | Plinth | Basement's | Stilts | Podium's | Open Parkings | Closed Parkings |
| Building No 6 | Jan 1900 | 5 | 1 | 0 | 1 | 0 | 0 | 0 |
| Apartment Type | Carpet Area | Number of Apartments | Booked Apartments |
| RESIDENTIAL | 18.72 Sq.mts. ( 202 Sq.ft. ) | 32 | |
| RESIDENTIAL | 20.97 Sq.mts. ( 226 Sq.ft. ) | 16 | |
| RESIDENTIAL | 23.3 Sq.mts. ( 251 Sq.ft. ) | 12 | |
| RESIDENTIAL | 26.13 Sq.mts. ( 281 Sq.ft. ) | 16 | |
76 total apartments / 59 apartments booked. 77% apartments booked. |
| Work Description in Building Building No 6 | Completion |
| Basement (if any) | |
| Excavation | |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | |
| Plinth | |
| Podiums (if any) | |
| Sanitary Fittings within the flats / premises | |
| Slabs of Super Structure | |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | |
| Stilt Floor | |
Channel Partners Registered by Developer
Housing Development And Infrastructure Ltd
for Project
Hdil Paradise City Sector 5
last updated on
28 Jul 2025 as per information obtained from MARA RERA.
| Name |
Company |
Location |
Mobile |
Designation |